Building, Heavy, Highway, Residential construction - Hawaii, revision 3, modified 2026-05-27
Parsed from the official text as a reading aid - zone pay, group definitions and footnotes in the full text below modify specific classifications. Identifier prefixes: union-agreement rates carry the local's id, SU marks DOL survey rates (how to read a determination).
Full official text of HI20260001 rev 3
"General Decision Number: HI20260001 05/27/2026
State: Hawaii
Construction Types: Building, Heavy, Highway and Residential
Counties: Hawaii Counties of
Hawaii, Honolulu, Kalawao, Kauai and
Maui
BUILDING CONSTRUCTION PROJECTS
RESIDENTIAL CONSTRUCTION PROJECTS (consisting of single family homes and apartments up to and including 4 stories)
HIGHWAY CONSTRUCTION PROJECTS
HEAVY CONSTRUCTION PROJECTS
Modification Number Publication Date
1 01/16/2026
2 05/18/2026
3 05/27/2026
ASBE0132-001 09/07/2025
Rates Fringes
ASBESTOS WORKERS/INSULATOR (INCLUDES APPLICATION OF
ALL INSULATING MATERIALS, PROTECTIVE COVERINGS,
COATINGS AND FINISHES TO ALL TYPES OF MECHANICAL
SYSTEMS. ALSO THE APPLICATION OF FIRESTOPPING
MATERIAL FOR WALL OPENINGS AND PENETRATIONS IN
WALLS, FLOORS, CEILINGS AND CURTAIN WALLS.).........$ 46.90 29.75
----------------------------------------------------------------
BOIL0627-005 01/01/2025
Rates Fringes
BOILERMAKER.........................................$ 49.37 31.25
----------------------------------------------------------------
BRHI0001-001 09/05/2023
Rates Fringes
BRICKLAYER: POINTERS, CAULKERS AND WEATHERPROOFERS..$ 48.28 32.23
BRICKLAYERS AND STONEMASONS.........................$ 48.03 32.23
----------------------------------------------------------------
BRHI0001-002 09/05/2023
Rates Fringes
TILE, MARBLE & TERRAZZO WORKER (TERRAZZO BASE
GRINDERS)...........................................$ 44.69 33.00
TILE, MARBLE & TERRAZZO WORKER (TERRAZZO FLOOR
GRINDERS AND TENDERS)...............................$ 43.14 33.00
TILE, MARBLE & TERRAZZO WORKER (TILE, MARBLE AND
TERRAZZO WORKERS)...................................$ 46.50 33.00
----------------------------------------------------------------
CARP0745-001 09/01/2025
Rates Fringes
CARPENTERS: (CARPENTERS; HARDWOOD FLOOR LAYERS;
PATENT SCAFFOLD ERECTORS (14 FT. AND OVER);
PILEDRIVERS; PNEUMATIC NAILERS; WOOD SHINGLERS AND
TRANSIT AND/OR LAYOUT MAN)..........................$ 55.50 29.81
CARPENTERS: MILLWRIGHTS AND MACHINE ERECTORS........$ 55.75 29.81
CARPENTERS: POWER SAW OPERATORS (2 H.P. AND OVER)...$ 55.65 29.81
----------------------------------------------------------------
CARP0745-002 09/01/2025
Rates Fringes
DRYWALL AND ACOUSTICAL WORKERS AND LATHERS..........$ 55.75 29.81
----------------------------------------------------------------
ELEC1186-001 08/24/2025
Rates Fringes
ELECTRICIANS........................................$ 56.55 33.16
ELECTRICIANS: CABLE SPLICERS........................$ 63.90 33.38
ELECTRICIANS: TELECOMMUNICATION WORKER..............$ 41.00 16.28
----------------------------------------------------------------
ELEC1186-002 08/24/2025
Rates Fringes
LINE CONSTRUCTION: CABLE SPLICERS...................$ 63.90 33.38
LINE CONSTRUCTION: GROUNDMEN/TRUCK DRIVERS..........$ 42.41 27.14
LINE CONSTRUCTION: HEAVY EQUIPMENT OPERATORS........$ 50.90 30.75
LINE CONSTRUCTION: LINEMEN..........................$ 56.55 33.16
LINE CONSTRUCTION: TELECOMMUNICATION WORKER.........$ 41.00 16.28
----------------------------------------------------------------
ELEV0126-001 01/01/2025
Rates Fringes
ELEVATOR MECHANIC A. VACATION: EMPLOYER
CONTRIBUTES 8% OF BASIC HOURLY RATE FOR 5 YEARS
SERVICE AND 6% OF BASIC HOURLY RATE FOR 6 MONTHS TO
5 YEARS SERVICE AS VACATION PAY CREDIT. B. PAID
HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY,
INDEPENDENCE DAY, LABOR DAY, VETERANS' DAY,
THANKSGIVING DAY, THE FRIDAY AFTER THANKSGIVING DAY
AND CHRISTMAS DAY...................................$ 73.85 38.44
----------------------------------------------------------------
ENGI0003-002 09/01/2025
Rates Fringes
DIVER TENDER: OTHER THAN AQUA LUNG..................$ 59.94 35.68
DIVER: (AQUA LUNG) (SCUBA) (over 30 feet)...........$ 81.72 35.68
DIVER: (AQUA LUNG) (SCUBA) (up to 30 feet)..........$ 72.35 35.68
DIVER: OTHER THAN AQUA LUNG.........................$ 81.72 35.68
HELICOPTER WORK, AIRBORNE HOIST OPERATOR FOR
HELICOPTER..........................................$ 61.52 35.68
HELICOPTER WORK: CO-PILOT OF HELICOPTER.............$ 61.66 35.68
HELICOPTER WORK: PILOT OF HELICOPTER................$ 62.83 35.68
POWER EQUIPMENT OPERATOR - TUNNEL WORK, GROUP 1:
FORK LIFT (UP TO AND INCLUDING 10 TONS); PARTSMAN
(HEAVY DUTY REPAIR SHOP PARTS ROOM WHEN NEEDED).
BOOMS AND/OR LEADS (HOURLY PREMIUMS): THE OPERATOR
OF A CRANE (UNDER 50 TONS) WITH A BOOM OF 80 FEET
OR MORE (INCLUDING JIB), OR OF A CRANE (UNDER 50
TONS) WITH LEADS OF 100 FEET OR MORE, SHALL RECEIVE
A PER HOUR PREMIUM FOR EACH HOUR WORKED ON SAID
CRANE (UNDER 50 TONS) IN ACCORDANCE WITH THE
FOLLOWING SCHEDULE: BOOMS OF 80 FEET UP TO BUT
NOT INCLUDING 130 FEET OR LEADS OF 100 FEET UP TO
BUT NOT INCLUDING 130 FEET
0.50 BOOMS AND/OR LEADS OF 130 FEET UP
TO BUT NOT INCLUDING 180 FEET 0.75 BOOMS
AND/OR LEADS OF 180 FEET UP TO AND INCLUDING 250
FEET 1.15 BOOMS AND/OR
LEADS OVER 250 FEET 1.50 THE OPERATOR OF A
CRANE (50 TONS AND OVER) WITH A BOOM OF 180 FEET OR
MORE (INCLUDING JIB) SHALL RECEIVE A PER HOUR
PREMIUM FOR EACH HOUR WORKED ON SAID CRANE (50 TONS
AND OVER) IN ACCORDANCE WITH THE FOLLOWING
SCHEDULE: BOOMS OF 180 FEET UP TO AND INCLUDING
250 FEET 1.25 BOOMS
OVER 250 FEET
1.75................................................$ 57.96 35.68
POWER EQUIPMENT OPERATOR - TUNNEL WORK, GROUP 2:
CONVEYOR OPERATOR (HANDLING BUILDING MATERIAL);
HYDRAULIC MONITOR; MIXER BOX OPERATOR (CONCRETE
PLANT). BOOMS AND/OR LEADS (HOURLY PREMIUMS): THE
OPERATOR OF A CRANE (UNDER 50 TONS) WITH A BOOM OF
80 FEET OR MORE (INCLUDING JIB), OR OF A CRANE
(UNDER 50 TONS) WITH LEADS OF 100 FEET OR MORE,
SHALL RECEIVE A PER HOUR PREMIUM FOR EACH HOUR
WORKED ON SAID CRANE (UNDER 50 TONS) IN ACCORDANCE
WITH THE FOLLOWING SCHEDULE: BOOMS OF 80 FEET UP
TO BUT NOT INCLUDING 130 FEET OR LEADS OF 100
FEET UP TO BUT NOT INCLUDING 130 FEET
0.50 BOOMS AND/OR LEADS OF 130
FEET UP TO BUT NOT INCLUDING 180 FEET
0.75 BOOMS AND/OR LEADS OF 180 FEET UP TO AND
INCLUDING 250 FEET 1.15
BOOMS AND/OR LEADS OVER 250 FEET 1.50 THE
OPERATOR OF A CRANE (50 TONS AND OVER) WITH A BOOM
OF 180 FEET OR MORE (INCLUDING JIB) SHALL RECEIVE A
PER HOUR PREMIUM FOR EACH HOUR WORKED ON SAID CRANE
(50 TONS AND OVER) IN ACCORDANCE WITH THE FOLLOWING
SCHEDULE: BOOMS OF 180 FEET UP TO AND INCLUDING
250 FEET 1.25 BOOMS
OVER 250 FEET
1.75................................................$ 58.07 35.68
POWER EQUIPMENT OPERATOR - TUNNEL WORK, GROUP 3:
BRAKEMAN; DECKHAND; FIREMAN; OILER;
OILER/GRADECHECKER; SIGNALMAN; SWITCHMAN; HIGHLINE
CABLEWAY SIGNALMAN; BARGEMAN; BUNKERMAN; CONCRETE
CURING MACHINE (SELF-PROPELLED, AUTOMATICALLY
APPLIED UNIT ON STREETS, HIGHWAYS, AIRPORTS AND
CANALS); LEVEEMAN; ROLLER (5 TONS AND UNDER);
TUGGER HOIST. BOOMS AND/OR LEADS (HOURLY
PREMIUMS): THE OPERATOR OF A CRANE (UNDER 50 TONS)
WITH A BOOM OF 80 FEET OR MORE (INCLUDING JIB), OR
OF A CRANE (UNDER 50 TONS) WITH LEADS OF 100 FEET
OR MORE, SHALL RECEIVE A PER HOUR PREMIUM FOR EACH
HOUR WORKED ON SAID CRANE (UNDER 50 TONS) IN
ACCORDANCE WITH THE FOLLOWING SCHEDULE: BOOMS OF
80 FEET UP TO BUT NOT INCLUDING 130 FEET OR
LEADS OF 100 FEET UP TO BUT NOT INCLUDING 130
FEET 0.50 BOOMS
AND/OR LEADS OF 130 FEET UP TO BUT NOT INCLUDING
