Parsed from the official text as a reading aid - zone pay, group definitions and footnotes in the full text below modify specific classifications. Identifier prefixes: union-agreement rates carry the local's id, SU marks DOL survey rates (how to read a determination).
Full official text of CA20260021 rev 2
"General Decision Number: CA20260021 05/18/2026
State: California
Construction Types: Heavy and Highway
Counties: California Counties of
Tulare
Includes Dredging Projects (does not include self-propelled hopper dredge work); Excludes water well drilling
Modification Number Publication Date
1 01/09/2026
2 05/18/2026
ASBE0016-006 05/01/2025
Rates Fringes
ASBESTOS REMOVAL WORKER/HAZARDOUS MATERIAL HANDLER
(INCLUDES PREPARATION, WETTING, STRIPPING, REMOVAL,
SCRAPPING, VACUUMING, BAGGING AND DISPOSING OF ALL
INSULATION MATERIALS FROM MECHANICAL SYSTEMS,
WHETHER THEY CONTAIN ASBESTOS OR NOT)...............$ 35.31 12.75
----------------------------------------------------------------
ASBE0016-010 01/01/2024
Rates Fringes
ASBESTOS WORKERS/INSULATOR (INCLUDES THE
APPLICATION OF ALL INSULATING MATERIALS,
PROTECTIVE COVERINGS, COATINGS, AND FINISHES TO
ALL TYPES OF MECHANICAL SYSTEMS)....................$ 64.56 25.07
----------------------------------------------------------------
BOIL0549-004 01/01/2021
Rates Fringes
BOILERMAKER.........................................$ 45.60 38.99
----------------------------------------------------------------
BRCA0003-001 08/01/2024
Rates Fringes
MARBLE FINISHER.....................................$ 42.06 19.80
----------------------------------------------------------------
BRCA0003-016 04/01/2024
Rates Fringes
TILE LAYER..........................................$ 50.28 22.05
TILE FINISHER.......................................$ 32.68 18.32
----------------------------------------------------------------
BRCA0003-017 07/01/2024
Rates Fringes
TERRAZZO WORKER/SETTER..............................$ 60.58 29.79
TERRAZZO FINISHER...................................$ 44.93 20.98
----------------------------------------------------------------
BRCA0004-005 05/01/2024
Rates Fringes
BRICKLAYER; MARBLE SETTER *THE WAGE SCALE FOR
PREVAILING WAGE PROJECTS PERFORMED IN BLYTHE, CHINA
LAKE, DEATH VALLEY, FORT IRWIN, TWENTY-NINE PALMS,
NEEDLES AND 1-15 CORRIDOR (BARSTOW TO THE NEVADA
STATE LINE) WILL BE THREE DOLLARS ($3.00) ABOVE THE
STANDARD SAN BERNARDINO/RIVERSIDE COUNTY HOURLY
WAGE RATE...........................................$ 45.53 20.29
----------------------------------------------------------------
CARP0034-002 07/01/2021
Rates Fringes
DIVER: MANIFOLD OPERATOR (STANDBY) DEPTH PAY
(SURFACE DIVING): 050 TO 100 FT $2.00 PER
FOOT 101 TO 150 FT $3.00 PER FOOT 151 TO
220 FT $4.00 PER FOOT 221 FT.-DEEPER $5.00
PER FOOT SATURATION DIVING: THE STANDBY RATE
SHALL APPLY UNTIL SATURATION STARTS. THE
SATURATION DIVING RATE APPLIES WHEN DIVERS ARE
UNDER PRESSURE CONTINUOUSLY UNTIL WORK TASK AND
DECOMPRESSION ARE COMPLETE. THE DIVER RATE SHALL BE
PAID FOR ALL SATURATION HOURS. DIVING IN
ENCLOSURES: WHERE IT IS NECESSARY FOR DIVERS TO
ENTER PIPES OR TUNNELS, OR OTHER ENCLOSURES WHERE
THERE IS NO VERTICAL ASCENT, THE FOLLOWING PREMIUM
SHALL BE PAID: DISTANCE TRAVELED FROM ENTRANCE 26
FEET TO 300 FEET: $1.00 PER FOOT. WHEN IT IS
NECESSARY FOR A DIVER TO ENTER ANY PIPE, TUNNEL OR
OTHER ENCLOSURE LESS THAN 48"" IN HEIGHT, THE
PREMIUM WILL BE $1.00 PER FOOT. WORK IN
COMBINATION OF CLASSIFICATIONS: EMPLOYEES WORKING
IN ANY COMBINATION OF CLASSIFICATIONS WITHIN THE
DIVING CREW (EXCEPT DIVE SUPERVISOR) IN A SHIFT ARE
PAID IN THE CLASSIFICATION WITH THE HIGHEST RATE
FOR THAT SHIFT......................................$ 59.51 34.69
DIVER: MANIFOLD OPERATOR (MIXED GAS) DEPTH PAY
(SURFACE DIVING): 050 TO 100 FT $2.00 PER
FOOT 101 TO 150 FT $3.00 PER FOOT 151 TO
220 FT $4.00 PER FOOT 221 FT.-DEEPER $5.00
PER FOOT SATURATION DIVING: THE STANDBY RATE
SHALL APPLY UNTIL SATURATION STARTS. THE
SATURATION DIVING RATE APPLIES WHEN DIVERS ARE
UNDER PRESSURE CONTINUOUSLY UNTIL WORK TASK AND
DECOMPRESSION ARE COMPLETE. THE DIVER RATE SHALL BE
PAID FOR ALL SATURATION HOURS. DIVING IN
ENCLOSURES: WHERE IT IS NECESSARY FOR DIVERS TO
ENTER PIPES OR TUNNELS, OR OTHER ENCLOSURES WHERE
THERE IS NO VERTICAL ASCENT, THE FOLLOWING PREMIUM
SHALL BE PAID: DISTANCE TRAVELED FROM ENTRANCE 26
FEET TO 300 FEET: $1.00 PER FOOT. WHEN IT IS
NECESSARY FOR A DIVER TO ENTER ANY PIPE, TUNNEL OR
OTHER ENCLOSURE LESS THAN 48"" IN HEIGHT, THE
PREMIUM WILL BE $1.00 PER FOOT. WORK IN
COMBINATION OF CLASSIFICATIONS: EMPLOYEES WORKING
IN ANY COMBINATION OF CLASSIFICATIONS WITHIN THE
DIVING CREW (EXCEPT DIVE SUPERVISOR) IN A SHIFT ARE
PAID IN THE CLASSIFICATION WITH THE HIGHEST RATE
FOR THAT SHIFT......................................$ 64.51 34.69
DIVER: DIVER WET DEPTH PAY (SURFACE DIVING):
050 TO 100 FT $2.00 PER FOOT 101 TO 150 FT
$3.00 PER FOOT 151 TO 220 FT $4.00 PER FOOT
221 FT.-DEEPER $5.00 PER FOOT SATURATION
DIVING: THE STANDBY RATE SHALL APPLY UNTIL
SATURATION STARTS. THE SATURATION DIVING RATE
APPLIES WHEN DIVERS ARE UNDER PRESSURE CONTINUOUSLY
UNTIL WORK TASK AND DECOMPRESSION ARE COMPLETE. THE
DIVER RATE SHALL BE PAID FOR ALL SATURATION HOURS.
DIVING IN ENCLOSURES: WHERE IT IS NECESSARY FOR
DIVERS TO ENTER PIPES OR TUNNELS, OR OTHER
ENCLOSURES WHERE THERE IS NO VERTICAL ASCENT, THE
FOLLOWING PREMIUM SHALL BE PAID: DISTANCE TRAVELED
FROM ENTRANCE 26 FEET TO 300 FEET: $1.00 PER FOOT.
WHEN IT IS NECESSARY FOR A DIVER TO ENTER ANY
PIPE, TUNNEL OR OTHER ENCLOSURE LESS THAN 48"" IN
HEIGHT, THE PREMIUM WILL BE $1.00 PER FOOT. WORK
IN COMBINATION OF CLASSIFICATIONS: EMPLOYEES
WORKING IN ANY COMBINATION OF CLASSIFICATIONS
WITHIN THE DIVING CREW (EXCEPT DIVE SUPERVISOR) IN
A SHIFT ARE PAID IN THE CLASSIFICATION WITH THE
HIGHEST RATE FOR THAT SHIFT.........................$ 103.62 34.69
DIVER: DIVER TENDER DEPTH PAY (SURFACE DIVING):
050 TO 100 FT $2.00 PER FOOT 101 TO 150 FT
$3.00 PER FOOT 151 TO 220 FT $4.00 PER
FOOT 221 FT.-DEEPER $5.00 PER FOOT SATURATION
DIVING: THE STANDBY RATE SHALL APPLY UNTIL
SATURATION STARTS. THE SATURATION DIVING RATE
APPLIES WHEN DIVERS ARE UNDER PRESSURE CONTINUOUSLY
UNTIL WORK TASK AND DECOMPRESSION ARE COMPLETE. THE
DIVER RATE SHALL BE PAID FOR ALL SATURATION HOURS.
DIVING IN ENCLOSURES: WHERE IT IS NECESSARY FOR
DIVERS TO ENTER PIPES OR TUNNELS, OR OTHER
ENCLOSURES WHERE THERE IS NO VERTICAL ASCENT, THE
FOLLOWING PREMIUM SHALL BE PAID: DISTANCE TRAVELED
FROM ENTRANCE 26 FEET TO 300 FEET: $1.00 PER FOOT.
WHEN IT IS NECESSARY FOR A DIVER TO ENTER ANY
PIPE, TUNNEL OR OTHER ENCLOSURE LESS THAN 48"" IN
HEIGHT, THE PREMIUM WILL BE $1.00 PER FOOT. WORK
IN COMBINATION OF CLASSIFICATIONS: EMPLOYEES
WORKING IN ANY COMBINATION OF CLASSIFICATIONS
WITHIN THE DIVING CREW (EXCEPT DIVE SUPERVISOR) IN
A SHIFT ARE PAID IN THE CLASSIFICATION WITH THE
HIGHEST RATE FOR THAT SHIFT.........................$ 59.51 34.69
DIVER: DIVER STANDBY DEPTH PAY (SURFACE DIVING):
050 TO 100 FT $2.00 PER FOOT 101 TO 150
FT $3.00 PER FOOT 151 TO 220 FT $4.00 PER
FOOT 221 FT.-DEEPER $5.00 PER FOOT SATURATION
DIVING: THE STANDBY RATE SHALL APPLY UNTIL
SATURATION STARTS. THE SATURATION DIVING RATE
APPLIES WHEN DIVERS ARE UNDER PRESSURE CONTINUOUSLY
UNTIL WORK TASK AND DECOMPRESSION ARE COMPLETE. THE
DIVER RATE SHALL BE PAID FOR ALL SATURATION HOURS.
DIVING IN ENCLOSURES: WHERE IT IS NECESSARY FOR
DIVERS TO ENTER PIPES OR TUNNELS, OR OTHER
ENCLOSURES WHERE THERE IS NO VERTICAL ASCENT, THE
FOLLOWING PREMIUM SHALL BE PAID: DISTANCE TRAVELED
FROM ENTRANCE 26 FEET TO 300 FEET: $1.00 PER FOOT.