180 FEET 0.75 BOOMS AND/OR LEADS OF 180
FEET UP TO AND INCLUDING 250 FEET
1.15 BOOMS AND/OR LEADS OVER 250 FEET
1.50 THE OPERATOR OF A CRANE (50 TONS AND OVER)
WITH A BOOM OF 180 FEET OR MORE (INCLUDING JIB)
SHALL RECEIVE A PER HOUR PREMIUM FOR EACH HOUR
WORKED ON SAID CRANE (50 TONS AND OVER) IN
ACCORDANCE WITH THE FOLLOWING SCHEDULE: BOOMS OF
180 FEET UP TO AND INCLUDING 250 FEET
1.25 BOOMS OVER 250 FEET
1.75......................$ 58.24 35.68
POWER EQUIPMENT OPERATOR - TUNNEL WORK, GROUP 4:
BOOM TRUCK OR DUAL PURPOSE ""A"" FRAME TRUCK (5 TONS
OR LESS); CONCRETE PLACING BOOM (BUILDING
CONSTRUCTION); DINKY OPERATOR; ELEVATOR OPERATOR;
HOIST AND/OR WINCH (ONE DRUM); STRADDLE TRUCK (ROSS
CARRIER, HYSTER AND SIMILAR BOOMS AND/OR LEADS
(HOURLY PREMIUMS): THE OPERATOR OF A CRANE (UNDER
50 TONS) WITH A BOOM OF 80 FEET OR MORE (INCLUDING
JIB), OR OF A CRANE (UNDER 50 TONS) WITH LEADS OF
100 FEET OR MORE, SHALL RECEIVE A PER HOUR PREMIUM
FOR EACH HOUR WORKED ON SAID CRANE (UNDER 50 TONS)
IN ACCORDANCE WITH THE FOLLOWING SCHEDULE: BOOMS
OF 80 FEET UP TO BUT NOT INCLUDING 130 FEET OR
LEADS OF 100 FEET UP TO BUT NOT INCLUDING 130
FEET 0.50 BOOMS
AND/OR LEADS OF 130 FEET UP TO BUT NOT INCLUDING
180 FEET 0.75 BOOMS AND/OR LEADS OF 180
FEET UP TO AND INCLUDING 250 FEET
1.15 BOOMS AND/OR LEADS OVER 250 FEET
1.50 THE OPERATOR OF A CRANE (50 TONS AND OVER)
WITH A BOOM OF 180 FEET OR MORE (INCLUDING JIB)
SHALL RECEIVE A PER HOUR PREMIUM FOR EACH HOUR
WORKED ON SAID CRANE (50 TONS AND OVER) IN
ACCORDANCE WITH THE FOLLOWING SCHEDULE: BOOMS OF
180 FEET UP TO AND INCLUDING 250 FEET
1.25 BOOMS OVER 250 FEET
1.75......................$ 58.51 35.68
POWER EQUIPMENT OPERATOR - TUNNEL WORK, GROUP 5:
ASPHALT PLANT FIREMAN; COMPRESSORS, PUMPS,
GENERATORS AND WELDING MACHINES (""BANK"" OF 9 OR
MORE, INDIVIDUALLY OR COLLECTIVELY); CONCRETE PUMPS
OR PUMPCRETE GUNS; LUBRICATION AND SERVICE ENGINEER
(GREASE RACK); SCREEDMAN. BOOMS AND/OR LEADS
(HOURLY PREMIUMS): THE OPERATOR OF A CRANE (UNDER
50 TONS) WITH A BOOM OF 80 FEET OR MORE (INCLUDING
JIB), OR OF A CRANE (UNDER 50 TONS) WITH LEADS OF
100 FEET OR MORE, SHALL RECEIVE A PER HOUR PREMIUM
FOR EACH HOUR WORKED ON SAID CRANE (UNDER 50 TONS)
IN ACCORDANCE WITH THE FOLLOWING SCHEDULE: BOOMS
OF 80 FEET UP TO BUT NOT INCLUDING 130 FEET OR
LEADS OF 100 FEET UP TO BUT NOT INCLUDING 130
FEET 0.50 BOOMS
AND/OR LEADS OF 130 FEET UP TO BUT NOT INCLUDING
180 FEET 0.75 BOOMS AND/OR LEADS OF 180
FEET UP TO AND INCLUDING 250 FEET
1.15 BOOMS AND/OR LEADS OVER 250 FEET
1.50 THE OPERATOR OF A CRANE (50 TONS AND OVER)
WITH A BOOM OF 180 FEET OR MORE (INCLUDING JIB)
SHALL RECEIVE A PER HOUR PREMIUM FOR EACH HOUR
WORKED ON SAID CRANE (50 TONS AND OVER) IN
ACCORDANCE WITH THE FOLLOWING SCHEDULE: BOOMS OF
180 FEET UP TO AND INCLUDING 250 FEET
1.25 BOOMS OVER 250 FEET
1.75......................$ 58.82 35.68
POWER EQUIPMENT OPERATOR - TUNNEL WORK, GROUP 6:
BOOM TRUCK OR DUAL PURPOSE ""A""FRAME TRUCK (OVER 5
TONS); COMBINATION LOADER/BACKHOE (UP TO AND
INCLUDING 3/4 CU. YD.); CONCRETE BATCH PLANTS (WET
OR DRY); CONCRETE CUTTER, GROOVER AND/OR GRINDER
(SELF-PROPELLED UNIT ON STREETS, HIGHWAYS,
AIRPORTS, AND CANALS); CONVEYOR OR CONCRETE PUMP
(TRUCK OR EQUIPMENT MOUNTED); DRILLING MACHINERY
(NOT TO APPLY TO WATERLINERS, WAGON DRILLS OR JACK
HAMMERS); FORK LIFT (OVER 10 TONS); LOADER (UP TO
AND INCLUDING 3 AND 1/2 CU. YDS); LULL HIGH LIFT
(UNDER 40 FEET); LUBRICATION AND SERVICE ENGINEER
(MOBILE); MAGINNIS INTERNAL FULL SLAB VIBRATOR (ON
AIRPORTS, HIGHWAYS, CANALS AND WAREHOUSES); MAN OR
MATERIAL HOIST; MECHANICAL CONCRETE FINISHER (LARGE
CLARY, JOHNSON BIDWELL, BRIDGE DECK AND SIMILAR);
MOBILE TRUCK CRANE DRIVER; PORTABLE SHOTBLAST
CONCRETE CLEANING MACHINE; PORTABLE BORING MACHINE
(UNDER STREETS, HIGHWAYS, ETC.); PORTABLE CRUSHER;
POWER JUMBO OPERATOR (SETTING SLIP FORMS, ETC., IN
TUNNELS); ROLLERS (OVER 5 TONS); SELF-PROPELLED
COMPACTOR (SINGLE ENGINE); SELF-PROPELLED PAVEMENT
BREAKER; SKIDSTEER LOADER WITH ATTACHMENTS; SLIP
FORM PUMPS (POWER DRIVEN BY HYDRAULIC, ELECTRIC,
AIR, GAS, ETC., LIFTING DEVICE FOR CONCRETE FORMS);
SMALL RUBBER TIRED TRACTORS; TRENCHER (UP TO AND
INCLUDING 6 FEET); UNDERBRIDGE PERSONNEL AERIAL
PLATFORM (50 FEET OF PLATFORM OR LESS). BOOMS
AND/OR LEADS (HOURLY PREMIUMS): THE OPERATOR OF A
CRANE (UNDER 50 TONS) WITH A BOOM OF 80 FEET OR
MORE (INCLUDING JIB), OR OF A CRANE (UNDER 50 TONS)
WITH LEADS OF 100 FEET OR MORE, SHALL RECEIVE A PER
HOUR PREMIUM FOR EACH HOUR WORKED ON SAID CRANE
(UNDER 50 TONS) IN ACCORDANCE WITH THE FOLLOWING
SCHEDULE: BOOMS OF 80 FEET UP TO BUT NOT
INCLUDING 130 FEET OR LEADS OF 100 FEET UP TO BUT
NOT INCLUDING 130 FEET
0.50 BOOMS AND/OR LEADS OF 130 FEET UP TO
BUT NOT INCLUDING 180 FEET 0.75 BOOMS
AND/OR LEADS OF 180 FEET UP TO AND INCLUDING 250
FEET 1.15 BOOMS AND/OR
LEADS OVER 250 FEET 1.50 THE OPERATOR OF A
CRANE (50 TONS AND OVER) WITH A BOOM OF 180 FEET OR
MORE (INCLUDING JIB) SHALL RECEIVE A PER HOUR
PREMIUM FOR EACH HOUR WORKED ON SAID CRANE (50 TONS
AND OVER) IN ACCORDANCE WITH THE FOLLOWING
SCHEDULE: BOOMS OF 180 FEET UP TO AND INCLUDING
250 FEET 1.25 BOOMS
OVER 250 FEET
1.75................................................$ 59.47 35.68
POWER EQUIPMENT OPERATOR - TUNNEL WORK, GROUP 7:
CRUSHER PLANT ENGINEER, DOZER (D-4, CASE 450, JOHN
DEERE 450, AND SIMILAR); DUAL DRUM MIXER, EXTEND
LIFT; HOIST AND/OR WINCH (2 DRUMS); LOADER (OVER 3
AND 1/2 CU. YDS. UP TO AND INCLUDING 6 YARDS.);
MECHANICAL FINISHER OR SPREADER MACHINE (ASPHALT),
(BARBER GREENE AND SIMILAR) (SCREEDMAN REQUIRED);
MINE OR SHAFT HOIST; MOBILE CONCRETE MIXER (OVER 5
TONS); PIPE BENDING MACHINE (PIPELINES ONLY); PIPE
CLEANING MACHINE (TRACTOR PROPELLED AND SUPPORTED);
PIPE WRAPPING MACHINE (TRACTOR PROPELLED AND
SUPPORTED); ROLLER OPERATOR (ASPHALT);
SELF-PROPELLED ELEVATING GRADE PLANE; SLUSHER
OPERATOR; TRACTOR (WITH BOOM) (D-6, OR SIMILAR);
TRENCHER (OVER 6 FEET AND LESS THAN 200 H.P.);
WATER TANKER (PULLED BY EUCLIDS, T-PULLS, DW-10, 20
OR 21, OR SIMILAR); WINCHMAN (STERN WINCH ON
DREDGE). BOOMS AND/OR LEADS (HOURLY PREMIUMS):
THE OPERATOR OF A CRANE (UNDER 50 TONS) WITH A BOOM
OF 80 FEET OR MORE (INCLUDING JIB), OR OF A CRANE
(UNDER 50 TONS) WITH LEADS OF 100 FEET OR MORE,
SHALL RECEIVE A PER HOUR PREMIUM FOR EACH HOUR
WORKED ON SAID CRANE (UNDER 50 TONS) IN ACCORDANCE
WITH THE FOLLOWING SCHEDULE: BOOMS OF 80 FEET UP
TO BUT NOT INCLUDING 130 FEET OR LEADS OF 100
FEET UP TO BUT NOT INCLUDING 130 FEET
0.50 BOOMS AND/OR LEADS OF 130
FEET UP TO BUT NOT INCLUDING 180 FEET
0.75 BOOMS AND/OR LEADS OF 180 FEET UP TO AND
INCLUDING 250 FEET 1.15
BOOMS AND/OR LEADS OVER 250 FEET 1.50 THE
OPERATOR OF A CRANE (50 TONS AND OVER) WITH A BOOM
OF 180 FEET OR MORE (INCLUDING JIB) SHALL RECEIVE A
PER HOUR PREMIUM FOR EACH HOUR WORKED ON SAID CRANE
(50 TONS AND OVER) IN ACCORDANCE WITH THE FOLLOWING
SCHEDULE: BOOMS OF 180 FEET UP TO AND INCLUDING
250 FEET 1.25 BOOMS
OVER 250 FEET
1.75................................................$ 59.79 35.68
POWER EQUIPMENT OPERATOR - TUNNEL WORK, GROUP 8:
ASPHALT PLANT OPERATOR; BARGE MATE (SEAGOING);
CAST-IN-PLACE PIPE LAYING MACHINE; CONCRETE BATCH
PLANT (MULTIPLE UNITS); CONVEYOR OPERATOR (TUNNEL);
DECKMATE; DOZER (D-6 AND SIMILAR); FINISHING
MACHINE OPERATOR (AIRPORTS AND HIGHWAYS);
GRADESETTER; KOLMAN LOADER (AND SIMILAR); MUCKING
MACHINE (CRAWLER-TYPE); MUCKING MACHINE
(CONVEYOR-TYPE); NO-JOINT PIPE LAYING MACHINE;
PORTABLE CRUSHING AND SCREENING PLANT; POWER BLADE
OPERATOR (UNDER 12); SAURMAN TYPE DRAGLINE (UP TO
AND INCLUDING 5 YDS.); STATIONARY PIPE WRAPPING,