WHEN IT IS NECESSARY FOR A DIVER TO ENTER ANY
PIPE, TUNNEL OR OTHER ENCLOSURE LESS THAN 48"" IN
HEIGHT, THE PREMIUM WILL BE $1.00 PER FOOT. WORK
IN COMBINATION OF CLASSIFICATIONS: EMPLOYEES
WORKING IN ANY COMBINATION OF CLASSIFICATIONS
WITHIN THE DIVING CREW (EXCEPT DIVE SUPERVISOR) IN
A SHIFT ARE PAID IN THE CLASSIFICATION WITH THE
HIGHEST RATE FOR THAT SHIFT.........................$ 60.51 34.69
DIVER: ASSISTANT TENDER, ROV TENDER/TECHNICIAN
DEPTH PAY (SURFACE DIVING): 050 TO 100 FT
$2.00 PER FOOT 101 TO 150 FT $3.00 PER FOOT
151 TO 220 FT $4.00 PER FOOT 221 FT.-DEEPER
$5.00 PER FOOT SATURATION DIVING: THE STANDBY
RATE SHALL APPLY UNTIL SATURATION STARTS. THE
SATURATION DIVING RATE APPLIES WHEN DIVERS ARE
UNDER PRESSURE CONTINUOUSLY UNTIL WORK TASK AND
DECOMPRESSION ARE COMPLETE. THE DIVER RATE SHALL BE
PAID FOR ALL SATURATION HOURS. DIVING IN
ENCLOSURES: WHERE IT IS NECESSARY FOR DIVERS TO
ENTER PIPES OR TUNNELS, OR OTHER ENCLOSURES WHERE
THERE IS NO VERTICAL ASCENT, THE FOLLOWING PREMIUM
SHALL BE PAID: DISTANCE TRAVELED FROM ENTRANCE 26
FEET TO 300 FEET: $1.00 PER FOOT. WHEN IT IS
NECESSARY FOR A DIVER TO ENTER ANY PIPE, TUNNEL OR
OTHER ENCLOSURE LESS THAN 48"" IN HEIGHT, THE
PREMIUM WILL BE $1.00 PER FOOT. WORK IN
COMBINATION OF CLASSIFICATIONS: EMPLOYEES WORKING
IN ANY COMBINATION OF CLASSIFICATIONS WITHIN THE
DIVING CREW (EXCEPT DIVE SUPERVISOR) IN A SHIFT ARE
PAID IN THE CLASSIFICATION WITH THE HIGHEST RATE
FOR THAT SHIFT......................................$ 54.10 34.69
----------------------------------------------------------------
CARP0034-003 07/01/2021
Rates Fringes
PILEDRIVER..........................................$ 54.10 34.69
----------------------------------------------------------------
CARP1109-002 07/01/2020
Rates Fringes
CARPENTERS: MILLWRIGHT..............................$ 47.92 32.41
CARPENTERS: JOURNEYMAN CARPENTER....................$ 45.42 30.82
CARPENTERS: BRIDGE BUILDER/HIGHWAY CARPENTER........$ 52.65 30.82
CARPENTERS (HARDWOOD FLOORLAYER, SHINGLER, POWER
SAW OPERATOR, STEEL SCAFFOLD & STEEL SHORING
ERECTOR, SAW FILER).................................$ 45.57 30.82
----------------------------------------------------------------
ELEC0100-001 09/01/2025
Rates Fringes
ELECTRICIAN.........................................$ 50.00 30.15
----------------------------------------------------------------
ELEC1245-001 01/01/2025
Rates Fringes
LINE CONSTRUCTION: (3) GROUNDMAN HOLIDAYS: NEW
YEAR'S DAY, M.L. KING DAY, MEMORIAL DAY,
INDEPENDENCE DAY, LABOR DAY, VETERANS DAY,
THANKSGIVING DAY AND DAY AFTER THANKSGIVING,
CHRISTMAS DAY.......................................$ 40.76 21.76
LINE CONSTRUCTION: (2) EQUIPMENT SPECIALIST
(OPERATES CRAWLER TRACTORS, COMMERCIAL MOTOR
VEHICLES, BACKHOES, TRENCHERS, CRANES (50 TONS AND
BELOW), OVERHEAD & UNDERGROUND DISTRIBUTION LINE
EQUIPMENT) HOLIDAYS: NEW YEAR'S DAY, M.L. KING
DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY,
VETERANS DAY, THANKSGIVING DAY AND DAY AFTER
THANKSGIVING, CHRISTMAS DAY.........................$ 53.30 22.26
LINE CONSTRUCTION: (1) LINEMAN; CABLE SPLICER
HOLIDAYS: NEW YEAR'S DAY, M.L. KING DAY, MEMORIAL
DAY, INDEPENDENCE DAY, LABOR DAY, VETERANS DAY,
THANKSGIVING DAY AND DAY AFTER THANKSGIVING,
CHRISTMAS DAY.......................................$ 70.16 24.71
----------------------------------------------------------------
ENGI0003-006 06/29/2020
Rates Fringes
OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1::
GROUP 3 (Truck crane oiler).........................$ 45.12 31.15
OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1::
GROUP 3 (Oiler).....................................$ 42.89 31.15
OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1::
GROUP 3 (Lifting devices)...........................$ 49.14 31.15
OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1::
GROUP 2 (Truck crane oiler).........................$ 45.41 31.15
OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1::
GROUP 2 (Oiler).....................................$ 43.11 31.15
OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1::
GROUP 2 (Lifting devices)...........................$ 50.82 31.15
OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1::
GROUP 1 (Truck crane oiler).........................$ 45.66 31.15
OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1::
GROUP 1 (Oiler).....................................$ 43.38 31.15
OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1::
GROUP 1 (Lifting devices)...........................$ 52.64 31.15
OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1:
LIFTING DEVICES: GROUP 6: DECKHAND; FIRE TENDER
FOOTNOTE: WORK SUSPENDED BY ROPES OR CABLES, OR
WORK ON A YO-YO CAT: $.60 PER HOUR ADDITIONAL.......$ 42.50 31.15
OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1:
LIFTING DEVICES: GROUP 5: DECK ENGINEER
FOOTNOTE: WORK SUSPENDED BY ROPES OR CABLES, OR
WORK ON A YO-YO CAT: $.60 PER HOUR ADDITIONAL. ..$ 44.73 31.15
OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1:
LIFTING DEVICES: GROUP 4: ASSISTANT OPERATOR IN
LIEU OF ASSISTANT TO ENGINEER; FORKLIFT, 10 TONS
AND OVER; HEAVY-DUTY REPAIRPERSON/WELDER FOOTNOTE:
WORK SUSPENDED BY ROPES OR CABLES, OR WORK ON A
YO-YO CAT: $.60 PER HOUR ADDITIONAL. ..........$ 47.47 31.15
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND
WORK - AREA 1:: UNDERGROUND: (GROUP 5)..............$ 58.09 32.53
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND
WORK - AREA 1:: UNDERGROUND: (GROUP 4)..............$ 59.23 32.53
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND
WORK - AREA 1:: UNDERGROUND: (GROUP 3)..............$ 60.37 32.53
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND
WORK - AREA 1:: UNDERGROUND: (GROUP 2)..............$ 61.70 32.53
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND
WORK - AREA 1:: UNDERGROUND: (GROUP 1-A)............$ 65.43 32.53
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND
WORK - AREA 1:: UNDERGROUND: (GROUP 1)..............$ 62.96 32.53
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND
WORK - AREA 1:: SHAFTS, STOPES, RAISES: (GROUP 5)...$ 58.19 32.53
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND
WORK - AREA 1:: SHAFTS, STOPES, RAISES: (GROUP 4)...$ 59.33 32.53
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND
WORK - AREA 1:: SHAFTS, STOPES, RAISES: (GROUP 3)...$ 60.47 32.53
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND
WORK - AREA 1:: SHAFTS, STOPES, RAISES: (GROUP 2)...$ 61.80 32.53
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND
WORK - AREA 1:: SHAFTS, STOPES, RAISES: (GROUP 1-A).$ 65.53 32.53
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND
WORK - AREA 1:: SHAFTS, STOPES, RAISES: (GROUP 1)...$ 63.06 32.53
OPERATOR: POWER EQUIPMENT, STEEL ERECTION - AREA
1:CRANE: GROUP 5: BOOM CAT FOOTNOTE: WORK
SUSPENDED BY ROPES OR CABLES, OR WORK ON A YO-YO
CAT: $.60 PER HOUR ADDITIONAL.......................$ 62.24 32.53
OPERATOR: POWER EQUIPMENT, STEEL ERECTION - AREA
1:: GROUP 3 (Hydraulic).............................$ 60.61 32.53
OPERATOR: POWER EQUIPMENT, STEEL ERECTION - AREA
1:: GROUP 3 (Cranes)................................$ 65.56 32.53
OPERATOR: POWER EQUIPMENT, STEEL ERECTION - AREA
1: CRANES: GROUP 2: CRANE OVER 45 TONS TO 100 TONS;
DERRICK UNDER 100 TONS; SELF-PROPELLED BOOM-TYPE
LIFTING DEVICE OVER 45 TONS TO 100 TONS; TOWER
CRANE FOOTNOTE: WORK SUSPENDED BY ROPES OR
CABLES, OR WORK ON A YO-YO CAT: $.60 PER HOUR
ADDITIONAL..........................................$ 67.04 32.53
OPERATOR: POWER EQUIPMENT, STEEL ERECTION - AREA
1: CRANES: GROUP 1: CRANE OVER 100 TONS; DERRICK
OVER 100 TONS; SELF- PROPELLED BOOM-TYPE LIFTING
DEVICE OVER 100 TONS FOOTNOTE: WORK SUSPENDED BY
ROPES OR CABLES, OR WORK ON A YO-YO CAT: $.60 PER
HOUR ADDITIONAL.....................................$ 68.81 32.53
OPERATOR: POWER EQUIPMENT, STEEL ERECTION - AREA
1: CRANE: GROUP 4: CHICAGO BOOM; FORKLIFT, 10 TONS
AND OVER; HEAVY-DUTY REPAIR PERSON/WELDER GROUP
5: BOOM CAT FOOTNOTE: WORK SUSPENDED BY ROPES OR
CABLES, OR WORK ON A YO-YO CAT: $.60 PER HOUR
ADDITIONAL..........................................$ 63.54 32.53
OPERATOR: POWER EQUIPMENT, CRANES AND ATTACHMENTS
- AREA 1:CRANES GROUP 2: CLAMSHELL AND DRAGLINE
OVER 1 CU. YD. UP TO AND INCLUDING 7 CU. YDS.;
CRANE, OVER 45 TONS UP TO AND INCLUDING 100 TONS;
DERRICK BARGE, 100 TONS AND UNDER; SELF-PROPELLED
BOOM-TYPE LIFTING DEVICE, OVER 45 TONS; TOWER CRANE
FOOTNOTE: WORK SUSPENDED BY ROPES OR CABLES, OR
WORK ON A YO-YO CAT: $.60 PER HOUR ADDITIONAL.......$ 66.08 32.53
OPERATOR: POWER EQUIPMENT, CRANES AND ATTACHMENTS
- AREA 1: CRANES GROUP 3: CLAMSHELL AND DRAGLINE
UP TO AND INCLUDING 1 CU. YD.; CRANES 45 TONS AND
UNDER; SELF-PROPELLED BOOM-TYPE LIFTING DEVICE 45
TONS AND UNDER; FOOTNOTE: WORK SUSPENDED BY ROPES
OR CABLES, OR WORK ON A YO-YO CAT: $.60 PER HOUR
ADDITIONAL..........................................$ 64.34 32.53
OPERATOR: POWER EQUIPMENT, CRANES AND ATTACHMENTS
- AREA 1: CRANES GROUP 4: BOOM TRUCK OR DUAL
PURPOSE A-FRAME TRUCK, NON-ROTATING OVER 15 TONS;
TRUCK-MOUNTED ROTATING TELESCOPIC BOOM TYPE LIFTING
DEVICE, MANITEX OR SIMILAR (BOOM TRUCK) OVER 15
TONS; TRUCK-MOUNTED ROTATING TELESCOPIC BOOM TYPE
LIFTING DEVICE, MANITEX OR SIMILAR (BOOM TRUCK) -
UNDER 15 TONS; FOOTNOTE: WORK SUSPENDED BY
ROPES OR CABLES, OR WORK ON A YO-YO CAT: $.60 PER
HOUR ADDITIONAL.....................................$ 61.30 32.53
OPERATOR: POWER EQUIPMENT, CRANES AND ATTACHMENTS
- AREA 1: CRANES GROUP 1: CLAMSHELL AND DRAGLINE
OVER 7 CU. YDS.; CRANE, OVER 100 TONS; DERRICK,
OVER 100 TONS; DERRICK BARGE PEDESTAL-MOUNTED, OVER
100 TONS; SELF-PROPELLED BOOM-TYPE LIFTING DEVICE,
OVER 100 TONS FOOTNOTE: WORK SUSPENDED BY ROPES
OR CABLES, OR WORK ON A YO-YO CAT: $.60 PER HOUR
ADDITIONAL..........................................$ 68.59 32.53
OPERATOR: POWER EQUIPMENT, AREA 1: GROUP 8-A
ELEVATOR OPERATOR; SKIDSTEER LOADER-BOBCAT 743
SERIES OR SMALLER, AND SIMILAR (WITHOUT
ATTACHMENTS); MINI EXCAVATOR UNDER 25 H.P.
(BACKHOE-TRENCHER); TUB GRINDER WOOD CHIPPER
FOOTNOTE: WORK SUSPENDED BY ROPES OR CABLES,
OR WORK ON A YO-YO CAT: $.60 PER HOUR ADDITIONAL....$ 55.49 32.53
OPERATOR: POWER EQUIPMENT, AREA 1: GROUP 8 BIT
SHARPENER; BOILER TENDER; BOX OPERATOR;
BRAKEPERSON; COMBINATION MIXER AND COMPRESSOR
(SHOTCRETE/GUNITE); COMPRESSOR OPERATOR; DECKHAND;
FIRE TENDER; FORKLIFT (UNDER 20 FT.); GENERATOR;
GUNITE/SHOTCRETE EQUIPMENT OPERATOR; HYDRAULIC
MONITOR; KEN SEAL MACHINE (OR SIMILAR);
MIXERMOBILE; OILER; PUMP OPERATOR; REFRIGERATION
PLANT; RESERVOIR-DEBRIS TUG (SELF- PROPELLED
FLOATING); ROSS CARRIER (CONSTRUCTION SITE);
ROTOMIST OPERATOR; SELF-PROPELLED TAPE MACHINE;
SHUTTLECAR; SELF-PROPELLED POWER SWEEPER OPERATOR
(INCLUDES VACUUM SWEEPER); SLUSHER OPERATOR;
SURFACE HEATER; SWITCHPERSON; TAR POT FIRETENDER;
TUGGER HOIST, SINGLE DRUM; VACUUM COOLING PLANT;
WELDING MACHINE (POWERED OTHER THAN BY ELECTRICITY)
FOOTNOTE: WORK SUSPENDED BY ROPES OR CABLES, OR
WORK ON A YO-YO CAT: $.60 PER HOUR ADDITIONAL.......$ 57.70 32.53
OPERATOR: POWER EQUIPMENT, AREA 1: GROUP 7 BALLAST
REGULATOR; BOOM TRUCK OR DUAL-PURPOSE A-FRAME
TRUCK, NON-ROTATING - UNDER 15 TONS; CARY LIFT OR
SIMILAR; COMBINATION SLURRY MIXER AND/OR CLEANER;
DRILLING EQUIPMENT, 20 FT. AND UNDER M.R.C.;
FIRETENDER (HOT PLANT); GROUTING MACHINE OPERATOR;
HIGHLINE CABLEWAY SIGNALPERSON; STATIONARY BELT
LOADER (KOLMAN OR SIMILAR); LIFT SLAB MACHINE
(VAGTBORG AND SIMILAR TYPES); MAGINNES INTERNAL
FULL SLAB VIBRATOR; MATERIAL HOIST (1 DRUM);
MECHANICAL TRENCH SHIELD; PAVEMENT BREAKER WITH OR
WITHOUT COMPRESSOR COMBINATION); PIPE CLEANING
MACHINE (TRACTOR PROPELLED AND SUPPORTED); POST
DRIVER; ROLLER (EXCEPT ASPHALT); CHIP SEAL;
SELF-PROPELLED AUTOMATICALLY APPLIED CONCRETE
CURING MAHCINE (ON STREETS, HIGHWAYS, AIRPORTS AND
CANALS); SELF-PROPELLED COMPACTOR (WITHOUT DOZER);
SIGNALPERSON; SLIP-FORM PUMPS (LIFTING DEVICE FOR
CONCRETE FORMS); TIE SPACER; TOWER MOBILE;
TRENCHING MACHINE, MAXIMUM DIGGING CAPACITY UP TO
AND INCLUDING 5 FT. DEPTH; TRUCK- TYPE LOADER
FOOTNOTE: WORK SUSPENDED BY ROPES OR CABLES, OR
WORK ON A YO-YO CAT: $.60 PER HOUR ADDITIONAL.......$ 58.84 32.53
OPERATOR: POWER EQUIPMENT, AREA 1: GROUP 6
ARMOR-COATER (OR SIMILAR); BALLAST JACK TAMPER;
BOOM- TYPE BACKFILLING MACHINE; ASSISTANT PLANT
ENGINEER; BRIDGE AND/OR GANTRY CRANE; CHEMICAL
GROUTING MACHINE, TRUCK-MOUNTED; CHIP SPREADING
MACHINE OPERATOR; CONCRETE SAW (SELF-PROPELLED UNIT
ON STREETS, HIGHWAYS, AIRPORTS AND CANALS); DECK
ENGINEER; DRILLING EQUIPMENT TEXOMA 600, HUGHES 200
SERIES OR SIMILAR UP TO AND INCLUDING 30 FT.