CLEANING AND BENDING MACHINE; SURFACE HEATER AND
PLANER OPERATOR, TRACTOR (D-6 AND SIMILAR);
TRI-BATCH PAVER; TUNNEL BADGER; TUNNEL MOLE AND/OR
BORING MACHINE OPERATOR UNDERBRIDGE PERSONNEL
AERIAL PLATFORM (OVER 50 FEET OF PLATFORM). BOOMS
AND/OR LEADS (HOURLY PREMIUMS): THE OPERATOR OF A
CRANE (UNDER 50 TONS) WITH A BOOM OF 80 FEET OR
MORE (INCLUDING JIB), OR OF A CRANE (UNDER 50 TONS)
WITH LEADS OF 100 FEET OR MORE, SHALL RECEIVE A PER
HOUR PREMIUM FOR EACH HOUR WORKED ON SAID CRANE
(UNDER 50 TONS) IN ACCORDANCE WITH THE FOLLOWING
SCHEDULE: BOOMS OF 80 FEET UP TO BUT NOT
INCLUDING 130 FEET OR LEADS OF 100 FEET UP TO BUT
NOT INCLUDING 130 FEET
0.50 BOOMS AND/OR LEADS OF 130 FEET UP TO
BUT NOT INCLUDING 180 FEET 0.75 BOOMS
AND/OR LEADS OF 180 FEET UP TO AND INCLUDING 250
FEET 1.15 BOOMS AND/OR
LEADS OVER 250 FEET 1.50 THE OPERATOR OF A
CRANE (50 TONS AND OVER) WITH A BOOM OF 180 FEET OR
MORE (INCLUDING JIB) SHALL RECEIVE A PER HOUR
PREMIUM FOR EACH HOUR WORKED ON SAID CRANE (50 TONS
AND OVER) IN ACCORDANCE WITH THE FOLLOWING
SCHEDULE: BOOMS OF 180 FEET UP TO AND INCLUDING
250 FEET 1.25 BOOMS
OVER 250 FEET
1.75................................................$ 59.90 35.68
POWER EQUIPMENT OPERATOR - TUNNEL WORK, GROUP 9:
COMBINATION MIXER AND COMPRESSOR (GUNITE); DO-MOR
LOADERAND ADAMS ELEGRADER; DOZER (D-7 OR EQUAL);
WHEEL AND/OR LADDER TRENCHER (OVER 6 FEET AND 200
TO 749 H.P.). BOOMS AND/OR LEADS (HOURLY
PREMIUMS): THE OPERATOR OF A CRANE (UNDER 50 TONS)
WITH A BOOM OF 80 FEET OR MORE (INCLUDING JIB), OR
OF A CRANE (UNDER 50 TONS) WITH LEADS OF 100 FEET
OR MORE, SHALL RECEIVE A PER HOUR PREMIUM FOR EACH
HOUR WORKED ON SAID CRANE (UNDER 50 TONS) IN
ACCORDANCE WITH THE FOLLOWING SCHEDULE: BOOMS OF
80 FEET UP TO BUT NOT INCLUDING 130 FEET OR
LEADS OF 100 FEET UP TO BUT NOT INCLUDING 130
FEET 0.50 BOOMS
AND/OR LEADS OF 130 FEET UP TO BUT NOT INCLUDING
180 FEET 0.75 BOOMS AND/OR LEADS OF 180
FEET UP TO AND INCLUDING 250 FEET
1.15 BOOMS AND/OR LEADS OVER 250 FEET
1.50 THE OPERATOR OF A CRANE (50 TONS AND OVER)
WITH A BOOM OF 180 FEET OR MORE (INCLUDING JIB)
SHALL RECEIVE A PER HOUR PREMIUM FOR EACH HOUR
WORKED ON SAID CRANE (50 TONS AND OVER) IN
ACCORDANCE WITH THE FOLLOWING SCHEDULE: BOOMS OF
180 FEET UP TO AND INCLUDING 250 FEET
1.25 BOOMS OVER 250 FEET
1.75......................$ 60.01 35.68
POWER EQUIPMENT OPERATOR - TUNNEL WORK, GROUP 9A:
DOZER (D-8 AND SIMILAR); GRADESETTER (WHEN REQUIRED
BY THE CONTRACTOR TO WORK FROM DRAWINGS, PLANS OR
SPECIFICATIONS WITHOUT THE DIRECT SUPERVISION OF A
FOREMAN OR SUPERINTENDENT); PUSH CAT; SCRAPERS (UP
TO AND INCLUDING 20 CU. YDS); SELF-PROPELLED
COMPACTOR WITH DOZER; SELF-PROPELLED, RUBBER-TIRED
EARTHMOVING EQUIPMENT (UP TO AND INCLUDING 20 CU.
YDS) (621 BAND AND SIMILAR); SHEEP'S FOOT; TRACTOR
(D-8 AND SIMILAR); TRACTORS WITH BOOM (LARGER THAN
D-6, AND SIMILAR). BOOMS AND/OR LEADS (HOURLY
PREMIUMS): THE OPERATOR OF A CRANE (UNDER 50 TONS)
WITH A BOOM OF 80 FEET OR MORE (INCLUDING JIB), OR
OF A CRANE (UNDER 50 TONS) WITH LEADS OF 100 FEET
OR MORE, SHALL RECEIVE A PER HOUR PREMIUM FOR EACH
HOUR WORKED ON SAID CRANE (UNDER 50 TONS) IN
ACCORDANCE WITH THE FOLLOWING SCHEDULE: BOOMS OF
80 FEET UP TO BUT NOT INCLUDING 130 FEET OR
LEADS OF 100 FEET UP TO BUT NOT INCLUDING 130
FEET 0.50 BOOMS
AND/OR LEADS OF 130 FEET UP TO BUT NOT INCLUDING
180 FEET 0.75 BOOMS AND/OR LEADS OF 180
FEET UP TO AND INCLUDING 250 FEET
1.15 BOOMS AND/OR LEADS OVER 250 FEET
1.50 THE OPERATOR OF A CRANE (50 TONS AND OVER)
WITH A BOOM OF 180 FEET OR MORE (INCLUDING JIB)
SHALL RECEIVE A PER HOUR PREMIUM FOR EACH HOUR
WORKED ON SAID CRANE (50 TONS AND OVER) IN
ACCORDANCE WITH THE FOLLOWING SCHEDULE: BOOMS OF
180 FEET UP TO AND INCLUDING 250 FEET
1.25 BOOMS OVER 250 FEET
1.75......................$ 60.24 35.68
POWER EQUIPMENT OPERATOR - TUNNEL WORK, GROUP 10:
CHICAGO BOOM; COLD PLANERS; HEAVY DUTY REPAIRMAN OR
WELDER; HOIST AND/OR WINCH (3 DRUMS); HYDRAULIC
SKOOPER (KOEHRING AND SIMILAR); LOADER (OVER 6 CU.
YDS. UP TO AND INCLUDING 12 CU. YDS.); SAURMAN TYPE
DRAGLINE (OVER 5 CU. YDS.); SELF-PROPELLED,
RUBBER-TIRED EARTHMOVING EQUIPMENT (OVER 20 CU.
YDS. UP TO AND INCLUDING 31 CU. YDS.) (637D AND
SIMILAR); SOIL STABILIZER (P & H OR EQUAL);
SUB-GRADER (GURRIES OR OTHER AUTOMATIC TYPE);
TRACTORS (D-9 OR EQUIVALENT, ALL ATTACHMENTS);
TRACTOR (TANDEM SCRAPER); WATCH ENGINEER. BOOMS
AND/OR LEADS (HOURLY PREMIUMS): THE OPERATOR OF A
CRANE (UNDER 50 TONS) WITH A BOOM OF 80 FEET OR
MORE (INCLUDING JIB), OR OF A CRANE (UNDER 50 TONS)
WITH LEADS OF 100 FEET OR MORE, SHALL RECEIVE A PER
HOUR PREMIUM FOR EACH HOUR WORKED ON SAID CRANE
(UNDER 50 TONS) IN ACCORDANCE WITH THE FOLLOWING
SCHEDULE: BOOMS OF 80 FEET UP TO BUT NOT
INCLUDING 130 FEET OR LEADS OF 100 FEET UP TO BUT
NOT INCLUDING 130 FEET
0.50 BOOMS AND/OR LEADS OF 130 FEET UP TO
BUT NOT INCLUDING 180 FEET 0.75 BOOMS
AND/OR LEADS OF 180 FEET UP TO AND INCLUDING 250
FEET 1.15 BOOMS AND/OR
LEADS OVER 250 FEET 1.50 THE OPERATOR OF A
CRANE (50 TONS AND OVER) WITH A BOOM OF 180 FEET OR
MORE (INCLUDING JIB) SHALL RECEIVE A PER HOUR
PREMIUM FOR EACH HOUR WORKED ON SAID CRANE (50 TONS
AND OVER) IN ACCORDANCE WITH THE FOLLOWING
SCHEDULE: BOOMS OF 180 FEET UP TO AND INCLUDING
250 FEET 1.25 BOOMS
OVER 250 FEET
1.75................................................$ 60.30 35.68
POWER EQUIPMENT OPERATOR - TUNNEL WORK, GROUP 10A:
BOAT OPERATOR; CABLE-OPERATED CRAWLER CRANE (UP TO
AND INCLUDING 25 TONS); CABLE-OPERATED POWER
SHOVEL, CLAMSHELL, DRAGLINE AND BACKHOE (UP TO AND
INCLUDING 1 CU. YD.); DOZER D9-L; DOZER (D-10, HD41
AND SIMILAR) (ALL ATTACHMENTS); GRADALL (UP TO AND
INCLUDING 1 CU. YD.); HYDRAULIC BACKHOE (OVER 3/4
CU. YDS. UP TO AND INCLUDING 2 CU. YDS.); MOBILE
TRUCK CRANE OPERATOR (UP TO AND INCLUDING 25 TONS)
(MOBILE TRUCK CRANE DRIVER REQUIRED);
SELF-PROPELLED BOOM TYPE LIFTING DEVICE (CENTER
MOUNT) (UP TO AND INCLUDING 25 TONS) (GROVE, DROTT,
P&H, PETTIBONE AND SIMILAR; TRENCHER (OVER 6 FEET
AND 750 H.P. OR MORE); WATCH ENGINEER (STEAM OR
ELECTRIC). BOOMS AND/OR LEADS (HOURLY PREMIUMS):
THE OPERATOR OF A CRANE (UNDER 50 TONS) WITH A BOOM
OF 80 FEET OR MORE (INCLUDING JIB), OR OF A CRANE
(UNDER 50 TONS) WITH LEADS OF 100 FEET OR MORE,
SHALL RECEIVE A PER HOUR PREMIUM FOR EACH HOUR
WORKED ON SAID CRANE (UNDER 50 TONS) IN ACCORDANCE
WITH THE FOLLOWING SCHEDULE: BOOMS OF 80 FEET UP
TO BUT NOT INCLUDING 130 FEET OR LEADS OF 100
FEET UP TO BUT NOT INCLUDING 130 FEET
0.50 BOOMS AND/OR LEADS OF 130
FEET UP TO BUT NOT INCLUDING 180 FEET
0.75 BOOMS AND/OR LEADS OF 180 FEET UP TO AND
INCLUDING 250 FEET 1.15
BOOMS AND/OR LEADS OVER 250 FEET 1.50 THE
OPERATOR OF A CRANE (50 TONS AND OVER) WITH A BOOM
OF 180 FEET OR MORE (INCLUDING JIB) SHALL RECEIVE A
PER HOUR PREMIUM FOR EACH HOUR WORKED ON SAID CRANE
(50 TONS AND OVER) IN ACCORDANCE WITH THE FOLLOWING
SCHEDULE: BOOMS OF 180 FEET UP TO AND INCLUDING
250 FEET 1.25 BOOMS
OVER 250 FEET
1.75................................................$ 60.45 35.68
POWER EQUIPMENT OPERATOR - TUNNEL WORK, GROUP 11:
AUTOMATIC SLIP FORM PAVER (CONCRETE OR ASPHALT);
BAND WAGON (IN CONJUNCTION WITH WHEEL EXCAVATOR);
CABLE-OPERATED CRAWLER CRANES (OVER 25 TONS BUT
LESS THAN 50 TONS); CABLE-OPERATED POWER SHOVEL,
CLAMSHELL, DRAGLINE AND BACKHOE (OVER 1 CU. YD. UP
TO 7 CU. YDS.); GRADALL (OVER 1 CU. YDS. UP TO 7
CU. YDS.); DW-10, 20, ETC. (TANDEM); EARTHMOVING
MACHINES (MULTIPLE PROPULSION POWER UNITS AND 2 OR
MORE SCRAPERS) (UP TO AND INCLUDING 35 CU. YDS.,""
STRUCK"" M.R.C.); HIGHLINE CABLEWAY; HYDRAULIC
BACKHOE (OVER 2 CU. YDS. UP TO AND INCLUDING 4 CU.