M.R.C.; DRILL DOCTOR; HELICOPTER RADIO OPERATOR;
HYDRO-HAMMER OR SIMILAR; LINE MASTER; SKIDSTEER
LOADER, BOBCAT LARGER THAN 743 SERIES OR SIMILAR
(WITH ATTACHMENTS); LOCOMOTIVE; LULL HI-LIFT OR
SIMILAR; OILER, TRUCK MOUNTED EQUIPMENT; PAVEMENT
BREAKER, TRUCK-MOUNTED, WITH COMPRESSOR
COMBINATION; PAVING FABRIC INSTALLATION AND/OR
LAYING MACHINE; PIPE BENDING MACHINE (PIPELINES
ONLY); PIPE WRAPPING MACHINE (TRACTOR PROPELLED AND
SUPPORTED); SCREED (EXCEPT ASPHALTIC CONCRETE
PAVING); SELF- PROPELLED PIPELINE WRAPPING MACHINE;
TRACTOR; SELF-LOADING CHIPPER; CONCRETE BARRIER
MOVING MACHINE FOOTNOTE: WORK SUSPENDED BY ROPES
OR CABLES, OR WORK ON A YO-YO CAT: $.60 PER HOUR
ADDITIONAL..........................................$ 59.98 32.53
OPERATOR: POWER EQUIPMENT, AREA 1: GROUP 5
CAST-IN-PLACE PIPE LAYING MACHINE; COMBINATION
SLUSHER AND MOTOR OPERATOR; CONCRETE CONVEYOR OR
CONCRETE PUMP, TRUCK OR EQUIPMENT MOUNTED; CONCRETE
CONVEYOR, BUILDING SITE; CONCRETE PUMP OR PUMPCRETE
GUN; DRILLING EQUIPMENT, WATSON 2000, TEXOMA 700 OR
SIMILAR; DRILLING AND BORING MACHINERY, HORIZONTAL
(NOT TO APPLY TO WATERLINERS, WAGON DRILLS OR
JACKHAMMERS); CONCRETE MIXER/ALL; PERSON AND/OR
MATERIAL HOIST; MECHANICAL FINISHERS (CONCRETE)
(CLARY, JOHNSON, BIDWELL BRIDGE DECK OR SIMILAR
TYPES); MECHANICAL BURM, CURB AND/OR CURB AND
GUTTER MACHINE, CONCRETE OR ASPHALT); MINE OR SHAFT
HOIST; PORTABLE CRUSHER; POWER JUMBO OPERATOR
(SETTING SLIP-FORMS, ETC., IN TUNNELS); SCREED
(AUTOMATIC OR MANUAL); SELF-PROPELLED COMPACTOR
WITH DOZER; TRACTOR WITH BOOM D6 OR SMALLER;
TRENCHING MACHINE, MAXIMUM DIGGING CAPACITY OVER 5
FT. DEPTH; VERMEER T-600B ROCK CUTTER OR SIMILAR
FOOTNOTE: WORK SUSPENDED BY ROPES OR CABLES, OR
WORK ON A YO-YO CAT: $.60 PER HOUR ADDITIONAL.......$ 61.30 32.53
OPERATOR: POWER EQUIPMENT, AREA 1: GROUP 4 ASPHALT
PLANT ENGINEER/BOX PERSON; CHICAGO BOOM;
COMBINATION BACKHOE AND LOADER UP TO AND INCLUDING
3/4 CU. YD.; CONCRETE BATCH PLANT (WET OR DRY);
DOZER AND/OR PUSH CAT; PULL- TYPE ELEVATING LOADER;
GRADESETTER, GRADE CHECKER (GPS, MECHANICAL OR
OTHERWISE); GROOVING AND GRINDING MACHINE; HEADING
SHIELD OPERATOR; HEAVY-DUTY DRILLING EQUIPMENT,
HUGHES, LDH, WATSON 3000 OR SIMILAR; HEAVY-DUTY
REPAIRPERSON AND/OR WELDER; LIME SPREADER; LOADER
UNDER 4 CU. YDS.; LUBRICATION AND SERVICE ENGINEER
(MOBILE AND GREASE RACK); MECHANICAL FINISHERS OR
SPREADER MACHINE (ASPHALT, BARBER-GREENE AND
SIMILAR); MILLER FORMLESS M-9000 SLOPE PAVER OR
SIMILAR; PORTABLE CRUSHING AND SCREENING PLANTS;
POWER BLADE SUPPORT; ROLLER OPERATOR, ASPHALT;
RUBBER-TIRED SCRAPER, SELF-LOADING (PADDLE-WHEELS,
ETC.); RUBBER- TIRED EARTHMOVING EQUIPMENT
(SCRAPERS); SLIP FORM PAVER (CONCRETE); SMALL
TRACTOR WITH DRAG; SOIL STABILIZER (P & H OR
EQUAL); SPIDER PLOW AND SPIDER PULLER; TUBEX PILE
RIG; UNLICENSED CONSTUCTION WORK BOAT OPERATOR, ON
SITE; TIMBER SKIDDER; TRACK LOADER UP TO 4 YDS.;
TRACTOR-DRAWN SCRAPER; TRACTOR, COMPRESSOR DRILL
COMBINATION; WELDER; WOODS-MIXER (AND OTHER SIMILAR
PUGMILL EQUIPMENT) FOOTNOTE: WORK SUSPENDED BY
ROPES OR CABLES, OR WORK ON A YO-YO CAT: $.60 PER
HOUR ADDITIONAL.....................................$ 62.57 32.53
OPERATOR: POWER EQUIPMENT, AREA 1: GROUP 3 ASPHALT
MILLING MACHINE; CABLE BACKHOE; COMBINATION BACKHOE
AND LOADER OVER 3/4 CU. YDS.; CONTINUOUS FLIGHT TIE
BACK MACHINE ASSISTANT TO ENGINEER OR MECHANIC;
CRANE MOUNTED CONTINUOUS FLIGHT TIE BACK MACHINE,
TONNAGE TO APPLY; CRANE MOUNTED DRILL ATTACHMENT,
TONNAGE TO APPLY; DOZER, SLOPE BRD; GRADALL;
HYDRAULIC EXCAVATOR, UP TO 3 1/2 CU. YDS.; LOADER 4
CU. YDS. AND OVER; LONG REACH EXCAVATOR; MULTIPLE
ENGINE SCRAPER (WHEN USED AS PUSH PULL); POWER
SHOVELS, UP TO AND INCLUDING 1 CU. YD.; PRE-STRESS
WIRE WRAPPING MACHINE; SIDE BOOM CAT, 572 OR
LARGER; TRACK LOADER 4 CU. YDS. AND OVER; WHEEL
EXCAVATOR (UP TO AND INCLUDING 750 CU. YDS. PER
HOUR) FOOTNOTE: WORK SUSPENDED BY ROPES OR CABLES,
OR WORK ON A YO-YO CAT: $.60 PER HOUR ADDITIONAL....$ 63.95 32.53
OPERATOR: POWER EQUIPMENT, AREA 1: GROUP 2
HIGHLINE CABLEWAY; HYDRAULIC EXCAVATOR, 3-1/2 CU.
YDS. UP TO 7 CU. YDS.; LICENSED CONSTRUCTION WORK
BOAT OPERATOR, ON SITE; POWER BLADE OPERATOR
(FINISH); POWER SHOVELS, OVER 1 CU. YD. UP TO AND
INCLUDING 7 CU. YDS. M.R.C. FOOTNOTE: WORK
SUSPENDED BY ROPES OR CABLES, OR WORK ON A YO-YO
CAT: $.60 PER HOUR ADDITIONAL.......................$ 65.43 32.53
OPERATOR: POWER EQUIPMENT, AREA 1: GROUP 1
OPERATOR OF HELICOPTER (WHEN USED IN ERECTION
WORK); HYDRAULIC EXCAVATOR, 7 CU. YDS. AND OVER;
POWER SHOVELS, OVER 7 CU. YDS. FOOTNOTE: WORK
SUSPENDED BY ROPES OR CABLES, OR WORK ON A YO-YO
CAT: $.60 PER HOUR ADDITIONAL.......................$ 66.96 32.53
----------------------------------------------------------------
ENGI0003-006 06/30/2025
Rates Fringes
OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1::
GROUP 3 (Truck crane oiler).........................$ 45.12 31.15
OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1::
GROUP 3 (Oiler).....................................$ 42.89 31.15
OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1::
GROUP 3 (Lifting devices)...........................$ 49.14 31.15
OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1::
GROUP 2 (Truck crane oiler).........................$ 45.41 31.15
OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1::
GROUP 2 (Oiler).....................................$ 43.11 31.15
OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1::
GROUP 2 (Lifting devices)...........................$ 50.82 31.15
OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1::
GROUP 1 (Truck crane oiler).........................$ 45.66 31.15
OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1::
GROUP 1 (Oiler).....................................$ 43.38 31.15
OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1::
GROUP 1 (Lifting devices)...........................$ 52.64 31.15
OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1:
LIFTING DEVICES: GROUP 6: DECKHAND; FIRE TENDER
FOOTNOTE: WORK SUSPENDED BY ROPES OR CABLES, OR
WORK ON A YO-YO CAT: $.60 PER HOUR ADDITIONAL.......$ 42.50 31.15
OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1:
LIFTING DEVICES: GROUP 5: DECK ENGINEER
FOOTNOTE: WORK SUSPENDED BY ROPES OR CABLES, OR
WORK ON A YO-YO CAT: $.60 PER HOUR ADDITIONAL. ..$ 44.73 31.15
OPERATOR: POWER EQUIPMENT, PILEDRIVING - AREA 1:
LIFTING DEVICES: GROUP 4: ASSISTANT OPERATOR IN
LIEU OF ASSISTANT TO ENGINEER; FORKLIFT, 10 TONS
AND OVER; HEAVY-DUTY REPAIRPERSON/WELDER FOOTNOTE:
WORK SUSPENDED BY ROPES OR CABLES, OR WORK ON A
YO-YO CAT: $.60 PER HOUR ADDITIONAL. ..........$ 47.47 31.15
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND
WORK - AREA 1:: UNDERGROUND: (GROUP 5)..............$ 58.09 32.53
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND
WORK - AREA 1:: UNDERGROUND: (GROUP 4)..............$ 59.23 32.53
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND
WORK - AREA 1:: UNDERGROUND: (GROUP 3)..............$ 60.37 32.53
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND
WORK - AREA 1:: UNDERGROUND: (GROUP 2)..............$ 61.70 32.53
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND
WORK - AREA 1:: UNDERGROUND: (GROUP 1-A)............$ 65.43 32.53
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND
WORK - AREA 1:: UNDERGROUND: (GROUP 1)..............$ 62.96 32.53
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND
WORK - AREA 1:: SHAFTS, STOPES, RAISES: (GROUP 5)...$ 58.19 32.53
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND
WORK - AREA 1:: SHAFTS, STOPES, RAISES: (GROUP 4)...$ 59.33 32.53
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND
WORK - AREA 1:: SHAFTS, STOPES, RAISES: (GROUP 3)...$ 60.47 32.53
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND
WORK - AREA 1:: SHAFTS, STOPES, RAISES: (GROUP 2)...$ 61.80 32.53
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND
WORK - AREA 1:: SHAFTS, STOPES, RAISES: (GROUP 1-A).$ 65.53 32.53
OPERATOR: POWER EQUIPMENT, TUNNEL AND UNDERGROUND
WORK - AREA 1:: SHAFTS, STOPES, RAISES: (GROUP 1)...$ 63.06 32.53
OPERATOR: POWER EQUIPMENT, STEEL ERECTION - AREA
1:CRANE: GROUP 5: BOOM CAT FOOTNOTE: WORK
SUSPENDED BY ROPES OR CABLES, OR WORK ON A YO-YO
CAT: $.60 PER HOUR ADDITIONAL.......................$ 62.24 32.53
OPERATOR: POWER EQUIPMENT, STEEL ERECTION - AREA
1:: GROUP 3 (Hydraulic).............................$ 60.61 32.53
OPERATOR: POWER EQUIPMENT, STEEL ERECTION - AREA
1:: GROUP 3 (Cranes)................................$ 65.56 32.53
OPERATOR: POWER EQUIPMENT, STEEL ERECTION - AREA
1: CRANES: GROUP 2: CRANE OVER 45 TONS TO 100 TONS;
DERRICK UNDER 100 TONS; SELF-PROPELLED BOOM-TYPE
LIFTING DEVICE OVER 45 TONS TO 100 TONS; TOWER
CRANE FOOTNOTE: WORK SUSPENDED BY ROPES OR
CABLES, OR WORK ON A YO-YO CAT: $.60 PER HOUR
ADDITIONAL..........................................$ 67.04 32.53
OPERATOR: POWER EQUIPMENT, STEEL ERECTION - AREA
1: CRANES: GROUP 1: CRANE OVER 100 TONS; DERRICK
OVER 100 TONS; SELF- PROPELLED BOOM-TYPE LIFTING
DEVICE OVER 100 TONS FOOTNOTE: WORK SUSPENDED BY
ROPES OR CABLES, OR WORK ON A YO-YO CAT: $.60 PER
HOUR ADDITIONAL.....................................$ 68.81 32.53
OPERATOR: POWER EQUIPMENT, STEEL ERECTION - AREA
1: CRANE: GROUP 4: CHICAGO BOOM; FORKLIFT, 10 TONS
AND OVER; HEAVY-DUTY REPAIR PERSON/WELDER GROUP
5: BOOM CAT FOOTNOTE: WORK SUSPENDED BY ROPES OR
CABLES, OR WORK ON A YO-YO CAT: $.60 PER HOUR
ADDITIONAL..........................................$ 63.54 32.53
OPERATOR: POWER EQUIPMENT, CRANES AND ATTACHMENTS
- AREA 1:CRANES GROUP 2: CLAMSHELL AND DRAGLINE
OVER 1 CU. YD. UP TO AND INCLUDING 7 CU. YDS.;
CRANE, OVER 45 TONS UP TO AND INCLUDING 100 TONS;
DERRICK BARGE, 100 TONS AND UNDER; SELF-PROPELLED
BOOM-TYPE LIFTING DEVICE, OVER 45 TONS; TOWER CRANE
FOOTNOTE: WORK SUSPENDED BY ROPES OR CABLES, OR
WORK ON A YO-YO CAT: $.60 PER HOUR ADDITIONAL.......$ 66.08 32.53
OPERATOR: POWER EQUIPMENT, CRANES AND ATTACHMENTS
- AREA 1: CRANES GROUP 3: CLAMSHELL AND DRAGLINE
UP TO AND INCLUDING 1 CU. YD.; CRANES 45 TONS AND
UNDER; SELF-PROPELLED BOOM-TYPE LIFTING DEVICE 45
TONS AND UNDER; FOOTNOTE: WORK SUSPENDED BY ROPES
OR CABLES, OR WORK ON A YO-YO CAT: $.60 PER HOUR
ADDITIONAL..........................................$ 64.34 32.53
OPERATOR: POWER EQUIPMENT, CRANES AND ATTACHMENTS
- AREA 1: CRANES GROUP 4: BOOM TRUCK OR DUAL
PURPOSE A-FRAME TRUCK, NON-ROTATING OVER 15 TONS;
TRUCK-MOUNTED ROTATING TELESCOPIC BOOM TYPE LIFTING
DEVICE, MANITEX OR SIMILAR (BOOM TRUCK) OVER 15
TONS; TRUCK-MOUNTED ROTATING TELESCOPIC BOOM TYPE
LIFTING DEVICE, MANITEX OR SIMILAR (BOOM TRUCK) -
UNDER 15 TONS; FOOTNOTE: WORK SUSPENDED BY
ROPES OR CABLES, OR WORK ON A YO-YO CAT: $.60 PER
HOUR ADDITIONAL.....................................$ 61.30 32.53
OPERATOR: POWER EQUIPMENT, CRANES AND ATTACHMENTS
- AREA 1: CRANES GROUP 1: CLAMSHELL AND DRAGLINE
OVER 7 CU. YDS.; CRANE, OVER 100 TONS; DERRICK,
OVER 100 TONS; DERRICK BARGE PEDESTAL-MOUNTED, OVER
100 TONS; SELF-PROPELLED BOOM-TYPE LIFTING DEVICE,
OVER 100 TONS FOOTNOTE: WORK SUSPENDED BY ROPES
OR CABLES, OR WORK ON A YO-YO CAT: $.60 PER HOUR
ADDITIONAL..........................................$ 68.59 32.53
OPERATOR: POWER EQUIPMENT, AREA 1: GROUP 8-A
ELEVATOR OPERATOR; SKIDSTEER LOADER-BOBCAT 743
SERIES OR SMALLER, AND SIMILAR (WITHOUT
ATTACHMENTS); MINI EXCAVATOR UNDER 25 H.P.
(BACKHOE-TRENCHER); TUB GRINDER WOOD CHIPPER
FOOTNOTE: WORK SUSPENDED BY ROPES OR CABLES,
OR WORK ON A YO-YO CAT: $.60 PER HOUR ADDITIONAL....$ 55.49 32.53
OPERATOR: POWER EQUIPMENT, AREA 1: GROUP 8 BIT
SHARPENER; BOILER TENDER; BOX OPERATOR;
BRAKEPERSON; COMBINATION MIXER AND COMPRESSOR
(SHOTCRETE/GUNITE); COMPRESSOR OPERATOR; DECKHAND;
FIRE TENDER; FORKLIFT (UNDER 20 FT.); GENERATOR;
GUNITE/SHOTCRETE EQUIPMENT OPERATOR; HYDRAULIC
MONITOR; KEN SEAL MACHINE (OR SIMILAR);
MIXERMOBILE; OILER; PUMP OPERATOR; REFRIGERATION
PLANT; RESERVOIR-DEBRIS TUG (SELF- PROPELLED
FLOATING); ROSS CARRIER (CONSTRUCTION SITE);
ROTOMIST OPERATOR; SELF-PROPELLED TAPE MACHINE;
SHUTTLECAR; SELF-PROPELLED POWER SWEEPER OPERATOR
(INCLUDES VACUUM SWEEPER); SLUSHER OPERATOR;
SURFACE HEATER; SWITCHPERSON; TAR POT FIRETENDER;
TUGGER HOIST, SINGLE DRUM; VACUUM COOLING PLANT;
WELDING MACHINE (POWERED OTHER THAN BY ELECTRICITY)
FOOTNOTE: WORK SUSPENDED BY ROPES OR CABLES, OR
WORK ON A YO-YO CAT: $.60 PER HOUR ADDITIONAL.......$ 57.70 32.53
OPERATOR: POWER EQUIPMENT, AREA 1: GROUP 7 BALLAST
REGULATOR; BOOM TRUCK OR DUAL-PURPOSE A-FRAME
TRUCK, NON-ROTATING - UNDER 15 TONS; CARY LIFT OR
SIMILAR; COMBINATION SLURRY MIXER AND/OR CLEANER;
DRILLING EQUIPMENT, 20 FT. AND UNDER M.R.C.;
FIRETENDER (HOT PLANT); GROUTING MACHINE OPERATOR;
HIGHLINE CABLEWAY SIGNALPERSON; STATIONARY BELT
LOADER (KOLMAN OR SIMILAR); LIFT SLAB MACHINE
(VAGTBORG AND SIMILAR TYPES); MAGINNES INTERNAL
FULL SLAB VIBRATOR; MATERIAL HOIST (1 DRUM);
MECHANICAL TRENCH SHIELD; PAVEMENT BREAKER WITH OR
WITHOUT COMPRESSOR COMBINATION); PIPE CLEANING
MACHINE (TRACTOR PROPELLED AND SUPPORTED); POST
DRIVER; ROLLER (EXCEPT ASPHALT); CHIP SEAL;
SELF-PROPELLED AUTOMATICALLY APPLIED CONCRETE
CURING MAHCINE (ON STREETS, HIGHWAYS, AIRPORTS AND
CANALS); SELF-PROPELLED COMPACTOR (WITHOUT DOZER);
SIGNALPERSON; SLIP-FORM PUMPS (LIFTING DEVICE FOR
CONCRETE FORMS); TIE SPACER; TOWER MOBILE;
TRENCHING MACHINE, MAXIMUM DIGGING CAPACITY UP TO
AND INCLUDING 5 FT. DEPTH; TRUCK- TYPE LOADER
FOOTNOTE: WORK SUSPENDED BY ROPES OR CABLES, OR
WORK ON A YO-YO CAT: $.60 PER HOUR ADDITIONAL.......$ 58.84 32.53
OPERATOR: POWER EQUIPMENT, AREA 1: GROUP 6
ARMOR-COATER (OR SIMILAR); BALLAST JACK TAMPER;
BOOM- TYPE BACKFILLING MACHINE; ASSISTANT PLANT
ENGINEER; BRIDGE AND/OR GANTRY CRANE; CHEMICAL
GROUTING MACHINE, TRUCK-MOUNTED; CHIP SPREADING
MACHINE OPERATOR; CONCRETE SAW (SELF-PROPELLED UNIT
ON STREETS, HIGHWAYS, AIRPORTS AND CANALS); DECK
ENGINEER; DRILLING EQUIPMENT TEXOMA 600, HUGHES 200
SERIES OR SIMILAR UP TO AND INCLUDING 30 FT.
M.R.C.; DRILL DOCTOR; HELICOPTER RADIO OPERATOR;
HYDRO-HAMMER OR SIMILAR; LINE MASTER; SKIDSTEER
LOADER, BOBCAT LARGER THAN 743 SERIES OR SIMILAR
(WITH ATTACHMENTS); LOCOMOTIVE; LULL HI-LIFT OR
SIMILAR; OILER, TRUCK MOUNTED EQUIPMENT; PAVEMENT
BREAKER, TRUCK-MOUNTED, WITH COMPRESSOR
COMBINATION; PAVING FABRIC INSTALLATION AND/OR
LAYING MACHINE; PIPE BENDING MACHINE (PIPELINES
ONLY); PIPE WRAPPING MACHINE (TRACTOR PROPELLED AND
SUPPORTED); SCREED (EXCEPT ASPHALTIC CONCRETE
PAVING); SELF- PROPELLED PIPELINE WRAPPING MACHINE;
TRACTOR; SELF-LOADING CHIPPER; CONCRETE BARRIER
MOVING MACHINE FOOTNOTE: WORK SUSPENDED BY ROPES
OR CABLES, OR WORK ON A YO-YO CAT: $.60 PER HOUR
ADDITIONAL..........................................$ 59.98 32.53
OPERATOR: POWER EQUIPMENT, AREA 1: GROUP 5
CAST-IN-PLACE PIPE LAYING MACHINE; COMBINATION
SLUSHER AND MOTOR OPERATOR; CONCRETE CONVEYOR OR
CONCRETE PUMP, TRUCK OR EQUIPMENT MOUNTED; CONCRETE
CONVEYOR, BUILDING SITE; CONCRETE PUMP OR PUMPCRETE
GUN; DRILLING EQUIPMENT, WATSON 2000, TEXOMA 700 OR
SIMILAR; DRILLING AND BORING MACHINERY, HORIZONTAL
(NOT TO APPLY TO WATERLINERS, WAGON DRILLS OR
JACKHAMMERS); CONCRETE MIXER/ALL; PERSON AND/OR
MATERIAL HOIST; MECHANICAL FINISHERS (CONCRETE)
(CLARY, JOHNSON, BIDWELL BRIDGE DECK OR SIMILAR
TYPES); MECHANICAL BURM, CURB AND/OR CURB AND
GUTTER MACHINE, CONCRETE OR ASPHALT); MINE OR SHAFT
HOIST; PORTABLE CRUSHER; POWER JUMBO OPERATOR
(SETTING SLIP-FORMS, ETC., IN TUNNELS); SCREED
(AUTOMATIC OR MANUAL); SELF-PROPELLED COMPACTOR
WITH DOZER; TRACTOR WITH BOOM D6 OR SMALLER;
TRENCHING MACHINE, MAXIMUM DIGGING CAPACITY OVER 5
FT. DEPTH; VERMEER T-600B ROCK CUTTER OR SIMILAR
FOOTNOTE: WORK SUSPENDED BY ROPES OR CABLES, OR
WORK ON A YO-YO CAT: $.60 PER HOUR ADDITIONAL.......$ 61.30 32.53
OPERATOR: POWER EQUIPMENT, AREA 1: GROUP 4 ASPHALT
PLANT ENGINEER/BOX PERSON; CHICAGO BOOM;
COMBINATION BACKHOE AND LOADER UP TO AND INCLUDING
3/4 CU. YD.; CONCRETE BATCH PLANT (WET OR DRY);
DOZER AND/OR PUSH CAT; PULL- TYPE ELEVATING LOADER;
GRADESETTER, GRADE CHECKER (GPS, MECHANICAL OR
OTHERWISE); GROOVING AND GRINDING MACHINE; HEADING
SHIELD OPERATOR; HEAVY-DUTY DRILLING EQUIPMENT,
HUGHES, LDH, WATSON 3000 OR SIMILAR; HEAVY-DUTY
REPAIRPERSON AND/OR WELDER; LIME SPREADER; LOADER
UNDER 4 CU. YDS.; LUBRICATION AND SERVICE ENGINEER
(MOBILE AND GREASE RACK); MECHANICAL FINISHERS OR
SPREADER MACHINE (ASPHALT, BARBER-GREENE AND
SIMILAR); MILLER FORMLESS M-9000 SLOPE PAVER OR
SIMILAR; PORTABLE CRUSHING AND SCREENING PLANTS;
POWER BLADE SUPPORT; ROLLER OPERATOR, ASPHALT;
RUBBER-TIRED SCRAPER, SELF-LOADING (PADDLE-WHEELS,
ETC.); RUBBER- TIRED EARTHMOVING EQUIPMENT
(SCRAPERS); SLIP FORM PAVER (CONCRETE); SMALL
TRACTOR WITH DRAG; SOIL STABILIZER (P & H OR
EQUAL); SPIDER PLOW AND SPIDER PULLER; TUBEX PILE
RIG; UNLICENSED CONSTUCTION WORK BOAT OPERATOR, ON
SITE; TIMBER SKIDDER; TRACK LOADER UP TO 4 YDS.;
TRACTOR-DRAWN SCRAPER; TRACTOR, COMPRESSOR DRILL
COMBINATION; WELDER; WOODS-MIXER (AND OTHER SIMILAR
PUGMILL EQUIPMENT) FOOTNOTE: WORK SUSPENDED BY
ROPES OR CABLES, OR WORK ON A YO-YO CAT: $.60 PER
HOUR ADDITIONAL.....................................$ 62.57 32.53
OPERATOR: POWER EQUIPMENT, AREA 1: GROUP 3 ASPHALT
MILLING MACHINE; CABLE BACKHOE; COMBINATION BACKHOE
AND LOADER OVER 3/4 CU. YDS.; CONTINUOUS FLIGHT TIE
BACK MACHINE ASSISTANT TO ENGINEER OR MECHANIC;
CRANE MOUNTED CONTINUOUS FLIGHT TIE BACK MACHINE,
TONNAGE TO APPLY; CRANE MOUNTED DRILL ATTACHMENT,
TONNAGE TO APPLY; DOZER, SLOPE BRD; GRADALL;
HYDRAULIC EXCAVATOR, UP TO 3 1/2 CU. YDS.; LOADER 4
CU. YDS. AND OVER; LONG REACH EXCAVATOR; MULTIPLE
ENGINE SCRAPER (WHEN USED AS PUSH PULL); POWER
SHOVELS, UP TO AND INCLUDING 1 CU. YD.; PRE-STRESS
WIRE WRAPPING MACHINE; SIDE BOOM CAT, 572 OR
LARGER; TRACK LOADER 4 CU. YDS. AND OVER; WHEEL
EXCAVATOR (UP TO AND INCLUDING 750 CU. YDS. PER
HOUR) FOOTNOTE: WORK SUSPENDED BY ROPES OR CABLES,
OR WORK ON A YO-YO CAT: $.60 PER HOUR ADDITIONAL....$ 63.95 32.53
OPERATOR: POWER EQUIPMENT, AREA 1: GROUP 2
HIGHLINE CABLEWAY; HYDRAULIC EXCAVATOR, 3-1/2 CU.
YDS. UP TO 7 CU. YDS.; LICENSED CONSTRUCTION WORK
BOAT OPERATOR, ON SITE; POWER BLADE OPERATOR
(FINISH); POWER SHOVELS, OVER 1 CU. YD. UP TO AND
INCLUDING 7 CU. YDS. M.R.C. FOOTNOTE: WORK
SUSPENDED BY ROPES OR CABLES, OR WORK ON A YO-YO
CAT: $.60 PER HOUR ADDITIONAL.......................$ 65.43 32.53
OPERATOR: POWER EQUIPMENT, AREA 1: GROUP 1
OPERATOR OF HELICOPTER (WHEN USED IN ERECTION
WORK); HYDRAULIC EXCAVATOR, 7 CU. YDS. AND OVER;
POWER SHOVELS, OVER 7 CU. YDS. FOOTNOTE: WORK
SUSPENDED BY ROPES OR CABLES, OR WORK ON A YO-YO
CAT: $.60 PER HOUR ADDITIONAL.......................$ 66.96 32.53
----------------------------------------------------------------
ENGI0003-008 08/01/2024
Rates Fringes
DREDGING (CLAMSHELL & DIPPER DREDGING; HYDRAULIC
SUCTION DREDGING) AREA 2: (4) BARGEMAN; DECKHAND;
FIREMAN; LEVEEHAND; OILER AREA DESCRIPTIONS
AREA 1: ALAMEDA,BUTTE, CONTRA COSTA, KINGS, MARIN,
MERCED, NAPA, SACRAMENTO, SAN BENITO, SAN
FRANCISCO, SAN JOAQUIN, SAN MATEO, SANTA CLARA,
SANTA CRUZ, SOLANO, STANISLAUS, SUTTER, YOLO, AND
YUBA COUNTIES AREA 2: MODOC COUNTY THE
REMAINGING COUNTIES ARE SPLIT BETWEEN AREA 1 AND
AREA 2 AS NOTED BELOW: ALPINE COUNTY: AREA 1:
NORTHERNMOST PART AREA 2: REMAINDER CALAVERAS
COUNTY: AREA 1: REMAINDER AREA 2: EASTERN PART
COLUSA COUNTY: AREA 1: EASTERN PART AREA 2:
REMAINDER ELDORADO COUNTY: AREA 1: NORTH CENTRAL
PART AREA 2: REMAINDER FRESNO COUNTY: AREA
1: REMAINDER AREA 2: EASTERN PART GLENN
COUNTY: AREA 1: EASTERN PART AREA 2: REMAINDER
LASSEN COUNTY: AREA 1: WESTERN PART ALONG THE
SOUTHERN PORTION OF BORDER WITH SHASTA COUNTY AREA
2: REMAINDER MADERA COUNTY: AREA 1: EXCEPT
EASTERN PART AREA 2: EASTERN PART MARIPOSA
COUNTY AREA 1: EXCEPT EASTERN PART AREA 2:
EASTERN PART MONTERREY COUNTY AREA 1: EXCEPT
SOUTHWESTERN PART AREA 2: SOUTHWESTERN PART
NEVADA COUNTY: AREA 1: ALL BUT THE NORTHERN
PORTION ALONG THE BORDER OF SIERRA COUNTY AREA 2:
REMAINDER PLACER COUNTY: AREA 1: AL BUT THE
CENTRAL PORTION AREA 2: REMAINDER PLUMAS COUNTY:
AREA 1: WESTERN PORTION AREA 2: REMAINDER
SHASTA COUNTY: AREA 1: ALL BUT THE NORTHEASTERN
CORNER AREA 2: REMAINDER SIERRA COUNTY: AREA 1:
WESTERN PART AREA 2: REMAINDER SISKIYOU COUNTY:
AREA 1: CENTRAL PART AREA 2: REMAINDER SONOMA
COUNTY: AREA 1: ALL BUT THE NORTHWESTERN CORNER
AREA 2: REMAINDER TEHAMA COUNTY: AREA 1: ALL
BUT THE WESTERN BORDER WITH MENDOCINO & TRINITY
COUNTIES AREA 2: REMAINDER TRINITY COUNTY: AREA
1: EAST CENTRAL PART AND THE NORTHEASTERN BORDER
WITH SHASTA COUNTY AREA 2: REMAINDER TUOLUMNE
COUNTY: AREA 1: EXCEPT EASTERN PART AREA 2:
EASTERN PART........................................$ 53.23 39.55
DREDGING (CLAMSHELL & DIPPER DREDGING; HYDRAULIC
SUCTION DREDGING) AREA 2: (3) BOOSTER PUMP
OPERATOR; DECK ENGINEER; DECK MATE; DREDGE
TENDER; WINCH OPERATOR AREA DESCRIPTIONS