YDS.); LEVERMAN; LIFT SLAB MACHINE; LOADER (OVER 12
CU. YDS); MASTER BOAT OPERATOR; MOBILE TRUCK CRANE
OPERATOR (OVER 25 TONS BUT LESS THAN 50 TONS);
(MOBILE TRUCK CRANE DRIVER REQUIRED); PRE-STRESS
WIRE WRAPPING MACHINE; SELF-PROPELLED BOOM-TYPE
LIFTING DEVICE (CENTER MOUNT) (OVER 25 TONS M.R.C);
SELF-PROPELLED COMPACTOR (WITH MULTIPLE-PROPULSION
POWER UNITS); SINGLE ENGINE RUBBER TIRED
EARTHMOVING MACHINE (WITH TANDEM SCRAPER); TANDEM
CATS; TRENCHER (PULLING ATTACHED SHIELD). BOOMS
AND/OR LEADS (HOURLY PREMIUMS): THE OPERATOR OF A
CRANE (UNDER 50 TONS) WITH A BOOM OF 80 FEET OR
MORE (INCLUDING JIB), OR OF A CRANE (UNDER 50 TONS)
WITH LEADS OF 100 FEET OR MORE, SHALL RECEIVE A PER
HOUR PREMIUM FOR EACH HOUR WORKED ON SAID CRANE
(UNDER 50 TONS) IN ACCORDANCE WITH THE FOLLOWING
SCHEDULE: BOOMS OF 80 FEET UP TO BUT NOT
INCLUDING 130 FEET OR LEADS OF 100 FEET UP TO BUT
NOT INCLUDING 130 FEET
0.50 BOOMS AND/OR LEADS OF 130 FEET UP TO
BUT NOT INCLUDING 180 FEET 0.75 BOOMS
AND/OR LEADS OF 180 FEET UP TO AND INCLUDING 250
FEET 1.15 BOOMS AND/OR
LEADS OVER 250 FEET 1.50 THE OPERATOR OF A
CRANE (50 TONS AND OVER) WITH A BOOM OF 180 FEET OR
MORE (INCLUDING JIB) SHALL RECEIVE A PER HOUR
PREMIUM FOR EACH HOUR WORKED ON SAID CRANE (50 TONS
AND OVER) IN ACCORDANCE WITH THE FOLLOWING
SCHEDULE: BOOMS OF 180 FEET UP TO AND INCLUDING
250 FEET 1.25 BOOMS
OVER 250 FEET
1.75................................................$ 60.60 35.68
POWER EQUIPMENT OPERATOR - TUNNEL WORK, GROUP 12:
CLAMSHELL OR DIPPER OPERATOR; DERRICKS; DRILL RIGS;
MULTI-PROPULSION EARTHMOVING MACHINES (2 OR MORE
SCRAPERS) (OVER 35 CU. YDS ""STRUCK""M.R.C.);
OPERATORS (DERRICKS, PILEDRIVERS AND CRANES); POWER
SHOVELS AND DRAGLINES (7 CU. YDS. M.R.C. AND OVER);
SELF-PROPELLED RUBBER-TIRED EARTHMOVING EQUIPMENT
(OVER 31 CU. YDS.) (657B AND SIMILAR); WHEEL
EXCAVATOR (UP TO AND INCLUDING 750 CU. YDS. PER
HOUR); WHEEL EXCAVATOR (OVER 750 CU. YDS. PER
HOUR). ............................................$ 60.96 35.68
POWER EQUIPMENT OPERATOR - TUNNEL WORK, GROUP 12A:
DOZER (D-11 OR SIMILAR OR LARGER); HYDRAULIC
EXCAVATORS (OVER 4 CU. YDS.); LIFTING CRANES (50
TONS AND OVER); PIONEERING DOZER/BACKHOE (INITIAL
CLEARING AND EXCAVATION FOR THE PURPOSE OF
PROVIDING ACCESS FOR OTHER EQUIPMENT WHERE THE
TERRAIN WORKED INVOLVES 1-TO-1 SLOPES THAT ARE 50
FEET IN HEIGHT OR DEPTH, THE SCOPE OF THIS WORK
DOES NOT INCLUDE NORMAL CLEARING AND GRUBBING ON
USUAL HILLY TERRAIN NOR THE EXCAVATION WORK ONCE
THE ACCESS IS PROVIDED); POWER BLADE OPERATOR (CAT
12 OR EQUIVALENT OR OVER); STRADDLE LIFTS (OVER 50
TONS); TOWER CRANE, MOBILE; TRAVELING TRUSS CRANES;
UNIVERSAL, LIEBHER, LINDEN, AND SIMILAR TYPES OF
TOWER CRANES (IN THE ERECTION, DISMANTLING, AND
MOVING OF EQUIPMENT THERE SHALL BE AN ADDITIONAL
OPERATING ENGINEER OR HEAVY DUTY REPAIRMAN); YO-YO
CAT OR DOZER. BOOMS AND/OR LEADS (HOURLY
PREMIUMS): THE OPERATOR OF A CRANE (UNDER 50 TONS)
WITH A BOOM OF 80 FEET OR MORE (INCLUDING JIB), OR
OF A CRANE (UNDER 50 TONS) WITH LEADS OF 100 FEET
OR MORE, SHALL RECEIVE A PER HOUR PREMIUM FOR EACH
HOUR WORKED ON SAID CRANE (UNDER 50 TONS) IN
ACCORDANCE WITH THE FOLLOWING SCHEDULE: BOOMS OF
80 FEET UP TO BUT NOT INCLUDING 130 FEET OR
LEADS OF 100 FEET UP TO BUT NOT INCLUDING 130
FEET 0.50 BOOMS
AND/OR LEADS OF 130 FEET UP TO BUT NOT INCLUDING
180 FEET 0.75 BOOMS AND/OR LEADS OF 180
FEET UP TO AND INCLUDING 250 FEET
1.15 BOOMS AND/OR LEADS OVER 250 FEET
1.50 THE OPERATOR OF A CRANE (50 TONS AND OVER)
WITH A BOOM OF 180 FEET OR MORE (INCLUDING JIB)
SHALL RECEIVE A PER HOUR PREMIUM FOR EACH HOUR
WORKED ON SAID CRANE (50 TONS AND OVER) IN
ACCORDANCE WITH THE FOLLOWING SCHEDULE: BOOMS OF
180 FEET UP TO AND INCLUDING 250 FEET
1.25 BOOMS OVER 250 FEET
1.75......................$ 61.32 35.68
POWER EQUIPMENT OPERATORS:, GROUP 1: FORK LIFT (UP
TO AND INCLUDING 10 TONS); PARTSMAN (HEAVY DUTY
REPAIR SHOP PARTS ROOM WHEN NEEDED). BOOMS AND/OR
LEADS (HOURLY PREMIUMS): THE OPERATOR OF A CRANE
(UNDER 50 TONS) WITH A BOOM OF 80 FEET OR MORE
(INCLUDING JIB), OR OF A CRANE (UNDER 50 TONS) WITH
LEADS OF 100 FEET OR MORE, SHALL RECEIVE A PER HOUR
PREMIUM FOR EACH HOUR WORKED ON SAID CRANE (UNDER
50 TONS) IN ACCORDANCE WITH THE FOLLOWING SCHEDULE:
BOOMS OF 80 FEET UP TO BUT NOT INCLUDING 130
FEET OR LEADS OF 100 FEET UP TO BUT NOT
INCLUDING 130 FEET
0.50 BOOMS AND/OR LEADS OF 130 FEET UP TO BUT
NOT INCLUDING 180 FEET 0.75 BOOMS AND/OR
LEADS OF 180 FEET UP TO AND INCLUDING 250 FEET
1.15 BOOMS AND/OR LEADS OVER
250 FEET 1.50 THE OPERATOR OF A CRANE (50
TONS AND OVER) WITH A BOOM OF 180 FEET OR MORE
(INCLUDING JIB) SHALL RECEIVE A PER HOUR PREMIUM
FOR EACH HOUR WORKED ON SAID CRANE (50 TONS AND
OVER) IN ACCORDANCE WITH THE FOLLOWING SCHEDULE:
BOOMS OF 180 FEET UP TO AND INCLUDING 250 FEET
1.25 BOOMS OVER 250 FEET
1.75.............$ 57.66 35.68
POWER EQUIPMENT OPERATORS:, GROUP 2: CONVEYOR
OPERATOR (HANDLING BUILDING MATERIAL); HYDRAULIC
MONITOR; MIXER BOX OPERATOR (CONCRETE PLANT).