AREA 1: ALAMEDA,BUTTE, CONTRA COSTA, KINGS, MARIN,
MERCED, NAPA, SACRAMENTO, SAN BENITO, SAN
FRANCISCO, SAN JOAQUIN, SAN MATEO, SANTA CLARA,
SANTA CRUZ, SOLANO, STANISLAUS, SUTTER, YOLO, AND
YUBA COUNTIES AREA 2: MODOC COUNTY THE
REMAINGING COUNTIES ARE SPLIT BETWEEN AREA 1 AND
AREA 2 AS NOTED BELOW: ALPINE COUNTY: AREA 1:
NORTHERNMOST PART AREA 2: REMAINDER CALAVERAS
COUNTY: AREA 1: REMAINDER AREA 2: EASTERN PART
COLUSA COUNTY: AREA 1: EASTERN PART AREA 2:
REMAINDER ELDORADO COUNTY: AREA 1: NORTH CENTRAL
PART AREA 2: REMAINDER FRESNO COUNTY: AREA
1: REMAINDER AREA 2: EASTERN PART GLENN
COUNTY: AREA 1: EASTERN PART AREA 2: REMAINDER
LASSEN COUNTY: AREA 1: WESTERN PART ALONG THE
SOUTHERN PORTION OF BORDER WITH SHASTA COUNTY AREA
2: REMAINDER MADERA COUNTY: AREA 1: EXCEPT
EASTERN PART AREA 2: EASTERN PART MARIPOSA
COUNTY AREA 1: EXCEPT EASTERN PART AREA 2:
EASTERN PART MONTERREY COUNTY AREA 1: EXCEPT
SOUTHWESTERN PART AREA 2: SOUTHWESTERN PART
NEVADA COUNTY: AREA 1: ALL BUT THE NORTHERN
PORTION ALONG THE BORDER OF SIERRA COUNTY AREA 2:
REMAINDER PLACER COUNTY: AREA 1: AL BUT THE
CENTRAL PORTION AREA 2: REMAINDER PLUMAS COUNTY:
AREA 1: WESTERN PORTION AREA 2: REMAINDER
SHASTA COUNTY: AREA 1: ALL BUT THE NORTHEASTERN
CORNER AREA 2: REMAINDER SIERRA COUNTY: AREA 1:
WESTERN PART AREA 2: REMAINDER SISKIYOU COUNTY:
AREA 1: CENTRAL PART AREA 2: REMAINDER SONOMA
COUNTY: AREA 1: ALL BUT THE NORTHWESTERN CORNER
AREA 2: REMAINDER TEHAMA COUNTY: AREA 1: ALL
BUT THE WESTERN BORDER WITH MENDOCINO & TRINITY
COUNTIES AREA 2: REMAINDER TRINITY COUNTY: AREA
1: EAST CENTRAL PART AND THE NORTHEASTERN BORDER
WITH SHASTA COUNTY AREA 2: REMAINDER TUOLUMNE
COUNTY: AREA 1: EXCEPT EASTERN PART AREA 2:
EASTERN PART........................................$ 56.53 39.55
DREDGING (CLAMSHELL & DIPPER DREDGING; HYDRAULIC
SUCTION DREDGING) AREA 2: (2) DREDGE DOZER; HEAVY
DUTY REPAIRMAN : AREA DESCRIPTIONS AREA 1:
ALAMEDA,BUTTE, CONTRA COSTA, KINGS, MARIN, MERCED,
NAPA, SACRAMENTO, SAN BENITO, SAN FRANCISCO, SAN
JOAQUIN, SAN MATEO, SANTA CLARA, SANTA CRUZ,
SOLANO, STANISLAUS, SUTTER, YOLO, AND YUBA COUNTIES
AREA 2: MODOC COUNTY THE REMAINGING COUNTIES
ARE SPLIT BETWEEN AREA 1 AND AREA 2 AS NOTED BELOW:
ALPINE COUNTY: AREA 1: NORTHERNMOST PART AREA
2: REMAINDER CALAVERAS COUNTY: AREA 1:
REMAINDER AREA 2: EASTERN PART COLUSA COUNTY:
AREA 1: EASTERN PART AREA 2: REMAINDER ELDORADO
COUNTY: AREA 1: NORTH CENTRAL PART AREA 2:
REMAINDER FRESNO COUNTY: AREA 1: REMAINDER
AREA 2: EASTERN PART GLENN COUNTY: AREA 1:
EASTERN PART AREA 2: REMAINDER LASSEN COUNTY:
AREA 1: WESTERN PART ALONG THE SOUTHERN PORTION OF
BORDER WITH SHASTA COUNTY AREA 2: REMAINDER
MADERA COUNTY: AREA 1: EXCEPT EASTERN PART AREA
2: EASTERN PART MARIPOSA COUNTY AREA 1: EXCEPT
EASTERN PART AREA 2: EASTERN PART MONTERREY
COUNTY AREA 1: EXCEPT SOUTHWESTERN PART AREA 2:
SOUTHWESTERN PART NEVADA COUNTY: AREA 1: ALL
BUT THE NORTHERN PORTION ALONG THE BORDER OF SIERRA
COUNTY AREA 2: REMAINDER PLACER COUNTY: AREA 1:
AL BUT THE CENTRAL PORTION AREA 2: REMAINDER
PLUMAS COUNTY: AREA 1: WESTERN PORTION AREA 2:
REMAINDER SHASTA COUNTY: AREA 1: ALL BUT THE
NORTHEASTERN CORNER AREA 2: REMAINDER SIERRA
COUNTY: AREA 1: WESTERN PART AREA 2: REMAINDER
SISKIYOU COUNTY: AREA 1: CENTRAL PART AREA 2:
REMAINDER SONOMA COUNTY: AREA 1: ALL BUT THE
NORTHWESTERN CORNER AREA 2: REMAINDER TEHAMA
COUNTY: AREA 1: ALL BUT THE WESTERN BORDER WITH
MENDOCINO & TRINITY COUNTIES AREA 2: REMAINDER
TRINITY COUNTY: AREA 1: EAST CENTRAL PART AND THE
NORTHEASTERN BORDER WITH SHASTA COUNTY AREA 2:
REMAINDER TUOLUMNE COUNTY: AREA 1: EXCEPT
EASTERN PART AREA 2: EASTERN PART.................$ 57.65 39.55
DREDGING (CLAMSHELL & DIPPER DREDGING; HYDRAULIC
SUCTION DREDGING) AREA 2: (1) LEVERMAN AREA
DESCRIPTIONS AREA 1: ALAMEDA,BUTTE, CONTRA
COSTA, KINGS, MARIN, MERCED, NAPA, SACRAMENTO, SAN
BENITO, SAN FRANCISCO, SAN JOAQUIN, SAN MATEO,
SANTA CLARA, SANTA CRUZ, SOLANO, STANISLAUS,
SUTTER, YOLO, AND YUBA COUNTIES AREA 2: MODOC
COUNTY THE REMAINGING COUNTIES ARE SPLIT BETWEEN
AREA 1 AND AREA 2 AS NOTED BELOW: ALPINE COUNTY:
AREA 1: NORTHERNMOST PART AREA 2: REMAINDER
CALAVERAS COUNTY: AREA 1: REMAINDER AREA 2:
EASTERN PART COLUSA COUNTY: AREA 1: EASTERN
PART AREA 2: REMAINDER ELDORADO COUNTY: AREA 1:
NORTH CENTRAL PART AREA 2: REMAINDER FRESNO
COUNTY: AREA 1: REMAINDER AREA 2: EASTERN PART
GLENN COUNTY: AREA 1: EASTERN PART AREA 2:
REMAINDER LASSEN COUNTY: AREA 1: WESTERN PART
ALONG THE SOUTHERN PORTION OF BORDER WITH SHASTA
COUNTY AREA 2: REMAINDER MADERA COUNTY: AREA
1: EXCEPT EASTERN PART AREA 2: EASTERN PART
MARIPOSA COUNTY AREA 1: EXCEPT EASTERN PART
AREA 2: EASTERN PART MONTERREY COUNTY AREA 1:
EXCEPT SOUTHWESTERN PART AREA 2: SOUTHWESTERN
PART NEVADA COUNTY: AREA 1: ALL BUT THE
NORTHERN PORTION ALONG THE BORDER OF SIERRA COUNTY
AREA 2: REMAINDER PLACER COUNTY: AREA 1: AL BUT
THE CENTRAL PORTION AREA 2: REMAINDER PLUMAS
COUNTY: AREA 1: WESTERN PORTION AREA 2:
REMAINDER SHASTA COUNTY: AREA 1: ALL BUT THE
NORTHEASTERN CORNER AREA 2: REMAINDER SIERRA
COUNTY: AREA 1: WESTERN PART AREA 2: REMAINDER
SISKIYOU COUNTY: AREA 1: CENTRAL PART AREA 2:
REMAINDER SONOMA COUNTY: AREA 1: ALL BUT THE
NORTHWESTERN CORNER AREA 2: REMAINDER TEHAMA
COUNTY: AREA 1: ALL BUT THE WESTERN BORDER WITH
MENDOCINO & TRINITY COUNTIES AREA 2: REMAINDER
TRINITY COUNTY: AREA 1: EAST CENTRAL PART AND THE
NORTHEASTERN BORDER WITH SHASTA COUNTY AREA 2:
REMAINDER TUOLUMNE COUNTY: AREA 1: EXCEPT
EASTERN PART AREA 2: EASTERN PART.................$ 62.61 39.55
DREDGING (CLAMSHELL & DIPPER DREDGING; HYDRAULIC
SUCTION DREDGING) AREA 1: (4) BARGEMAN; DECKHAND;
FIREMAN; LEVEEHAND; OILER AREA DESCRIPTIONS
AREA 1: ALAMEDA,BUTTE, CONTRA COSTA, KINGS, MARIN,
MERCED, NAPA, SACRAMENTO, SAN BENITO, SAN
FRANCISCO, SAN JOAQUIN, SAN MATEO, SANTA CLARA,
SANTA CRUZ, SOLANO, STANISLAUS, SUTTER, YOLO, AND
YUBA COUNTIES AREA 2: MODOC COUNTY THE
REMAINGING COUNTIES ARE SPLIT BETWEEN AREA 1 AND
AREA 2 AS NOTED BELOW: ALPINE COUNTY: AREA 1:
NORTHERNMOST PART AREA 2: REMAINDER CALAVERAS
COUNTY: AREA 1: REMAINDER AREA 2: EASTERN PART
COLUSA COUNTY: AREA 1: EASTERN PART AREA 2:
REMAINDER ELDORADO COUNTY: AREA 1: NORTH CENTRAL
PART AREA 2: REMAINDER FRESNO COUNTY: AREA
1: REMAINDER AREA 2: EASTERN PART GLENN
COUNTY: AREA 1: EASTERN PART AREA 2: REMAINDER
LASSEN COUNTY: AREA 1: WESTERN PART ALONG THE
SOUTHERN PORTION OF BORDER WITH SHASTA COUNTY AREA
2: REMAINDER MADERA COUNTY: AREA 1: EXCEPT
EASTERN PART AREA 2: EASTERN PART MARIPOSA
COUNTY AREA 1: EXCEPT EASTERN PART AREA 2:
EASTERN PART MONTERREY COUNTY AREA 1: EXCEPT
SOUTHWESTERN PART AREA 2: SOUTHWESTERN PART
NEVADA COUNTY: AREA 1: ALL BUT THE NORTHERN
PORTION ALONG THE BORDER OF SIERRA COUNTY AREA 2:
REMAINDER PLACER COUNTY: AREA 1: AL BUT THE
CENTRAL PORTION AREA 2: REMAINDER PLUMAS COUNTY:
AREA 1: WESTERN PORTION AREA 2: REMAINDER
SHASTA COUNTY: AREA 1: ALL BUT THE NORTHEASTERN
CORNER AREA 2: REMAINDER SIERRA COUNTY: AREA 1:
WESTERN PART AREA 2: REMAINDER SISKIYOU COUNTY:
AREA 1: CENTRAL PART AREA 2: REMAINDER SONOMA
COUNTY: AREA 1: ALL BUT THE NORTHWESTERN CORNER
AREA 2: REMAINDER TEHAMA COUNTY: AREA 1: ALL
BUT THE WESTERN BORDER WITH MENDOCINO & TRINITY
COUNTIES AREA 2: REMAINDER TRINITY COUNTY: AREA
1: EAST CENTRAL PART AND THE NORTHEASTERN BORDER
WITH SHASTA COUNTY AREA 2: REMAINDER TUOLUMNE
COUNTY: AREA 1: EXCEPT EASTERN PART AREA 2:
EASTERN PART........................................$ 51.23 39.55
DREDGING (CLAMSHELL & DIPPER DREDGING; HYDRAULIC
SUCTION DREDGING) AREA 1: (3) BOOSTER PUMP
OPERATOR; DECK ENGINEER; DECK MATE; DREDGE
TENDER; WINCH OPERATOR AREA DESCRIPTIONS
AREA 1: ALAMEDA,BUTTE, CONTRA COSTA, KINGS, MARIN,
MERCED, NAPA, SACRAMENTO, SAN BENITO, SAN
FRANCISCO, SAN JOAQUIN, SAN MATEO, SANTA CLARA,
SANTA CRUZ, SOLANO, STANISLAUS, SUTTER, YOLO, AND
YUBA COUNTIES AREA 2: MODOC COUNTY THE
REMAINGING COUNTIES ARE SPLIT BETWEEN AREA 1 AND
AREA 2 AS NOTED BELOW: ALPINE COUNTY: AREA 1:
NORTHERNMOST PART AREA 2: REMAINDER CALAVERAS
COUNTY: AREA 1: REMAINDER AREA 2: EASTERN PART
COLUSA COUNTY: AREA 1: EASTERN PART AREA 2:
REMAINDER ELDORADO COUNTY: AREA 1: NORTH CENTRAL
PART AREA 2: REMAINDER FRESNO COUNTY: AREA
1: REMAINDER AREA 2: EASTERN PART GLENN
COUNTY: AREA 1: EASTERN PART AREA 2: REMAINDER
LASSEN COUNTY: AREA 1: WESTERN PART ALONG THE
SOUTHERN PORTION OF BORDER WITH SHASTA COUNTY AREA
2: REMAINDER MADERA COUNTY: AREA 1: EXCEPT
EASTERN PART AREA 2: EASTERN PART MARIPOSA
COUNTY AREA 1: EXCEPT EASTERN PART AREA 2:
EASTERN PART MONTERREY COUNTY AREA 1: EXCEPT
SOUTHWESTERN PART AREA 2: SOUTHWESTERN PART
NEVADA COUNTY: AREA 1: ALL BUT THE NORTHERN
PORTION ALONG THE BORDER OF SIERRA COUNTY AREA 2:
REMAINDER PLACER COUNTY: AREA 1: AL BUT THE
CENTRAL PORTION AREA 2: REMAINDER PLUMAS COUNTY:
AREA 1: WESTERN PORTION AREA 2: REMAINDER
SHASTA COUNTY: AREA 1: ALL BUT THE NORTHEASTERN
CORNER AREA 2: REMAINDER SIERRA COUNTY: AREA 1:
WESTERN PART AREA 2: REMAINDER SISKIYOU COUNTY:
AREA 1: CENTRAL PART AREA 2: REMAINDER SONOMA
COUNTY: AREA 1: ALL BUT THE NORTHWESTERN CORNER
AREA 2: REMAINDER TEHAMA COUNTY: AREA 1: ALL
BUT THE WESTERN BORDER WITH MENDOCINO & TRINITY
COUNTIES AREA 2: REMAINDER TRINITY COUNTY: AREA
1: EAST CENTRAL PART AND THE NORTHEASTERN BORDER
WITH SHASTA COUNTY AREA 2: REMAINDER TUOLUMNE
COUNTY: AREA 1: EXCEPT EASTERN PART AREA 2:
EASTERN PART........................................$ 54.53 39.55
DREDGING (CLAMSHELL & DIPPER DREDGING; HYDRAULIC