BOOMS AND/OR LEADS (HOURLY PREMIUMS): THE OPERATOR
OF A CRANE (UNDER 50 TONS) WITH A BOOM OF 80 FEET
OR MORE (INCLUDING JIB), OR OF A CRANE (UNDER 50
TONS) WITH LEADS OF 100 FEET OR MORE, SHALL RECEIVE
A PER HOUR PREMIUM FOR EACH HOUR WORKED ON SAID
CRANE (UNDER 50 TONS) IN ACCORDANCE WITH THE
FOLLOWING SCHEDULE: BOOMS OF 80 FEET UP TO BUT
NOT INCLUDING 130 FEET OR LEADS OF 100 FEET UP TO
BUT NOT INCLUDING 130 FEET
0.50 BOOMS AND/OR LEADS OF 130 FEET UP
TO BUT NOT INCLUDING 180 FEET 0.75 BOOMS
AND/OR LEADS OF 180 FEET UP TO AND INCLUDING 250
FEET 1.15 BOOMS AND/OR
LEADS OVER 250 FEET 1.50 THE OPERATOR OF A
CRANE (50 TONS AND OVER) WITH A BOOM OF 180 FEET OR
MORE (INCLUDING JIB) SHALL RECEIVE A PER HOUR
PREMIUM FOR EACH HOUR WORKED ON SAID CRANE (50 TONS
AND OVER) IN ACCORDANCE WITH THE FOLLOWING
SCHEDULE: BOOMS OF 180 FEET UP TO AND INCLUDING
250 FEET 1.25 BOOMS
OVER 250 FEET
1.75................................................$ 57.77 35.68
POWER EQUIPMENT OPERATORS:, GROUP 3: BRAKEMAN;
DECKHAND; FIREMAN; OILER; OILER/GRADECHECKER;
SIGNALMAN; SWITCHMAN; HIGHLINE CABLEWAY SIGNALMAN;
BARGEMAN; BUNKERMAN; CONCRETE CURING MACHINE
(SELF-PROPELLED, AUTOMATICALLY APPLIED UNIT ON
STREETS, HIGHWAYS, AIRPORTS AND CANALS); LEVEEMAN;
ROLLER (5 TONS AND UNDER); TUGGER HOIST. BOOMS
AND/OR LEADS (HOURLY PREMIUMS): THE OPERATOR OF A
CRANE (UNDER 50 TONS) WITH A BOOM OF 80 FEET OR
MORE (INCLUDING JIB), OR OF A CRANE (UNDER 50 TONS)
WITH LEADS OF 100 FEET OR MORE, SHALL RECEIVE A PER
HOUR PREMIUM FOR EACH HOUR WORKED ON SAID CRANE
(UNDER 50 TONS) IN ACCORDANCE WITH THE FOLLOWING
SCHEDULE: BOOMS OF 80 FEET UP TO BUT NOT
INCLUDING 130 FEET OR LEADS OF 100 FEET UP TO BUT
NOT INCLUDING 130 FEET
0.50 BOOMS AND/OR LEADS OF 130 FEET UP TO
BUT NOT INCLUDING 180 FEET 0.75 BOOMS
AND/OR LEADS OF 180 FEET UP TO AND INCLUDING 250
FEET 1.15 BOOMS AND/OR
LEADS OVER 250 FEET 1.50 THE OPERATOR OF A
CRANE (50 TONS AND OVER) WITH A BOOM OF 180 FEET OR
MORE (INCLUDING JIB) SHALL RECEIVE A PER HOUR
PREMIUM FOR EACH HOUR WORKED ON SAID CRANE (50 TONS
AND OVER) IN ACCORDANCE WITH THE FOLLOWING
SCHEDULE: BOOMS OF 180 FEET UP TO AND INCLUDING
250 FEET 1.25 BOOMS
OVER 250 FEET
1.75................................................$ 57.94 35.68
POWER EQUIPMENT OPERATORS:, GROUP 4: BOOM TRUCK OR
DUAL PURPOSE ""A"" FRAME TRUCK (5 TONS OR LESS);
CONCRETE PLACING BOOM (BUILDING CONSTRUCTION);
DINKY OPERATOR; ELEVATOR OPERATOR; HOIST AND/OR
WINCH (ONE DRUM); STRADDLE TRUCK (ROSS CARRIER,
HYSTER AND SIMILAR). BOOMS AND/OR LEADS (HOURLY
PREMIUMS): THE OPERATOR OF A CRANE (UNDER 50 TONS)
WITH A BOOM OF 80 FEET OR MORE (INCLUDING JIB), OR
OF A CRANE (UNDER 50 TONS) WITH LEADS OF 100 FEET
OR MORE, SHALL RECEIVE A PER HOUR PREMIUM FOR EACH
HOUR WORKED ON SAID CRANE (UNDER 50 TONS) IN
ACCORDANCE WITH THE FOLLOWING SCHEDULE: BOOMS OF
80 FEET UP TO BUT NOT INCLUDING 130 FEET OR
LEADS OF 100 FEET UP TO BUT NOT INCLUDING 130
FEET 0.50 BOOMS
AND/OR LEADS OF 130 FEET UP TO BUT NOT INCLUDING
180 FEET 0.75 BOOMS AND/OR LEADS OF 180
FEET UP TO AND INCLUDING 250 FEET
1.15 BOOMS AND/OR LEADS OVER 250 FEET
1.50 THE OPERATOR OF A CRANE (50 TONS AND OVER)
WITH A BOOM OF 180 FEET OR MORE (INCLUDING JIB)
SHALL RECEIVE A PER HOUR PREMIUM FOR EACH HOUR
WORKED ON SAID CRANE (50 TONS AND OVER) IN
ACCORDANCE WITH THE FOLLOWING SCHEDULE: BOOMS OF
180 FEET UP TO AND INCLUDING 250 FEET
1.25 BOOMS OVER 250 FEET
1.75......................$ 58.21 35.68
POWER EQUIPMENT OPERATORS:, GROUP 5: ASPHALT PLANT
FIREMAN; COMPRESSORS, PUMPS, GENERATORS AND WELDING
MACHINES (""BANK"" OF 9 OR MORE, INDIVIDUALLY OR
COLLECTIVELY); CONCRETE PUMPS OR PUMPCRETE GUNS;
LUBRICATION AND SERVICE ENGINEER (GREASE RACK);
SCREEDMAN BOOMS AND/OR LEADS (HOURLY PREMIUMS):
THE OPERATOR OF A CRANE (UNDER 50 TONS) WITH A BOOM
OF 80 FEET OR MORE (INCLUDING JIB), OR OF A CRANE
(UNDER 50 TONS) WITH LEADS OF 100 FEET OR MORE,
SHALL RECEIVE A PER HOUR PREMIUM FOR EACH HOUR
WORKED ON SAID CRANE (UNDER 50 TONS) IN ACCORDANCE
WITH THE FOLLOWING SCHEDULE: BOOMS OF 80 FEET UP
TO BUT NOT INCLUDING 130 FEET OR LEADS OF 100
FEET UP TO BUT NOT INCLUDING 130 FEET
0.50 BOOMS AND/OR LEADS OF 130
FEET UP TO BUT NOT INCLUDING 180 FEET
0.75 BOOMS AND/OR LEADS OF 180 FEET UP TO AND
INCLUDING 250 FEET 1.15
BOOMS AND/OR LEADS OVER 250 FEET 1.50 THE
OPERATOR OF A CRANE (50 TONS AND OVER) WITH A BOOM
OF 180 FEET OR MORE (INCLUDING JIB) SHALL RECEIVE A
PER HOUR PREMIUM FOR EACH HOUR WORKED ON SAID CRANE
(50 TONS AND OVER) IN ACCORDANCE WITH THE FOLLOWING
SCHEDULE: BOOMS OF 180 FEET UP TO AND INCLUDING
250 FEET 1.25 BOOMS
OVER 250 FEET
1.75................................................$ 58.52 35.68
POWER EQUIPMENT OPERATORS:, GROUP 6: BOOM TRUCK OR
DUAL PURPOSE ""A""FRAME TRUCK (OVER 5 TONS);
COMBINATION LOADER/BACKHOE (UP TO AND INCLUDING 3/4
CU. YD.); CONCRETE BATCH PLANTS (WET OR DRY);
CONCRETE CUTTER, GROOVER AND/OR GRINDER
(SELF-PROPELLED UNIT ON STREETS, HIGHWAYS,
AIRPORTS, AND CANALS); CONVEYOR OR CONCRETE PUMP
(TRUCK OR EQUIPMENT MOUNTED); DRILLING MACHINERY
(NOT TO APPLY TO WATERLINERS, WAGON DRILLS OR JACK
HAMMERS); FORK LIFT (OVER 10 TONS); LOADER (UP TO
AND INCLUDING 3 AND 1/2 CU. YDS); LULL HIGH LIFT
(UNDER 40 FEET); LUBRICATION AND SERVICE ENGINEER
(MOBILE); MAGINNIS INTERNAL FULL SLAB VIBRATOR (ON
AIRPORTS, HIGHWAYS, CANALS AND WAREHOUSES); MAN OR
MATERIAL HOIST; MECHANICAL CONCRETE FINISHER (LARGE
CLARY, JOHNSON BIDWELL, BRIDGE DECK AND SIMILAR);
MOBILE TRUCK CRANE DRIVER; PORTABLE SHOTBLAST
CONCRETE CLEANING MACHINE; PORTABLE BORING MACHINE
(UNDER STREETS, HIGHWAYS, ETC.); PORTABLE CRUSHER;
POWER JUMBO OPERATOR (SETTING SLIP FORMS, ETC., IN
TUNNELS); ROLLERS (OVER 5 TONS); SELF-PROPELLED
COMPACTOR (SINGLE ENGINE); SELF-PROPELLED PAVEMENT
BREAKER; SKIDSTEER LOADER WITH ATTACHMENTS; SLIP
FORM PUMPS (POWER DRIVEN BY HYDRAULIC, ELECTRIC,
AIR, GAS, ETC., LIFTING DEVICE FOR CONCRETE FORMS);
SMALL RUBBER TIRED TRACTORS; TRENCHER (UP TO AND
INCLUDING 6 FEET); UNDERBRIDGE PERSONNEL AERIAL
PLATFORM (50 FEET OF PLATFORM OR LESS). BOOMS
AND/OR LEADS (HOURLY PREMIUMS): THE OPERATOR OF A
CRANE (UNDER 50 TONS) WITH A BOOM OF 80 FEET OR
MORE (INCLUDING JIB), OR OF A CRANE (UNDER 50 TONS)
WITH LEADS OF 100 FEET OR MORE, SHALL RECEIVE A PER
HOUR PREMIUM FOR EACH HOUR WORKED ON SAID CRANE
(UNDER 50 TONS) IN ACCORDANCE WITH THE FOLLOWING
SCHEDULE: BOOMS OF 80 FEET UP TO BUT NOT
INCLUDING 130 FEET OR LEADS OF 100 FEET UP TO BUT
NOT INCLUDING 130 FEET
0.50 BOOMS AND/OR LEADS OF 130 FEET UP TO
BUT NOT INCLUDING 180 FEET 0.75 BOOMS
AND/OR LEADS OF 180 FEET UP TO AND INCLUDING 250
FEET 1.15 BOOMS AND/OR
LEADS OVER 250 FEET 1.50 THE OPERATOR OF A
CRANE (50 TONS AND OVER) WITH A BOOM OF 180 FEET OR
MORE (INCLUDING JIB) SHALL RECEIVE A PER HOUR
PREMIUM FOR EACH HOUR WORKED ON SAID CRANE (50 TONS
AND OVER) IN ACCORDANCE WITH THE FOLLOWING
SCHEDULE: BOOMS OF 180 FEET UP TO AND INCLUDING
250 FEET 1.25 BOOMS
OVER 250 FEET
1.75................................................$ 59.17 35.68
POWER EQUIPMENT OPERATORS:, GROUP 7: CRUSHER PLANT
ENGINEER, DOZER (D-4, CASE 450, JOHN DEERE 450, AND
SIMILAR); DUAL DRUM MIXER, EXTEND LIFT; HOIST
AND/OR WINCH (2 DRUMS); LOADER (OVER 3 AND 1/2 CU.
YDS. UP TO AND INCLUDING 6 YARDS.); MECHANICAL
FINISHER OR SPREADER MACHINE (ASPHALT), (BARBER
GREENE AND SIMILAR) (SCREEDMAN REQUIRED); MINE OR
SHAFT HOIST; MOBILE CONCRETE MIXER (OVER 5 TONS);
PIPE BENDING MACHINE (PIPELINES ONLY); PIPE
CLEANING MACHINE (TRACTOR PROPELLED AND SUPPORTED);
PIPE WRAPPING MACHINE (TRACTOR PROPELLED AND
SUPPORTED); ROLLER OPERATOR (ASPHALT);
SELF-PROPELLED ELEVATING GRADE PLANE; SLUSHER
OPERATOR; TRACTOR (WITH BOOM) (D-6, OR SIMILAR);
TRENCHER (OVER 6 FEET AND LESS THAN 200 H.P.);
WATER TANKER (PULLED BY EUCLIDS, T-PULLS, DW-10, 20
OR 21, OR SIMILAR); WINCHMAN (STERN WINCH ON
DREDGE). BOOMS AND/OR LEADS (HOURLY PREMIUMS):
THE OPERATOR OF A CRANE (UNDER 50 TONS) WITH A BOOM
OF 80 FEET OR MORE (INCLUDING JIB), OR OF A CRANE
(UNDER 50 TONS) WITH LEADS OF 100 FEET OR MORE,
SHALL RECEIVE A PER HOUR PREMIUM FOR EACH HOUR
WORKED ON SAID CRANE (UNDER 50 TONS) IN ACCORDANCE
WITH THE FOLLOWING SCHEDULE: BOOMS OF 80 FEET UP
TO BUT NOT INCLUDING 130 FEET OR LEADS OF 100
FEET UP TO BUT NOT INCLUDING 130 FEET
0.50 BOOMS AND/OR LEADS OF 130
FEET UP TO BUT NOT INCLUDING 180 FEET
0.75 BOOMS AND/OR LEADS OF 180 FEET UP TO AND
INCLUDING 250 FEET 1.15
BOOMS AND/OR LEADS OVER 250 FEET 1.50 THE
OPERATOR OF A CRANE (50 TONS AND OVER) WITH A BOOM
OF 180 FEET OR MORE (INCLUDING JIB) SHALL RECEIVE A
PER HOUR PREMIUM FOR EACH HOUR WORKED ON SAID CRANE
(50 TONS AND OVER) IN ACCORDANCE WITH THE FOLLOWING
SCHEDULE: BOOMS OF 180 FEET UP TO AND INCLUDING
250 FEET 1.25 BOOMS
OVER 250 FEET
1.75................................................$ 59.49 35.68
POWER EQUIPMENT OPERATORS:, GROUP 8: ASPHALT PLANT
OPERATOR; BARGE MATE (SEAGOING); CAST-IN-PLACE PIPE
LAYING MACHINE; CONCRETE BATCH PLANT (MULTIPLE
UNITS); CONVEYOR OPERATOR (TUNNEL); DECKMATE; DOZER
(D-6 AND SIMILAR); FINISHING MACHINE OPERATOR
(AIRPORTS AND HIGHWAYS); GRADESETTER; KOLMAN LOADER
(AND SIMILAR); MUCKING MACHINE (CRAWLER-TYPE);
MUCKING MACHINE (CONVEYOR-TYPE); NO-JOINT PIPE
LAYING MACHINE; PORTABLE CRUSHING AND SCREENING
PLANT; POWER BLADE OPERATOR (UNDER 12); SAURMAN
TYPE DRAGLINE (UP TO AND INCLUDING 5 YDS.);
STATIONARY PIPE WRAPPING, CLEANING AND BENDING
MACHINE; SURFACE HEATER AND PLANER OPERATOR,
TRACTOR (D-6 AND SIMILAR); TRI-BATCH PAVER; TUNNEL
BADGER; TUNNEL MOLE AND/OR BORING MACHINE OPERATOR
UNDERBRIDGE PERSONNEL AERIAL PLATFORM (OVER 50 FEET
OF PLATFORM). BOOMS AND/OR LEADS (HOURLY
PREMIUMS): THE OPERATOR OF A CRANE (UNDER 50 TONS)
WITH A BOOM OF 80 FEET OR MORE (INCLUDING JIB), OR
OF A CRANE (UNDER 50 TONS) WITH LEADS OF 100 FEET
OR MORE, SHALL RECEIVE A PER HOUR PREMIUM FOR EACH
HOUR WORKED ON SAID CRANE (UNDER 50 TONS) IN
ACCORDANCE WITH THE FOLLOWING SCHEDULE: BOOMS OF
80 FEET UP TO BUT NOT INCLUDING 130 FEET OR
LEADS OF 100 FEET UP TO BUT NOT INCLUDING 130
FEET 0.50 BOOMS
AND/OR LEADS OF 130 FEET UP TO BUT NOT INCLUDING
180 FEET 0.75 BOOMS AND/OR LEADS OF 180
FEET UP TO AND INCLUDING 250 FEET
1.15 BOOMS AND/OR LEADS OVER 250 FEET
1.50 THE OPERATOR OF A CRANE (50 TONS AND OVER)
WITH A BOOM OF 180 FEET OR MORE (INCLUDING JIB)
SHALL RECEIVE A PER HOUR PREMIUM FOR EACH HOUR
WORKED ON SAID CRANE (50 TONS AND OVER) IN
ACCORDANCE WITH THE FOLLOWING SCHEDULE: BOOMS OF
180 FEET UP TO AND INCLUDING 250 FEET
1.25 BOOMS OVER 250 FEET
1.75......................$ 59.60 35.68
POWER EQUIPMENT OPERATORS:, GROUP 9: COMBINATION
MIXER AND COMPRESSOR (GUNITE); DO-MOR LOADERAND
ADAMS ELEGRADER; DOZER (D-7 OR EQUAL); WHEEL AND/OR
LADDER TRENCHER (OVER 6 FEET AND 200 TO 749 H.P.).
BOOMS AND/OR LEADS (HOURLY PREMIUMS): THE OPERATOR
OF A CRANE (UNDER 50 TONS) WITH A BOOM OF 80 FEET
OR MORE (INCLUDING JIB), OR OF A CRANE (UNDER 50
TONS) WITH LEADS OF 100 FEET OR MORE, SHALL RECEIVE
A PER HOUR PREMIUM FOR EACH HOUR WORKED ON SAID
CRANE (UNDER 50 TONS) IN ACCORDANCE WITH THE
FOLLOWING SCHEDULE: BOOMS OF 80 FEET UP TO BUT
NOT INCLUDING 130 FEET OR LEADS OF 100 FEET UP TO
BUT NOT INCLUDING 130 FEET
0.50 BOOMS AND/OR LEADS OF 130 FEET UP
TO BUT NOT INCLUDING 180 FEET 0.75 BOOMS
AND/OR LEADS OF 180 FEET UP TO AND INCLUDING 250
FEET 1.15 BOOMS AND/OR
LEADS OVER 250 FEET 1.50 THE OPERATOR OF A
CRANE (50 TONS AND OVER) WITH A BOOM OF 180 FEET OR
MORE (INCLUDING JIB) SHALL RECEIVE A PER HOUR
PREMIUM FOR EACH HOUR WORKED ON SAID CRANE (50 TONS
AND OVER) IN ACCORDANCE WITH THE FOLLOWING
SCHEDULE: BOOMS OF 180 FEET UP TO AND INCLUDING
250 FEET 1.25 BOOMS
OVER 250 FEET
1.75................................................$ 59.71 35.68
POWER EQUIPMENT OPERATORS:, GROUP 9A: DOZER (D-8
AND SIMILAR); GRADESETTER (WHEN REQUIRED BY THE
CONTRACTOR TO WORK FROM DRAWINGS, PLANS OR
SPECIFICATIONS WITHOUT THE DIRECT SUPERVISION OF A
FOREMAN OR SUPERINTENDENT); PUSH CAT; SCRAPERS (UP
TO AND INCLUDING 20 CU. YDS); SELF-PROPELLED
COMPACTOR WITH DOZER; SELF-PROPELLED, RUBBER-TIRED
EARTHMOVING EQUIPMENT (UP TO AND INCLUDING 20 CU.
YDS) (621 BAND AND SIMILAR); SHEEP'S FOOT; TRACTOR
(D-8 AND SIMILAR); TRACTORS WITH BOOM (LARGER THAN
D-6, AND SIMILAR). BOOMS AND/OR LEADS (HOURLY
PREMIUMS): THE OPERATOR OF A CRANE (UNDER 50 TONS)
WITH A BOOM OF 80 FEET OR MORE (INCLUDING JIB), OR
OF A CRANE (UNDER 50 TONS) WITH LEADS OF 100 FEET
OR MORE, SHALL RECEIVE A PER HOUR PREMIUM FOR EACH
HOUR WORKED ON SAID CRANE (UNDER 50 TONS) IN
ACCORDANCE WITH THE FOLLOWING SCHEDULE: BOOMS OF
80 FEET UP TO BUT NOT INCLUDING 130 FEET OR
LEADS OF 100 FEET UP TO BUT NOT INCLUDING 130
FEET 0.50 BOOMS
AND/OR LEADS OF 130 FEET UP TO BUT NOT INCLUDING
180 FEET 0.75 BOOMS AND/OR LEADS OF 180
FEET UP TO AND INCLUDING 250 FEET
1.15 BOOMS AND/OR LEADS OVER 250 FEET
1.50 THE OPERATOR OF A CRANE (50 TONS AND OVER)
WITH A BOOM OF 180 FEET OR MORE (INCLUDING JIB)
SHALL RECEIVE A PER HOUR PREMIUM FOR EACH HOUR
WORKED ON SAID CRANE (50 TONS AND OVER) IN
ACCORDANCE WITH THE FOLLOWING SCHEDULE: BOOMS OF
180 FEET UP TO AND INCLUDING 250 FEET
1.25 BOOMS OVER 250 FEET
1.75......................$ 59.94 35.68
POWER EQUIPMENT OPERATORS:, GROUP 10: CHICAGO BOOM;
COLD PLANERS; HEAVY DUTY REPAIRMAN OR WELDER; HOIST
AND/OR WINCH (3 DRUMS); HYDRAULIC SKOOPER (KOEHRING
AND SIMILAR); LOADER (OVER 6 CU. YDS. UP TO AND
INCLUDING 12 CU. YDS.); SAURMAN TYPE DRAGLINE (OVER
5 CU. YDS.); SELF-PROPELLED, RUBBER-TIRED
EARTHMOVING EQUIPMENT (OVER 20 CU. YDS. UP TO AND
INCLUDING 31 CU. YDS.) (637D AND SIMILAR); SOIL
STABILIZER (P & H OR EQUAL); SUB-GRADER (GURRIES OR
OTHER AUTOMATIC TYPE); TRACTORS (D-9 OR EQUIVALENT,
ALL ATTACHMENTS); TRACTOR (TANDEM SCRAPER); WATCH
ENGINEER. BOOMS AND/OR LEADS (HOURLY PREMIUMS):
THE OPERATOR OF A CRANE (UNDER 50 TONS) WITH A BOOM
OF 80 FEET OR MORE (INCLUDING JIB), OR OF A CRANE
(UNDER 50 TONS) WITH LEADS OF 100 FEET OR MORE,
SHALL RECEIVE A PER HOUR PREMIUM FOR EACH HOUR
WORKED ON SAID CRANE (UNDER 50 TONS) IN ACCORDANCE
WITH THE FOLLOWING SCHEDULE: BOOMS OF 80 FEET UP
TO BUT NOT INCLUDING 130 FEET OR LEADS OF 100
FEET UP TO BUT NOT INCLUDING 130 FEET
0.50 BOOMS AND/OR LEADS OF 130
FEET UP TO BUT NOT INCLUDING 180 FEET
0.75 BOOMS AND/OR LEADS OF 180 FEET UP TO AND
INCLUDING 250 FEET 1.15
BOOMS AND/OR LEADS OVER 250 FEET 1.50 THE
OPERATOR OF A CRANE (50 TONS AND OVER) WITH A BOOM
OF 180 FEET OR MORE (INCLUDING JIB) SHALL RECEIVE A
PER HOUR PREMIUM FOR EACH HOUR WORKED ON SAID CRANE
(50 TONS AND OVER) IN ACCORDANCE WITH THE FOLLOWING
SCHEDULE: BOOMS OF 180 FEET UP TO AND INCLUDING
250 FEET 1.25 BOOMS
OVER 250 FEET
1.75................................................$ 60.00 35.68
POWER EQUIPMENT OPERATORS:, GROUP 10A: BOAT
OPERATOR; CABLE-OPERATED CRAWLER CRANE (UP TO AND
INCLUDING 25 TONS); CABLE-OPERATED POWER SHOVEL,
CLAMSHELL, DRAGLINE AND BACKHOE (UP TO AND
INCLUDING 1 CU. YD.); DOZER D9-L; DOZER (D-10, HD41
AND SIMILAR) (ALL ATTACHMENTS); GRADALL (UP TO AND
INCLUDING 1 CU. YD.); HYDRAULIC BACKHOE (OVER 3/4
CU. YDS. UP TO AND INCLUDING 2 CU. YDS.); MOBILE
TRUCK CRANE OPERATOR (UP TO AND INCLUDING 25 TONS)
(MOBILE TRUCK CRANE DRIVER REQUIRED);
SELF-PROPELLED BOOM TYPE LIFTING DEVICE (CENTER
MOUNT) (UP TO AND INCLUDING 25 TONS) (GROVE, DROTT,
P&H, PETTIBONE AND SIMILAR; TRENCHER (OVER 6 FEET
AND 750 H.P. OR MORE); WATCH ENGINEER (STEAM OR
ELECTRIC). BOOMS AND/OR LEADS (HOURLY PREMIUMS):
THE OPERATOR OF A CRANE (UNDER 50 TONS) WITH A BOOM
OF 80 FEET OR MORE (INCLUDING JIB), OR OF A CRANE
(UNDER 50 TONS) WITH LEADS OF 100 FEET OR MORE,
SHALL RECEIVE A PER HOUR PREMIUM FOR EACH HOUR
WORKED ON SAID CRANE (UNDER 50 TONS) IN ACCORDANCE
WITH THE FOLLOWING SCHEDULE: BOOMS OF 80 FEET UP
TO BUT NOT INCLUDING 130 FEET OR LEADS OF 100
FEET UP TO BUT NOT INCLUDING 130 FEET
0.50 BOOMS AND/OR LEADS OF 130
FEET UP TO BUT NOT INCLUDING 180 FEET
0.75 BOOMS AND/OR LEADS OF 180 FEET UP TO AND
INCLUDING 250 FEET 1.15
BOOMS AND/OR LEADS OVER 250 FEET 1.50 THE
OPERATOR OF A CRANE (50 TONS AND OVER) WITH A BOOM
OF 180 FEET OR MORE (INCLUDING JIB) SHALL RECEIVE A
PER HOUR PREMIUM FOR EACH HOUR WORKED ON SAID CRANE
(50 TONS AND OVER) IN ACCORDANCE WITH THE FOLLOWING
SCHEDULE: BOOMS OF 180 FEET UP TO AND INCLUDING
250 FEET 1.25 BOOMS
OVER 250 FEET
1.75................................................$ 60.15 35.68
POWER EQUIPMENT OPERATORS:, GROUP 11: AUTOMATIC
SLIP FORM PAVER (CONCRETE OR ASPHALT); BAND WAGON
(IN CONJUNCTION WITH WHEEL EXCAVATOR);
CABLE-OPERATED CRAWLER CRANES (OVER 25 TONS BUT
LESS THAN 50 TONS); CABLE-OPERATED POWER SHOVEL,
CLAMSHELL, DRAGLINE AND BACKHOE (OVER 1 CU. YD. UP
TO 7 CU. YDS.); GRADALL (OVER 1 CU. YDS. UP TO 7
CU. YDS.); DW-10, 20, ETC. (TANDEM); EARTHMOVING
MACHINES (MULTIPLE PROPULSION POWER UNITS AND 2 OR
MORE SCRAPERS) (UP TO AND INCLUDING 35 CU. YDS.,""
STRUCK"" M.R.C.); HIGHLINE CABLEWAY; HYDRAULIC
BACKHOE (OVER 2 CU. YDS. UP TO AND INCLUDING 4 CU.