SUCTION DREDGING) AREA 1: (1) LEVERMAN AREA
DESCRIPTIONS AREA 1: ALAMEDA,BUTTE, CONTRA
COSTA, KINGS, MARIN, MERCED, NAPA, SACRAMENTO, SAN
BENITO, SAN FRANCISCO, SAN JOAQUIN, SAN MATEO,
SANTA CLARA, SANTA CRUZ, SOLANO, STANISLAUS,
SUTTER, YOLO, AND YUBA COUNTIES AREA 2: MODOC
COUNTY THE REMAINGING COUNTIES ARE SPLIT BETWEEN
AREA 1 AND AREA 2 AS NOTED BELOW: ALPINE COUNTY:
AREA 1: NORTHERNMOST PART AREA 2: REMAINDER
CALAVERAS COUNTY: AREA 1: REMAINDER AREA 2:
EASTERN PART COLUSA COUNTY: AREA 1: EASTERN
PART AREA 2: REMAINDER ELDORADO COUNTY: AREA 1:
NORTH CENTRAL PART AREA 2: REMAINDER FRESNO
COUNTY: AREA 1: REMAINDER AREA 2: EASTERN PART
GLENN COUNTY: AREA 1: EASTERN PART AREA 2:
REMAINDER LASSEN COUNTY: AREA 1: WESTERN PART
ALONG THE SOUTHERN PORTION OF BORDER WITH SHASTA
COUNTY AREA 2: REMAINDER MADERA COUNTY: AREA
1: EXCEPT EASTERN PART AREA 2: EASTERN PART
MARIPOSA COUNTY AREA 1: EXCEPT EASTERN PART
AREA 2: EASTERN PART MONTERREY COUNTY AREA 1:
EXCEPT SOUTHWESTERN PART AREA 2: SOUTHWESTERN
PART NEVADA COUNTY: AREA 1: ALL BUT THE
NORTHERN PORTION ALONG THE BORDER OF SIERRA COUNTY
AREA 2: REMAINDER PLACER COUNTY: AREA 1: AL BUT
THE CENTRAL PORTION AREA 2: REMAINDER PLUMAS
COUNTY: AREA 1: WESTERN PORTION AREA 2:
REMAINDER SHASTA COUNTY: AREA 1: ALL BUT THE
NORTHEASTERN CORNER AREA 2: REMAINDER SIERRA
COUNTY: AREA 1: WESTERN PART AREA 2: REMAINDER
SISKIYOU COUNTY: AREA 1: CENTRAL PART AREA 2:
REMAINDER SONOMA COUNTY: AREA 1: ALL BUT THE
NORTHWESTERN CORNER AREA 2: REMAINDER TEHAMA
COUNTY: AREA 1: ALL BUT THE WESTERN BORDER WITH
MENDOCINO & TRINITY COUNTIES AREA 2: REMAINDER
TRINITY COUNTY: AREA 1: EAST CENTRAL PART AND THE
NORTHEASTERN BORDER WITH SHASTA COUNTY AREA 2:
REMAINDER TUOLUMNE COUNTY: AREA 1: EXCEPT
EASTERN PART AREA 2: EASTERN PART.................$ 60.61 39.55
DREDGING ( CLAMSHELL & DIPPER DREDGING; HYDRAULIC
SUCTION DREDGING) AREA 1: (2) DREDGE DOZER; HEAVY
DUTY REPAIRMAN AREA DESCRIPTIONS AREA 1:
ALAMEDA,BUTTE, CONTRA COSTA, KINGS, MARIN, MERCED,
NAPA, SACRAMENTO, SAN BENITO, SAN FRANCISCO, SAN
JOAQUIN, SAN MATEO, SANTA CLARA, SANTA CRUZ,
SOLANO, STANISLAUS, SUTTER, YOLO, AND YUBA COUNTIES
AREA 2: MODOC COUNTY THE REMAINGING COUNTIES
ARE SPLIT BETWEEN AREA 1 AND AREA 2 AS NOTED BELOW:
ALPINE COUNTY: AREA 1: NORTHERNMOST PART AREA
2: REMAINDER CALAVERAS COUNTY: AREA 1:
REMAINDER AREA 2: EASTERN PART COLUSA COUNTY:
AREA 1: EASTERN PART AREA 2: REMAINDER ELDORADO
COUNTY: AREA 1: NORTH CENTRAL PART AREA 2:
REMAINDER FRESNO COUNTY: AREA 1: REMAINDER
AREA 2: EASTERN PART GLENN COUNTY: AREA 1:
EASTERN PART AREA 2: REMAINDER LASSEN COUNTY:
AREA 1: WESTERN PART ALONG THE SOUTHERN PORTION OF
BORDER WITH SHASTA COUNTY AREA 2: REMAINDER
MADERA COUNTY: AREA 1: EXCEPT EASTERN PART AREA
2: EASTERN PART MARIPOSA COUNTY AREA 1: EXCEPT
EASTERN PART AREA 2: EASTERN PART MONTERREY
COUNTY AREA 1: EXCEPT SOUTHWESTERN PART AREA 2:
SOUTHWESTERN PART NEVADA COUNTY: AREA 1: ALL
BUT THE NORTHERN PORTION ALONG THE BORDER OF SIERRA
COUNTY AREA 2: REMAINDER PLACER COUNTY: AREA 1:
AL BUT THE CENTRAL PORTION AREA 2: REMAINDER
PLUMAS COUNTY: AREA 1: WESTERN PORTION AREA 2:
REMAINDER SHASTA COUNTY: AREA 1: ALL BUT THE
NORTHEASTERN CORNER AREA 2: REMAINDER SIERRA
COUNTY: AREA 1: WESTERN PART AREA 2: REMAINDER
SISKIYOU COUNTY: AREA 1: CENTRAL PART AREA 2:
REMAINDER SONOMA COUNTY: AREA 1: ALL BUT THE
NORTHWESTERN CORNER AREA 2: REMAINDER TEHAMA
COUNTY: AREA 1: ALL BUT THE WESTERN BORDER WITH
MENDOCINO & TRINITY COUNTIES AREA 2: REMAINDER
TRINITY COUNTY: AREA 1: EAST CENTRAL PART AND THE
NORTHEASTERN BORDER WITH SHASTA COUNTY AREA 2:
REMAINDER TUOLUMNE COUNTY: AREA 1: EXCEPT
EASTERN PART AREA 2: EASTERN PART.................$ 55.65 39.55
----------------------------------------------------------------
ENGI0003-019 06/30/2025
Rates Fringes
OPERATOR: POWER EQUIPMENT, LANDSCAPE WORK ONLY:
GROUP 3 (AREA 2)....................................$ 49.64 28.56
OPERATOR: POWER EQUIPMENT, LANDSCAPE WORK ONLY:
GROUP 3 (AREA 1)....................................$ 47.64 28.56
OPERATOR: POWER EQUIPMENT, LANDSCAPE WORK ONLY:
GROUP 2 (AREA 2)....................................$ 54.25 28.56
OPERATOR: POWER EQUIPMENT, LANDSCAPE WORK ONLY:
GROUP 2 (AREA 1)....................................$ 52.25 28.56
OPERATOR: POWER EQUIPMENT, LANDSCAPE WORK ONLY:
GROUP 1 (AREA 2)....................................$ 57.85 28.56
OPERATOR: POWER EQUIPMENT, LANDSCAPE WORK ONLY:
GROUP 1 (AREA 1)....................................$ 55.85 28.56
----------------------------------------------------------------
IRON0433-006 01/01/2025
Rates Fringes
IRONWORKER (ORNAMENTAL, REINFORCING AND STRUCTURAL).$ 50.70 35.15
IRONWORKER (FENCE ERECTOR)..........................$ 45.78 26.51
----------------------------------------------------------------
LABO0294-003 07/01/2023
Rates Fringes
LABORER: TRAFFIC CONTROL/LANE CLOSURE: TRAFFIC
CONTROL PERSON II INSTALLATION AND REMOVAL OF
TEMPORARY/PERMANENT SIGNS, MARKERS, DELINEATORS AND
CRASH CUSHIONS......................................$ 34.06 27.30
LABORER: TRAFFIC CONTROL/LANE CLOSURE: TRAFFIC
CONTROL PERSON I LAYOUT OF TRAFFIC CONTROL, CRASH
CUSHIONS, CONSTRUCTION AREA AND ROADSIDE SIGNAGE....$ 36.56 27.30
LABORER: TRAFFIC CONTROL/LANE CLOSURE: ESCORT
DRIVER, FLAG PERSON.................................$ 36.26 27.30
----------------------------------------------------------------
LABO0294-004 06/26/2023
Rates Fringes
LABORERS:, WRECKING: GROUP 2: Semi-skilled wrecker
(salvaging of other building materials) FOOTNOTES:
LABORERS WORKING OFF OR WITH OR FROM BOS'N CHAIRS,
SWINGING SCAFFOLDS, BELTS (NOT APPLICABLE TO
WORKERS ENTITLED TO RECEIVE THE WAGE RATE SET FORTH
IN GROUP 1-A): $0.25 PER HOUR ADDITIONAL.
LABORER CLASSIFICATIONS................$ 35.35 27.30
LABORERS:, WRECKING: GROUP 1: Skilled wrecker
(removing and salvaging of sash, windows and
materials) FOOTNOTES: LABORERS WORKING OFF OR
WITH OR FROM BOS'N CHAIRS, SWINGING SCAFFOLDS,
BELTS (NOT APPLICABLE TO WORKERS ENTITLED TO
RECEIVE THE WAGE RATE SET FORTH IN GROUP 1-A):
$0.25 PER HOUR ADDITIONAL.
LABORER CLASSIFICATIONS.............................$ 35.50 27.30
LABORERS:, GUNITE: GROUP 4: GUNITE LABORER
FOOTNOTES: LABORERS WORKING OFF OR WITH OR FROM
BOS'N CHAIRS, SWINGING SCAFFOLDS, BELTS (NOT
APPLICABLE TO WORKERS ENTITLED TO RECEIVE THE WAGE
RATE SET FORTH IN GROUP 1-A): $0.25 PER HOUR
ADDITIONAL..........................................$ 35.25 27.30
LABORERS:, GUNITE: GROUP 2: NOZZLEMAN, GUNMAN,
POTMAN, GROUNDMAN FOOTNOTES: LABORERS WORKING
OFF OR WITH OR FROM BOS'N CHAIRS, SWINGING
SCAFFOLDS, BELTS (NOT APPLICABLE TO WORKERS
ENTITLED TO RECEIVE THE WAGE RATE SET FORTH IN
GROUP 1-A): $0.25 PER HOUR ADDITIONAL. .$ 35.96 27.30
LABORERS:, GUNITE: GROUP 1: STRUCTURAL NOZZLEMAN
FOOTNOTES: LABORERS WORKING OFF OR WITH OR FROM
BOS'N CHAIRS, SWINGING SCAFFOLDS, BELTS (NOT
APPLICABLE TO WORKERS ENTITLED TO RECEIVE THE WAGE
RATE SET FORTH IN GROUP 1-A): $0.25 PER HOUR
ADDITIONAL..........................................$ 36.46 27.30
LABORERS:, GUNITE: GROUP 3: REBOUNDMAN
FOOTNOTES: LABORERS WORKING OFF OR WITH OR FROM
BOS'N CHAIRS, SWINGING SCAFFOLDS, BELTS (NOT
APPLICABLE TO WORKERS ENTITLED TO RECEIVE THE WAGE
RATE SET FORTH IN GROUP 1-A): $0.25 PER HOUR
ADDITIONAL..........................................$ 35.37 27.30
LABORERS:, CONSTRUCTION CRAFT LABORERS: GROUP 4 ALL
CLEAN-UP WORK OF DEBRIS, GROUNDS AND BUILDING
INCLUDING BUT NOT LIMITED TO: STREET CLEANER;
CLEANING AND WASHING WINDOWS; BRICK CLEANER
(JOBSITE ONLY); MATERIAL CLEANER (JOBSITE ONLY).
THE CLASSIFICATION ""MATERIAL CLEANER"" IS TO BE
UTILIZED UNDER THE FOLLOWING CONDITIONS: A: AT
DEMOLITION SITE FOR THE SALVAGE OF THE MATERIAL.
B: AT THE CONCLUSION OF A JOB WHERE THE MATERIAL
IS TO BE SALVAGED AND STOCKED TO BE REUSED ON
ANOTHER JOB. C: FOR THE CLEANING OF SALVAGE
MATERIAL AT THE JOBSITE OR TEMPORARY JOBSITE YARD.
THE MATERIAL CLEANER CLASSIFICATION SHOULD NOT
BE USED IN THE PERFORMANCE OF ""FORM STRIPPING,
CLEANING AND OILING AND MOVING TO THE NEXT POINT OF
ERECTION"". FOOTNOTES: LABORERS
WORKING OFF OR WITH OR FROM BOS'N CHAIRS, SWINGING
SCAFFOLDS, BELTS (NOT APPLICABLE TO WORKERS
ENTITLED TO RECEIVE THE WAGE RATE SET FORTH IN
GROUP 1-A): $0.25 PER HOUR ADDITIONAL.
LABORER CLASSIFICATIONS ................$ 28.94 27.30
LABORERS:, CONSTRUCTION CRAFT LABORERS: GROUP 3:
CONSTRUCTION LABORERS, INCLUDING BRIDGE AND GENERAL
LABORER; DUMP, LOAD SPOTTER; FLAG PERSON; FIRE
WATCHER; FENCE ERECTOR; GUARDRAIL ERECTOR;
GARDENER, HORTICULTURAL AND LANDSCAPE LABORER;
JETTING; LIMBER, BRUSH LOADER AND PILER; PAVEMENT
MARKER (BUTTON SETTER); MAINTENANCE, REPAIR TRACK
AND ROAD BEDS; STREETCAR AND RAILROAD CONSTRUCTION
TRACK LABORER; TEMPORARY AIR AND WATER LINES,
VICTAULIC OR SIMILAR; TOOL ROOM ATTENDANT (JOBSITE
ONLY) FOOTNOTES: LABORERS WORKING OFF OR WITH OR
FROM BOS'N CHAIRS, SWINGING SCAFFOLDS, BELTS (NOT
APPLICABLE TO WORKERS ENTITLED TO RECEIVE THE WAGE
RATE SET FORTH IN GROUP 1-A): $0.25 PER HOUR
ADDITIONAL. LABORER
CLASSIFICATIONS.....................................$ 35.25 27.30
LABORERS:, CONSTRUCTION CRAFT LABORERS: GROUP 2:
ASPHALT SHOVELER; CEMENT DUMPER AND HANDLING DRY
CEMENT OR GYPSUM; CHOKE-SETTER AND RIGGER (CLEARING
WORK); CONCRETE BUCKET DUMPER AND CHUTE; CONCRETE
CHIPPING AND GRINDING; CONCRETE LABORER (WET OR
DRY); DRILLER TENDER, CHUCK TENDER, NIPPER; GUINEA
CHASER (STAKE), GROUT CREW; HIGH PRESSURE NOZZLE,
ADDUCTOR; HYDRAULIC MONITOR (OVER 100 LBS.
PRESSURE); LOADING AND UNLOADING, CARRYING AND
HAULING OF ALL RODS AND MATERIALS FOR USE IN
REINFORCING CONCRETE CONSTRUCTION; PITTSBURGH
CHIPPER AND SIMILAR TYPE BRUSH SHREDDERS; SLOPER;
SINGLE FOOT, HAND-HELD, PNEUMATIC TAMPER; ALL
PNEUMATIC, AIR, GAS AND ELECTRIC TOOLS NOT LISTED
IN GROUPS 1 THROUGH 1-F; JACKING OF PIPE - UNDER 12
INCHES FOOTNOTES: LABORERS WORKING OFF OR WITH OR
FROM BOS'N CHAIRS, SWINGING SCAFFOLDS, BELTS (NOT
APPLICABLE TO WORKERS ENTITLED TO RECEIVE THE WAGE
RATE SET FORTH IN GROUP 1-A): $0.25 PER HOUR
ADDITIONAL. LABORER
CLASSIFICATIONS.....................................$ 35.35 27.30
LABORERS:, CONSTRUCTION CRAFT LABORERS: GROUP 1:
ASPHALT SPREADER BOXES (ALL TYPES); BARKO, WACKER
AND SIMILAR TYPE TAMPERS; BUGGYMOBILE; CAULKER,
BANDER, PIPEWRAPPER, CONDUIT LAYER, PLASTIC
PIPELAYER; CERTIFIED HAZARDOUS WASTE WORKER;
COMPACTORS OF ALL TYPES; CONCRETE AND MAGNESITE
MIXER, 1/2 YD. AND UNDER; CONCRETE PAN WORK;
CONCRETE SANDER; CONCRETE SAW; CRIBBER AND/OR
SHORING; CUT GRANITE CURB SETTER; DRI-PAK-IT
MACHINE; FALLER, LOGLOADER AND BUCKER; FORM RAISER,
SLIP FORMS; GREEN CUTTER; HEADERBOARD, HUBSETTER,
ALIGNER, BY ANY METHOD; HIGH PRESSURE BLOW PIPE
(1-1/2"" OR OVER, 100 LBS. PRESSURE/OVER); HYDRO
SEEDER AND SIMILAR YPE; JACKHAMMER OPERATOR;
JACKING OF PIPE OVER 12 INCHES; JACKSON AND SIMILAR
TYPE COMPACTOR; KETTLE TENDER, POT AND WORKER
APPLYING ASPHALT, LAY-KOLD, CREOSOTE, LIME, CAUSTIC
AND SIMILAR TYPE MATERIALS (APPLYING MEANS
APPLYING, DIPPING OR HANDLING OF SUCH MATERIALS);
LAGGING, SHEETING, WHALING, BRACING, TRENCHJACKING,
LAGGING HAMMER; MAGNESITE, EPOXYRESIN, FIBERGLASS,
MASTIC WORKER (WET OR DRY); NO JOINT PIPE AND
STRIPPING OF SAME, INCLUDING REPAIR OF VOIDS;
PAVEMENT BREAKER AND SPADER, INCLUDING TOOL
GRINDER; PERMA CURB; PIPELAYER (INCLUDING GRADE
CHECKING IN CONNECTION WITH PIPELAYING);
PRECAST-MANHOLE SETTER; PRESSURE PIPE TESTER; POST
HOLE DIGGER, AIR, GAS AND ELECTRIC; POWER BROOM
SWEEPER; POWER TAMPERS OF ALL TYPES (EXCEPT AS
SHOWN IN GROUP 2); RAM SET GUN AND STUD GUN; RIPRAP
STONEPAVER AND ROCK-SLINGER, INCLUDING PLACING OF
SACKED CONCRETE AND/OR SAND (WET OR DRY) AND
GABIONS AND SIMILAR TYPE; ROTARY SCARIFIER OR
MULTIPLE HEAD CONCRETE CHIPPING SCARIFIER; ROTO AND
DITCH WITCH; ROTOTILLER; SANDBLASTER, POT, GUN,
NOZZLE OPERATORS; SIGNALLING AND RIGGING; TANK
CLEANER; TREE CLIMBER; TURBO BLASTER; VIBRASCREED,
BULL FLOAT IN CONNECTION WITH LABORERS' WORK;
VIBRATOR FOOTNOTES: LABORERS WORKING OFF OR
WITH OR FROM BOS'N CHAIRS, SWINGING SCAFFOLDS,
BELTS (NOT APPLICABLE TO WORKERS ENTITLED TO
RECEIVE THE WAGE RATE SET FORTH IN GROUP 1-A):
$0.25 PER HOUR ADDITIONAL.
LABORER CLASSIFICATIONS ..........................$ 35.50 27.30
LABORERS:, CONSTRUCTION CRAFT LABORERS: GROUP 1-F:
WIRE WINDING MACHINE IN CONNECTION WITH GUNITING OR
SHOT CRETE FOOTNOTES: LABORERS WORKING OFF OR
WITH OR FROM BOS'N CHAIRS, SWINGING SCAFFOLDS,
BELTS (NOT APPLICABLE TO WORKERS ENTITLED TO
RECEIVE THE WAGE RATE SET FORTH IN GROUP 1-A):
$0.25 PER HOUR ADDITIONAL.
LABORER CLASSIFICATIONS.............................$ 36.08 27.30
LABORERS:, CONSTRUCTION CRAFT LABORERS: GROUP 1-E:
WORK ON AND/OR IN BELL HOLE FOOTINGS AND SHAFTS
THEREOF, AND WORK ON AND IN DEEP FOOTINGS. (A DEEP
FOOTING IS A HOLE 15 FEET OR MORE IN DEPTH.) IN
THE EVENT THE DEPTH OF THE FOOTING IS UNKNOWN AT
THE COMMENCEMENT OF EXCAVATION, AND THE FINAL DEPTH
EXCEEDS 15 FEET, THE DEEP FOOTING WAGE RATE WOULD
APPLY TO ALL EMPLOYEES FOR EACH AND EVERY DAY
WORKED ON OR IN THE EXCAVATION OF THE FOOTING FROM
THE DATE OF INCEPTION. FOOTNOTES: LABORERS
WORKING OFF OR WITH OR FROM BOS'N CHAIRS, SWINGING
SCAFFOLDS, BELTS (NOT APPLICABLE TO WORKERS
ENTITLED TO RECEIVE THE WAGE RATE SET FORTH IN
GROUP 1-A): $0.25 PER HOUR ADDITIONAL.
LABORER CLASSIFICATIONS...................$ 36.05 27.30
LABORERS:, CONSTRUCTION CRAFT LABORERS: GROUP 1-C:
BURNING AND WELDING IN CONNECTION WITH LABORERS'
WORK; SYNTHETIC THERMOPLASTICS AND SIMILAR TYPE
WELDING FOOTNOTES: LABORERS WORKING OFF OR WITH
OR FROM BOS'N CHAIRS, SWINGING SCAFFOLDS, BELTS
(NOT APPLICABLE TO WORKERS ENTITLED TO RECEIVE THE
WAGE RATE SET FORTH IN GROUP 1-A): $0.25 PER HOUR
ADDITIONAL. LABORER
CLASSIFICATIONS.....................................$ 35.55 27.30
LABORERS:, CONSTRUCTION CRAFT LABORERS: GROUP 1-A:
JOY DRILL MODEL TWM-2A; GARDNER-DENVER MODEL DH143
AND SIMILAR TYPE DRILLS; TRACK DRILLER; JACK LEG
DRILLER; WAGON DRILLER; MECHANICAL DRILLERS, ALL
TYPES REGARDLESS OF TYPE OR METHOD OF POWER;
MECHANICAL PIPE LAYERS, ALL TYPES REGARDLESS OF
TYPE OR METHOD OF POWER; BLASTER AND POWDER; ALL
WORK OF LOADING, PLACING AND BLASTING OF ALL POWDER
AND EXPLOSIVES OF WHATEVER TYPE REGARDLESS OF
METHOD USED FOR SUCH LOADING AND PLACING; HIGH
SCALERS (INCLUDING DRILLING OF SAME); TREE TOPPER;
BIT GRINDER FOOTNOTES: LABORERS WORKING OFF OR
WITH OR FROM BOS'N CHAIRS, SWINGING SCAFFOLDS,
BELTS (NOT APPLICABLE TO WORKERS ENTITLED TO
RECEIVE THE WAGE RATE SET FORTH IN GROUP 1-A):
$0.25 PER HOUR ADDITIONAL.
LABORER CLASSIFICATIONS.............................$ 35.72 27.30
LABORERS: CONSTRUCTION CRAFT LABORERS: CONSTRUCTION
SPECIALIST GROUP ASPHALT IRONER AND RAKER;
CHAINSAW; LASER BEAM IN CONNECTION WITH LABORERS'
WORK; MASONRY AND PLASTERER TENDER; CAST-IN-PLACE
MANHOLE FORM SETTER; PRESSURE PIPELAYER; DAVIS
TRENCHER - 300 OR SIMILAR TYPE (AND ALL SMALL
TRENCHERS); BLASTER; DIAMOND DRILLER; MULTIPLE UNIT
DRILL; HYDRAULIC DRILL FOOTNOTES: LABORERS
WORKING OFF OR WITH OR FROM BOS'N CHAIRS, SWINGING
SCAFFOLDS, BELTS (NOT APPLICABLE TO WORKERS
ENTITLED TO RECEIVE THE WAGE RATE SET FORTH IN
GROUP 1-A): $0.25 PER HOUR ADDITIONAL.
SEWER CLEANERS SHALL RECEIVE $4.00 PER DAY ABOVE
GROUP 1 WAGE RATES. ""SEWER CLEANER"" MEANS ANY
WORKER WHO HANDLES OR COMES IN CONTACT WITH RAW
SEWAGE IN SMALL DIAMETER SEWERS. THOSE WHO WORK
INSIDE RECENTLY ACTIVE, LARGE DIAMETER SEWERS, AND
ALL RECENTLY ACTIVE SEWER MANHOLES, SHALL RECEIVE
$5.00 PER DAY ABOVE GROUP 1 WAGE RATES.
MAINTENANCE AND REPAIR TRACK AND ROAD BEDS
(UNDERGROUND STRUCTURES). ALL EMPLOYEES PERFORMING
WORK COVERED HEREIN SHALL RECEIVE $ .25 PER HOUR
ABOVE THEIR REGULAR RATE FOR ALL WORK PERFORMED ON
UNDERGROUND STRUCTURES NOT SPECIFICALLY COVERED
HEREIN. THIS PARAGRAPH SHALL NOT BE CONSTRUED TO
APPLY TO WORK BELOW GROUND LEVEL IN OPEN CUT. IT
SHALL APPLY TO CUT AND COVER WORK OF SUBWAY
CONSTRUCTION AFTER THE TEMPORARY COVER HAS BEEN
PLACED..............................................$ 36.20 27.30
GARDENERS, HORTICULTURAL & LANDSCAPE LABORERS (New
Construction).......................................$ 35.25 27.30
GARDENERS, HORTICULTURAL & LANDSCAPE LABORERS
(Establishment Warranty Period).....................$ 28.94 27.30
----------------------------------------------------------------
LABO0294-006 06/26/2023
Rates Fringes
TUNNEL AND SHAFT LABORERS: SHOTCRETE SPECIALIST
(TULARE COUNTY).....................................$ 46.41 27.72
TUNNEL AND SHAFT LABORERS: GROUP 5 GROUT CREW;
REBOUNDMAN; SWAMPER/ BRAKEMAN (TULARE COUNTY).......$ 44.42 27.72
TUNNEL AND SHAFT LABORERS: GROUP 4 VIBRATOR
OPERATOR, PAVEMENT BREAKER; BULL GANG - MUCKERS,
TRACKMEN; CONCRETE CREW - INCLUDES RODDING AND
SPREADING, DUMPMEN (ANY METHOD) (TULARE COUNTY).....$ 44.96 27.72
TUNNEL AND SHAFT LABORERS: GROUP 3 BIT GRINDER;
BLASTER, DRILLER, POWDERMEN, HEADING; CHERRY
PICKERMEN - WHERE CAR IS LIFTED; CONCRETE FINISHER
IN TUNNEL; CONCRETE SCREEDMAN; GROUT PUMPMAN AND
POTMAN; GUNITE & SHOTCRETE GUNMAN & POTMAN;
HEADERMEN; HIGH PRESSURE NOZZLEMAN; MINER - TUNNEL,
INCLUDING TOP AND BOTTOM MAN ON SHAFT AND RAISE
WORK; NIPPER; NOZZLEMAN ON SLICK LINE; SANDBLASTER
- POTMAN, ROBOTIC SHOTCRETE PLACER, SEGMENT
ERECTOR, TUNNEL MUCK HAULER, STEEL FORM RAISER AND
SETTER; TIMBERMAN, RETIMBERMAN (WOOD OR STEEL OR
SUBSTITUTE MATERIALS THEREFORE); TUGGER (FOR TUNNEL
LABORER WORK); CABLE TENDER; CHUCK TENDER;
POWDERMAN - PRIMER HOUSE (TULARE COUNTY)............$ 45.41 27.72
TUNNEL AND SHAFT LABORERS: GROUP 2 RODMEN; SHAFT
WORK & RAISE (BELOW ACTUAL OR EXCAVATED GROUND
LEVEL) (TULARE COUNTY)..............................$ 45.66 27.72
TUNNEL AND SHAFT LABORERS: GROUP 1 DIAMOND DRILLER;
GROUNDMEN; GUNITE AND SHOTCRETE NOZZLEMEN (TULARE
COUNTY).............................................$ 45.89 27.72
----------------------------------------------------------------
LABO0294-009 07/01/2023
Rates Fringes
PLASTERER TENDER WORK ON A SWING STAGE SCAFFOLD:
$1.00 PER HOUR ADDITIONAL...........................$ 39.77 28.54
----------------------------------------------------------------
PAIN0294-003 01/01/2024
Rates Fringes
PAINTER FOOTNOTE: SANDBLAST/SPRAY PAINTING:
$1.00 PER HOUR ADDITIONAL. WORK OVER 30 FEET
(DOES NOT INCLUDE WORK FROM A LIFT): $1.00 PER HOUR
ADDITIONAL..........................................$ 36.57 22.69
----------------------------------------------------------------
PAIN1176-001 07/01/2022
Rates Fringes
PARKING LOT STRIPING/HIGHWAY MARKING: HIGHWAY
IMPROVEMENT: GROUP 3 PROTECTIVE COATING, PAVEMENT
SEALING.............................................$ 35.11 17.62
PARKING LOT STRIPING/HIGHWAY MARKING: HIGHWAY
IMPROVEMENT: GROUP 1 STRIPER: LAYOUT AND
APPLICATION OF PAINTED TRAFFIC STRIPES AND MARKING;
HOT THERMO PLASTIC; TAPE, TRAFFIC STRIPES AND
MARKINGS............................................$ 40.83 17.62
PARKING LOT STRIPING/HIGHWAY MARKING: HIGHWAY
IMPROVEMEMT: GROUP 2 GAMECOURT & PLAYGROUND
INSTALLER...........................................$ 34.71 17.62
----------------------------------------------------------------
PLAS0300-005 07/01/2016
Rates Fringes
CEMENT MASON/CONCRETE FINISHER......................$ 32.15 23.27
----------------------------------------------------------------
PLUM0246-002 01/01/2025
Rates Fringes
PLUMBER & STEAMFITTER...............................$ 51.65 41.59
----------------------------------------------------------------
PLUM0355-003 07/01/2025
Rates Fringes
UNDERGROUND UTILITY WORKER / LANDSCAPE FITTER.......$ 36.01 18.50
----------------------------------------------------------------
TEAM0094-001 07/01/2025
Rates Fringes
TRUCK DRIVERS: GROUP 5: DUMP TRUCKS, 65 YDS. AND
OVER; HOLLAND HAULER; LOW BED HEAVY DUTY TRANSPORT
OVER 7 AXLES FOOTNOTES: ARTICULATED DUMP
TRUCK; BULK CEMENT SPREADER (WITH OR WITHOUT
AUGER); DUMPCRETE TRUCK; SKID TRUCK (DEBRIS BOX);
DRY PRE-BATCH CONCRETE MIX TRUCKS; DUMPSTER OR
SIMILAR TYPE; SLURRY TRUCK: USE DUMP TRUCK YARDAGE
RATE. HEATER PLANER; ASPHALT BURNER; SCARIFIER
BURNER; INDUSTRIAL LIFT TRUCK (MECHANICAL
TAILGATE); UTILITY AND CLEAN-UP TRUCK: USE
APPROPRIATE RATE FOR THE POWER UNIT OR THE
EQUIPMENT UTILIZED. TRUCK DRIVER
CLASSIFICATIONS.....................................$ 44.56 34.28
TRUCK DRIVERS: GROUP 4: DUMP TRUCKS, OVER 25 YDS.