YDS.); LEVERMAN; LIFT SLAB MACHINE; LOADER (OVER 12
CU. YDS); MASTER BOAT OPERATOR; MOBILE TRUCK CRANE
OPERATOR (OVER 25 TONS BUT LESS THAN 50 TONS);
(MOBILE TRUCK CRANE DRIVER REQUIRED); PRE-STRESS
WIRE WRAPPING MACHINE; SELF-PROPELLED BOOM-TYPE
LIFTING DEVICE (CENTER MOUNT) (OVER 25 TONS M.R.C);
SELF-PROPELLED COMPACTOR (WITH MULTIPLE-PROPULSION
POWER UNITS); SINGLE ENGINE RUBBER TIRED
EARTHMOVING MACHINE (WITH TANDEM SCRAPER); TANDEM
CATS; TRENCHER (PULLING ATTACHED SHIELD). BOOMS
AND/OR LEADS (HOURLY PREMIUMS): THE OPERATOR OF A
CRANE (UNDER 50 TONS) WITH A BOOM OF 80 FEET OR
MORE (INCLUDING JIB), OR OF A CRANE (UNDER 50 TONS)
WITH LEADS OF 100 FEET OR MORE, SHALL RECEIVE A PER
HOUR PREMIUM FOR EACH HOUR WORKED ON SAID CRANE
(UNDER 50 TONS) IN ACCORDANCE WITH THE FOLLOWING
SCHEDULE: BOOMS OF 80 FEET UP TO BUT NOT
INCLUDING 130 FEET OR LEADS OF 100 FEET UP TO BUT
NOT INCLUDING 130 FEET
0.50 BOOMS AND/OR LEADS OF 130 FEET UP TO
BUT NOT INCLUDING 180 FEET 0.75 BOOMS
AND/OR LEADS OF 180 FEET UP TO AND INCLUDING 250
FEET 1.15 BOOMS AND/OR
LEADS OVER 250 FEET 1.50 THE OPERATOR OF A
CRANE (50 TONS AND OVER) WITH A BOOM OF 180 FEET OR
MORE (INCLUDING JIB) SHALL RECEIVE A PER HOUR
PREMIUM FOR EACH HOUR WORKED ON SAID CRANE (50 TONS
AND OVER) IN ACCORDANCE WITH THE FOLLOWING
SCHEDULE: BOOMS OF 180 FEET UP TO AND INCLUDING
250 FEET 1.25 BOOMS
OVER 250 FEET
1.75................................................$ 60.30 35.68
POWER EQUIPMENT OPERATORS:, GROUP 12 CLAMSHELL OR
DIPPER OPERATOR; DERRICKS; DRILL RIGS;
MULTI-PROPULSION EARTHMOVING MACHINES (2 OR MORE
SCRAPERS) (OVER 35 CU. YDS ""STRUCK""M.R.C.);
OPERATORS (DERRICKS, PILEDRIVERS AND CRANES); POWER
SHOVELS AND DRAGLINES (7 CU. YDS. M.R.C. AND OVER);
SELF-PROPELLED RUBBER-TIRED EARTHMOVING EQUIPMENT
(OVER 31 CU. YDS.) (657B AND SIMILAR); WHEEL
EXCAVATOR (UP TO AND INCLUDING 750 CU. YDS. PER
HOUR); WHEEL EXCAVATOR (OVER 750 CU. YDS. PER
HOUR). BOOMS AND/OR LEADS (HOURLY PREMIUMS): THE
OPERATOR OF A CRANE (UNDER 50 TONS) WITH A BOOM OF
80 FEET OR MORE (INCLUDING JIB), OR OF A CRANE
(UNDER 50 TONS) WITH LEADS OF 100 FEET OR MORE,
SHALL RECEIVE A PER HOUR PREMIUM FOR EACH HOUR
WORKED ON SAID CRANE (UNDER 50 TONS) IN ACCORDANCE
WITH THE FOLLOWING SCHEDULE: BOOMS OF 80 FEET UP
TO BUT NOT INCLUDING 130 FEET OR LEADS OF 100
FEET UP TO BUT NOT INCLUDING 130 FEET
0.50 BOOMS AND/OR LEADS OF 130
FEET UP TO BUT NOT INCLUDING 180 FEET
0.75 BOOMS AND/OR LEADS OF 180 FEET UP TO AND
INCLUDING 250 FEET 1.15
BOOMS AND/OR LEADS OVER 250 FEET 1.50 THE
OPERATOR OF A CRANE (50 TONS AND OVER) WITH A BOOM
OF 180 FEET OR MORE (INCLUDING JIB) SHALL RECEIVE A
PER HOUR PREMIUM FOR EACH HOUR WORKED ON SAID CRANE
(50 TONS AND OVER) IN ACCORDANCE WITH THE FOLLOWING
SCHEDULE: BOOMS OF 180 FEET UP TO AND INCLUDING
250 FEET 1.25 BOOMS
OVER 250 FEET
1.75................................................$ 60.66 35.68
POWER EQUIPMENT OPERATORS:, GROUP 12A: DOZER (D-11
OR SIMILAR OR LARGER); HYDRAULIC EXCAVATORS (OVER 4
CU. YDS.); LIFTING CRANES (50 TONS AND OVER);
PIONEERING DOZER/BACKHOE (INITIAL CLEARING AND
EXCAVATION FOR THE PURPOSE OF PROVIDING ACCESS FOR
OTHER EQUIPMENT WHERE THE TERRAIN WORKED INVOLVES
1-TO-1 SLOPES THAT ARE 50 FEET IN HEIGHT OR DEPTH,
THE SCOPE OF THIS WORK DOES NOT INCLUDE NORMAL
CLEARING AND GRUBBING ON USUAL HILLY TERRAIN NOR
THE EXCAVATION WORK ONCE THE ACCESS IS PROVIDED);
POWER BLADE OPERATOR (CAT 12 OR EQUIVALENT OR
OVER); STRADDLE LIFTS (OVER 50 TONS); TOWER CRANE,
MOBILE; TRAVELING TRUSS CRANES; UNIVERSAL, LIEBHER,
LINDEN, AND SIMILAR TYPES OF TOWER CRANES (IN THE
ERECTION, DISMANTLING, AND MOVING OF EQUIPMENT
THERE SHALL BE AN ADDITIONAL OPERATING ENGINEER OR
HEAVY DUTY REPAIRMAN); YO-YO CAT OR DOZER. BOOMS
AND/OR LEADS (HOURLY PREMIUMS): THE OPERATOR OF A
CRANE (UNDER 50 TONS) WITH A BOOM OF 80 FEET OR
MORE (INCLUDING JIB), OR OF A CRANE (UNDER 50 TONS)
WITH LEADS OF 100 FEET OR MORE, SHALL RECEIVE A PER
HOUR PREMIUM FOR EACH HOUR WORKED ON SAID CRANE
(UNDER 50 TONS) IN ACCORDANCE WITH THE FOLLOWING
SCHEDULE: BOOMS OF 80 FEET UP TO BUT NOT
INCLUDING 130 FEET OR LEADS OF 100 FEET UP TO BUT
NOT INCLUDING 130 FEET
0.50 BOOMS AND/OR LEADS OF 130 FEET UP TO
BUT NOT INCLUDING 180 FEET 0.75 BOOMS
AND/OR LEADS OF 180 FEET UP TO AND INCLUDING 250
FEET 1.15 BOOMS AND/OR
LEADS OVER 250 FEET 1.50 THE OPERATOR OF A
CRANE (50 TONS AND OVER) WITH A BOOM OF 180 FEET OR
MORE (INCLUDING JIB) SHALL RECEIVE A PER HOUR
PREMIUM FOR EACH HOUR WORKED ON SAID CRANE (50 TONS
AND OVER) IN ACCORDANCE WITH THE FOLLOWING
SCHEDULE: BOOMS OF 180 FEET UP TO AND INCLUDING
250 FEET 1.25 BOOMS
OVER 250 FEET
1.75................................................$ 61.02 35.68
POWER EQUIPMENT OPERATORS:, GROUP 13: TRUCK DRIVER
(UTILITY, FLATBED, ETC.)............................$ 57.94 35.68
POWER EQUIPMENT OPERATORS:, GROUP 13A: DUMP TRUCK,
8 CU.YDS. AND UNDER (WATER LEVEL); WATER TRUCK (UP
TO AND INCLUDING 2,000 GALLONS).....................$ 58.21 35.68
POWER EQUIPMENT OPERATORS:, GROUP 13B: WATER TRUCK
(OVER 2,000 GALLONS); TANDEM DUMP TRUCK, OVER 8 CU.