AND UNDER 65 YDS.; WATER PULLS - DW 10'S, 20'S,
21'S AND OTHER SIMILAR EQUIPMENT WHEN PULLING
AQUA/PAK OR WATER TANK TRAILERS; HELICOPTER PILOTS
(WHEN TRANSPORTING MEN AND MATERIALS); LOWBEDK
HEAVY DUTY TRANSPORT UP TO INCLUDING 7 AXLES;
DW10'S, 20'S, 21'S AND OTHER SIMILAR CAT TYPE,
TERRA COBRA, LETOURNEAU PULLS, TOURNOROCKER, EUCLID
AND SIMILAR TYPE EQUIPMENT WHEN PULLING FUEL AND/OR
GREASE TANK TRAILERS OR OTHER MISCELLANEOUS
TRAILERS; VACUUM TRUCKS 7500 GALS AND OVER AND
TRUCK REPAIRMAN FOOTNOTES: ARTICULATED DUMP
TRUCK; BULK CEMENT SPREADER (WITH OR WITHOUT
AUGER); DUMPCRETE TRUCK; SKID TRUCK (DEBRIS BOX);
DRY PRE-BATCH CONCRETE MIX TRUCKS; DUMPSTER OR
SIMILAR TYPE; SLURRY TRUCK: USE DUMP TRUCK YARDAGE
RATE. HEATER PLANER; ASPHALT BURNER; SCARIFIER
BURNER; INDUSTRIAL LIFT TRUCK (MECHANICAL
TAILGATE); UTILITY AND CLEAN-UP TRUCK: USE
APPROPRIATE RATE FOR THE POWER UNIT OR THE
EQUIPMENT UTILIZED. TRUCK DRIVER
CLASSIFICATIONS.....................................$ 44.21 34.28
TRUCK DRIVERS: GROUP 3: DUMP TRUCKS, 8 YDS. AND
INCLUDING 24 YDS.; TRANSIT MIXERS, OVER 10 YDS.;
WATER TRUCKS, 7,000 GALS. AND OVER; JETTING TRUCKS,
7,000 GALS. AND OVER; VACUUM TRUCKS UNDER 7500
GALS. TRUCKS TOWING TILT BED OR FLAT BED PULL
TRAILERS; LOWBED HEAVY DUTY TRANSPORT; HEAVY DUTY
TRANSPORT TILLER PERSON; SELF- PROPELLED STREET
SWEEPER WITH SELF-CONTAINED REFUSE BIN; BOOM TRUCK
- HYDRO-LIFT OR SWEDISH TYPE EXTENSION OR
RETRACTING CRANE; P.B. OR SIMILAR TYPE SELF-LOADING
TRUCK; TIRE REPAIRPERSON; COMBINATION BOOTPERSON
AND ROAD OILER; DRY DISTRIBUTION TRUCK (A
BOOTPERSON WHEN EMPLOYED ON SUCH EQUIPMENT, SHALL
RECEIVE THE RATE SPECIFIED FOR THE CLASSIFICATION
OF ROAD OIL TRUCKS OR BOOTPERSON); AMMONIA NITRATE
DISTRIBUTOR, DRIVER AND MIXER; SNOW GO AND/OR PLOW
FOOTNOTES: ARTICULATED DUMP TRUCK; BULK CEMENT
SPREADER (WITH OR WITHOUT AUGER); DUMPCRETE TRUCK;
SKID TRUCK (DEBRIS BOX); DRY PRE-BATCH CONCRETE MIX
TRUCKS; DUMPSTER OR SIMILAR TYPE; SLURRY TRUCK: USE
DUMP TRUCK YARDAGE RATE. HEATER PLANER;
ASPHALT BURNER; SCARIFIER BURNER; INDUSTRIAL LIFT
TRUCK (MECHANICAL TAILGATE); UTILITY AND CLEAN-UP
TRUCK: USE APPROPRIATE RATE FOR THE POWER UNIT OR
THE EQUIPMENT UTILIZED. TRUCK
DRIVER CLASSIFICATIONS..............................$ 43.86 34.28
TRUCK DRIVERS: GROUP 2: DUMP TRUCKS, 6 YDS. AND
UNDER 8 YDS.; TRANSIT MIXERS, THROUGH 10 YDS.;
WATER TRUCKS, UNDER 7,000 GALS.; JETTING TRUCKS,
UNDER 7,000 GALS.; SINGLE-UNIT FLAT RACK (3-AXLE
UNIT); HIGHBED HEAVY DUTY TRANSPORT; SCISSOR TRUCK;
RUBBER-TIRED MUCK CAR (NOT SELF-LOADED);
RUBBER-TIRED TRUCK JUMBO; WINCH TRUCK AND ""A"" FRAME
DRIVERS; COMBINATION WINCH TRUCK WITH HOIST; ROAD
OIL TRUCK OR BOOTPERSON; BUGGYMOBILE; ROSS, HYSTER
AND SIMILAR STRADDLE CARRIERS; SMALL RUBBER-TIRED
TRACTOR FOOTNOTES: ARTICULATED DUMP TRUCK;
BULK CEMENT SPREADER (WITH OR WITHOUT AUGER);
DUMPCRETE TRUCK; SKID TRUCK (DEBRIS BOX); DRY
PRE-BATCH CONCRETE MIX TRUCKS; DUMPSTER OR SIMILAR
TYPE; SLURRY TRUCK: USE DUMP TRUCK YARDAGE RATE.
HEATER PLANER; ASPHALT BURNER; SCARIFIER BURNER;
INDUSTRIAL LIFT TRUCK (MECHANICAL TAILGATE);
UTILITY AND CLEAN-UP TRUCK: USE APPROPRIATE RATE
FOR THE POWER UNIT OR THE EQUIPMENT UTILIZED.
TRUCK DRIVER CLASSIFICATIONS...........$ 43.56 34.28
TRUCK DRIVERS: GROUP 1: DUMP TRUCKS, UNDER 6 YDS.;
SINGLE UNIT FLAT RACK (2- AXLE UNIT); NIPPER TRUCK
(WHEN FLAT RACK TRUCK IS USED APPROPRIATE FLAT RACK
SHALL APPLY); CONCRETE PUMP TRUCK (WHEN FLAT RACK
TRUCK IS USED APPROPRIATE FLAT RACK SHALL APPLY);
CONCRETE PUMP MACHINE; FORK LIFT AND LIFT JITNEYS;
FUEL AND/OR GREASE TRUCK DRIVER OR FUEL PERSON;
SNOW BUGGY; STEAM CLEANING; BUS OR PERSONHAUL
DRIVER; ESCORT OR PILOT CAR DRIVER; PICKUP TRUCK;
TEAMSTER OILER/GREASER AND/OR SERVICEPERSON; HOOK
TENDER (INCLUDING LOADING AND UNLOADING); TEAM
DRIVER; TOOL ROOM ATTENDANT (REFINERIES)
FOOTNOTES: ARTICULATED DUMP TRUCK; BULK CEMENT
SPREADER (WITH OR WITHOUT AUGER); DUMPCRETE TRUCK;
SKID TRUCK (DEBRIS BOX); DRY PRE-BATCH CONCRETE MIX
TRUCKS; DUMPSTER OR SIMILAR TYPE; SLURRY TRUCK: USE
DUMP TRUCK YARDAGE RATE. HEATER PLANER;
ASPHALT BURNER; SCARIFIER BURNER; INDUSTRIAL LIFT
TRUCK (MECHANICAL TAILGATE); UTILITY AND CLEAN-UP
TRUCK: USE APPROPRIATE RATE FOR THE POWER UNIT OR
THE EQUIPMENT UTILIZED. TRUCK
DRIVER CLASSIFICATIONS..............................$ 43.26 34.28
----------------------------------------------------------------
----------------------------------------------------------------------------------------------------
WELDERS - Receive rate prescribed for craft performing
operation to which welding is incidental.
================================================================
Note: Executive Order (EO) 13706, Establishing Paid Sick Leave
for Federal Contractors applies to all contracts subject to the
Davis-Bacon Act for which the contract is awarded (and any
solicitation was issued) on or after January 1, 2017. If this
contract is covered by the EO, the contractor must provide
employees with 1 hour of paid sick leave for every 30 hours
they work, up to 56 hours of paid sick leave each year.
Employees must be permitted to use paid sick leave for their
own illness, injury or other health-related needs, including
preventive care; to assist a family member (or person who is
like family to the employee) who is ill, injured, or has other
health-related needs, including preventive care; or for reasons
resulting from, or to assist a family member (or person who is
like family to the employee) who is a victim of, domestic
violence, sexual assault, or stalking. Additional information
on contractor requirements and worker protections under the EO
is available at https://www.dol.gov/agencies/whd/government-contracts.
Note: Executive Order 13658 generally applies to contracts subject
to the Davis-Bacon Act that were awarded on or between January 1,
2015 and January 29, 2022, and that have not been renewed or
extended on or after January 30, 2022. Executive Order 13658 does
not apply to contracts subject only to the Davis-Bacon Related Acts
regardless of when they were awarded. If a contract is subject to
Executive Order 13658, the contractor must pay all covered workers
at least $13.65 per hour (or the applicable wage rate listed on this
wage determination, if it is higher) for all hours spent performing on
the contract from May 11, 2026, through December 31, 2026. The
applicable Executive Order minimum wage rate will be adjusted annually.
Additional information on contractor requirements and worker
protections under Executive Order 13658 is available at
www.dol.gov/whd/govcontracts.
Unlisted classifications needed for work not included within
the scope of the classifications listed may be added after
award only as provided in the labor standards contract clauses
(29CFR 5.5 (a) (1) (iii)).
-----------------------------------------------------------------------------------------------------
The body of each wage determination lists the classifications
and wage rates that have been found to be prevailing for the
type(s) of construction and geographic area covered by the wage
determination. The classifications are listed in alphabetical
order under rate identifiers indicating whether the particular
rate is a union rate (current union negotiated rate), a survey
rate, a weighted union average rate, a state adopted rate, or a
supplemental classification rate.
Union Rate Identifiers
A four-letter identifier beginning with characters other than
�SU�, �UAVG�, �SA�, or �SC� denotes that a union rate was
prevailing for that classification in the survey. Example:
PLUM0198-005 07/01/2024. PLUM is an identifier of the union
whose collectively bargained rate prevailed in the survey for
this classification, which in this example would be Plumbers.
0198 indicates the local union number or district council
number where applicable, i.e., Plumbers Local 0198. The next
number, 005 in the example, is an internal number used in
processing the wage determination. The date, 07/01/2024 in the
example, is the effective date of the most current negotiated
rate.
Union prevailing wage rates are updated to reflect all changes
over time that are reported to WHD in the rates
in the collective bargaining agreement (CBA) governing the
classification.
Union Average Rate Identifiers
The UAVG identifier indicates that no single rate prevailed for
those classifications, but that 100% of the data reported for
the classifications reflected union rates. EXAMPLE:
UAVG-OH-0010 01/01/2024. UAVG indicates that the rate is a
weighted union average rate. OH indicates the State of Ohio.
The next number, 0010 in the example, is an internal number
used in producing the wage determination. The date, 01/01/2024
in the example, indicates the date the wage determination was
updated to reflect the most current union average rate.
A UAVG rate will be updated once a year, usually in January, to
reflect a weighted average of the current rates in the
collective bargaining agreements on which the rate is based.
Survey Rate Identifiers
The �SU� identifier indicates that either a single non-union
rate prevailed (as defined in 29 CFR 1.2) for this
classification in the survey or that the rate was derived by
computing a weighted average rate based on all the rates
reported in the survey for that classification. As a weighted
average rate includes all rates reported in the survey, it may
include both union and non-union rates. Example: SUFL2022-007
6/27/2024. SU indicates the rate is a single non-union
prevailing rate or a weighted average of survey data for that
classification. FL indicates the State of Florida. 2022 is the
year of the survey on which these classifications and rates are
based. The next number, 007 in the example, is an internal
number used in producing the wage determination. The date,
6/27/2024 in the example, indicates the survey completion date
for the classifications and rates under that identifier.
�SU� wage rates typically remain in effect until a new survey
is conducted. However, the Wage and Hour Division (WHD) has the
discretion to update such rates under 29 CFR 1.6(c)(1).
State Adopted Rate Identifiers
The �SA� identifier indicates that the classifications and
prevailing wage rates set by a state (or local) government were
adopted under 29 C.F.R 1.3(g)-(h). Example: SAME2023-007
01/03/2024. SA reflects that the rates are state adopted. ME
refers to the State of Maine. 2023 is the year during which the
state completed the survey on which the listed classifications
and rates are based. The next number, 007 in the example, is an
internal number used in producing the wage determination.
The date, 01/03/2024 in the example, reflects the date on which
the classifications and rates under the �SA� identifier took
effect under state law in the state from which the rates were
adopted.
-----------------------------------------------------------------------------------------------------
WAGE DETERMINATION APPEALS PROCESS
1) Has there been an initial decision in the matter? This can
be:
a) a survey underlying a wage determination
b) an existing published wage determination
c) an initial WHD letter setting forth a position on
a wage determination matter
d) an initial conformance (additional classification
and rate) determination
On survey related matters, initial contact, including requests
for summaries of surveys, should be directed to the WHD Branch
of Wage Surveys. Requests can be submitted via email to
davisbaconinfo@dol.gov or by mail to:
Branch of Wage Surveys
Wage and Hour Division
U.S. Department of Labor
200 Constitution Avenue, N.W.
Washington, DC 20210
Regarding any other wage determination matter such as
conformance decisions, requests for initial decisions should be
directed to the WHD Branch of Construction Wage Determinations.
Requests can be submitted via email to BCWD-Office@dol.gov or
by mail to:
Branch of Construction Wage Determinations
Wage and Hour Division
U.S. Department of Labor
200 Constitution Avenue, N.W.
Washington, DC 20210
2) If an initial decision has been issued, then any interested
party (those affected by the action) that disagrees with the
decision can request review and reconsideration from the Wage
and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7).
Requests for review and reconsideration can be submitted via
email to dba.reconsideration@dol.gov or by mail to:
Wage and Hour Administrator
U.S. Department of Labor
200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the
interested party's position and any information (wage payment
data, project description, area practice material, etc.) that
the requestor considers relevant to the issue.
3) If the decision of the Administrator is not favorable, an
interested party may appeal directly to the Administrative
Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board
U.S. Department of Labor
200 Constitution Avenue, N.W.
Washington, DC 20210.
================================================================
END OF GENERAL DECISION
"