YDS. (WATER LEVEL)..................................$ 58.52 35.68
POWER EQUIPMENT OPERATORS:, GROUP 13C: TRUCK DRIVER
(SEMI-TRAILER. ROCK CANS, SEMI-DUMP OR ROLL-OFFS)...$ 59.17 35.68
POWER EQUIPMENT OPERATORS:, GROUP 13D: TRUCK DRIVER
(SLIP-IN OR PUP)....................................$ 59.49 35.68
POWER EQUIPMENT OPERATORS:, GROUP 13E: END DUMPS,
UNLICENSED (EUCLID, MACK, CATERPILLAR OR SIMILAR);
TRACTOR TRAILER (HAULING EQUIPMENT); TANDEM TRUCKS
HOOKED UP TO TRAILER (HAULING EQUIPMENT)
..................................................$ 59.60 35.68
STAND-BY DIVER: (AQUA LUNG) (SCUBA).................$ 62.97 35.68
STAND-BY DIVER: OTHER THAN AQUA LUNG................$ 62.97 35.68
----------------------------------------------------------------
ENGI0003-004 09/01/2025
Rates Fringes
DREDGING (BOAT OPERATORS): BOAT DECKHAND............$ 57.94 35.68
DREDGING (BOAT OPERATORS): BOAT OPERATOR............$ 60.15 35.68
DREDGING (BOAT OPERATORS): MASTER BOAT OPERATOR.....$ 60.30 35.68
DREDGING:, CLAMSHELL OR DIPPER DREDGING: GROUP 1:
CLAMSHELL OR DIPPER OPERATOR........................$ 60.66 35.68
DREDGING:, CLAMSHELL OR DIPPER DREDGING: GROUP 2:
MECHANIC OR WELDER; WATCH ENGINEER..................$ 60.00 35.68
DREDGING:, CLAMSHELL OR DIPPER DREDGING: GROUP 3:
BARGE MATE; DECKMATE................................$ 59.60 35.68
DREDGING:, CLAMSHELL OR DIPPER DREDGING: GROUP 4:
BARGEMAN; DECKHAND; FIREMAN; OILER. HYDRAULIC
SUCTION DREDGING CLASSIFICATIONS....................$ 57.94 35.68
DREDGING:, DERRICKS: GROUP 1: OPERATORS (DERRICKS,
PILEDRIVERS AND CRANES). ..........................$ 60.66 35.68
DREDGING:, DERRICKS: GROUP 2: SAURMAN TYPE
DRAGLINE (OVER 5 CUBIC YARDS). ....................$ 60.00 35.68
DREDGING:, DERRICKS: GROUP 3: DECKMATE; SAURMAN
TYPE DRAGLINE (UP TO AND INCLUDING 5 YARDS). ......$ 59.60 35.68
DREDGING:, DERRICKS: GROUP 4: DECKHAND, FIREMAN,
OILER...............................................$ 57.94 35.68
DREDGING:, HYDRAULIC SUCTION DREDGES: GROUP 1:
LEVERMAN. .........................................$ 60.30 35.68
DREDGING:, HYDRAULIC SUCTION DREDGES: GROUP 2:
WATCH ENGINEER (STEAM OR ELECTRIC). ...............$ 60.15 35.68
DREDGING:, HYDRAULIC SUCTION DREDGES: GROUP 3:
MECHANIC OR WELDER. ...............................$ 60.00 35.68
DREDGING:, HYDRAULIC SUCTION DREDGES: GROUP 4:
DOZER OPERATOR. ...................................$ 59.94 35.68
DREDGING:, HYDRAULIC SUCTION DREDGES: GROUP 5:
DECKMATE. .........................................$ 59.60 35.68
DREDGING:, HYDRAULIC SUCTION DREDGES: GROUP 6:
WINCHMAN (STERN WINCH ON DREDGE)....................$ 59.49 35.68
DREDGING:, HYDRAULIC SUCTION DREDGES: GROUP 7:
DECKHAND (CAN OPERATE ANCHOR SCOW UNDER DIRECTION
OF DECKMATE); FIREMAN; LEVEEMAN; OILER..............$ 57.94 35.68
----------------------------------------------------------------
ENGI0003-044 09/01/2025
Rates Fringes
POWER EQUIPMENT OPERATORS (PAVING): ASPHALT
CONCRETE MATERIAL TRANSFER..........................$ 58.67 34.86
POWER EQUIPMENT OPERATORS (PAVING): ASPHALT PLANT
OPERATOR............................................$ 59.07 34.86
POWER EQUIPMENT OPERATORS (PAVING): ASPHALT RAKER...$ 57.68 34.86
POWER EQUIPMENT OPERATORS (PAVING): ASPHALT
SPREADER OPERATOR...................................$ 59.16 34.86
POWER EQUIPMENT OPERATORS (PAVING): COLD PLANER.....$ 59.47 34.86
POWER EQUIPMENT OPERATORS (PAVING): COMBINATION
LOADER/BACKHOE (OVER 3/4 CU.YD.)....................$ 57.68 34.86
POWER EQUIPMENT OPERATORS (PAVING): COMBINATION
LOADER/BACKHOE (UP TO 3/4 CU.YD.)...................$ 56.70 34.86
POWER EQUIPMENT OPERATORS (PAVING): CONCRETE SAWS
AND/OR GRINDER (SELF-PROPELLED UNIT ON STREETS,
HIGHWAYS, AIRPORTS AND CANALS)......................$ 58.64 34.86
POWER EQUIPMENT OPERATORS (PAVING): GRADER..........$ 59.47 34.86
POWER EQUIPMENT OPERATORS (PAVING): LABORER, HAND
ROLLER..............................................$ 57.18 34.86
POWER EQUIPMENT OPERATORS (PAVING): LOADER (2 1/2
CU. YDS. AND UNDER).................................$ 58.64 34.86
POWER EQUIPMENT OPERATORS (PAVING): LOADER (OVER 2
1/2 CU. YDS. TO AND INCLUDING 5 CU. YDS.)...........$ 58.96 34.86
POWER EQUIPMENT OPERATORS (PAVING): ROLLER OPERATOR
(FIVE TONS AND UNDER)...............................$ 57.41 34.86
POWER EQUIPMENT OPERATORS (PAVING): ROLLER OPERATOR
(OVER FIVE TONS)....................................$ 58.84 34.86
POWER EQUIPMENT OPERATORS (PAVING): SCREED PERSON...$ 58.64 34.86
POWER EQUIPMENT OPERATORS (PAVING): SOIL STABILIZER.$ 59.47 34.86
----------------------------------------------------------------
IRON0625-001 09/01/2025
Rates Fringes
IRONWORKERS A. EMPLOYEES WILL BE PAID $.50 PER
HOUR MORE WHILE WORKING IN TUNNELS AND COFFER DAMS;
$1.00 PER HOUR MORE WHEN REQUIRED TO WORK UNDER OR
ARE COVERED WITH WATER (SUBMERGED) AND WHEN THEY
ARE REQUIRED TO WORK ON THE SUMMIT OF MAUNA KEA,
MAUNA LOA OR HALEAKALA..............................$ 50.50 43.46
----------------------------------------------------------------
LABO0368-001 09/02/2024
Rates Fringes
LABORERS: DRILLER...................................$ 44.75 25.96
LABORERS: FINAL CLEAN UP............................$ 31.40 21.37
LABORERS: GUNITE/SHOTCRETE OPERATOR AND HIGH SCALER.$ 42.25 25.96
LABORERS: MASON TENDER/HOD CARRIER..................$ 42.25 25.96
LABORERS: POWDERMAN.................................$ 42.75 25.96
LABORERS: WINDOW WASHER (BOSUN CHAIR)...............$ 41.25 25.96
SEE LABORERS: LABORER I IN FOOTER...................$ 41.75 25.96
SEE LABORERS: LABORER II IN FOOTER..................$ 39.15 25.96
----------------------------------------------------------------
LABO0368-002 09/03/2024
Rates Fringes
LANDSCAPE & IRRIGATION LABORERS, GROUP 1:
INSTALLATION OF NON-POTABLE PERMANENT OR TEMPORARY
IRRIGATION WATER SYSTEMS PERFORMED FOR THE PURPOSES
OF LANDSCAPING AND IRRIGATION ARCHITECTURAL
HORTICULTURAL WORK; THE INSTALLATION OF DRINKING
FOUNTAINS AND PERMANENT OR TEMPORARY IRRIGATION
SYSTEMS USING POTABLE WATER FOR LANDSCAPING AND
IRRIGATION ARCHITECTURAL HORTICULTURAL PURPOSES
ONLY. THIS WORK INCLUDES (A) THE INSTALLATION OF
ALL HEADS, RISERS, VALVES, VALVE BOXES, VACUUM
BREAKERS (PRESSURE AND NON-PRESSURE), LOW VOLTAGE
ELECTRICAL LINES AND, PROVIDED SUCH WORK INVOLVES
ELECTRICAL WIRING THAT WILL CARRY 24 VOLTS OR LESS,
THE INSTALLATION OF SENSORS, MASTER CONTROL PANELS,
DISPLAY BOARDS, JUNCTION BOXES, CONDUCTORS,
INCLUDING ALL OTHER COMPONENTS FOR CONTROLLERS, (B)
AND METALLIC (COPPER, BRASS, GALVANIZED, OR
SIMILAR) PIPE, AS WELL AS PVC OR OTHER PLASTIC PIPE
INCLUDING ALL WORK INCIDENTAL THERETO, I.E.,
UNLOADING, HANDLING AND DISTRIBUTION OF ALL PIPES
FITTINGS, TOOLS, MATERIALS AND EQUIPMENT, (C) ALL
SOLDERING WORK IN CONNECTION WITH THE ABOVE WHETHER
DONE BY TORCH, SOLDERING IRON, OR OTHER MEANS; (D)
TIE-IN TO MAIN LINES, THRUST BLOCKS (BOTH PRECAST
AND POURED IN PLACE), PIPE HANGERS AND SUPPORTS
INCIDENTAL TO INSTALLATION OF THE ENTIRE IRRIGATION
SYSTEM, (E) MAKING OF PRESSURE TESTS, START-UP
TESTING, FLUSHING, PURGING, WATER BALANCING,
PLACING INTO OPERATION ALL IRRIGATION EQUIPMENT,
FIXTURES AND APPURTENANCES INSTALLED UNDER THIS
AGREEMENT, AND (F) THE FABRICATION, REPLACEMENT,
REPAIR AND SERVICING OFLANDSCAPING AND IRRIGATION
SYSTEMS. OPERATION OF HAND-HELD GAS, AIR,
ELECTRIC, OR SELF-POWERED TOOLS AND EQUIPMENT USED
IN THE PERFORMANCE OF LANDSCAPE AND IRRIGATION WORK
IN CONNECTION WITH ARCHITECTURAL HORTICULTURE;
CHOKE-SETTING, SIGNALING, AND RIGGING FOR EQUIPMENT
OPERATORS ON JOB-SITE IN THE PERFORMANCE OF SUCH
LANDSCAPING AND IRRIGATION WORK; CONCRETE WORK (WET
OR DRY) PERFORMED IN CONNECTION WITH SUCH
LANDSCAPING AND IRRIGATION WORK. THIS WORK SHALL
ALSO INCLUDE THE SETTING OF ROCK, STONE, OR RIPRAP
IN CONNECTION WITH SUCH LANDSCAPE, WATERSCAPE,
ROCKSCAPE, AND IRRIGATION WORK; GRUBBING, PICK AND
SHOVEL EXCAVATION, AND HAND ROLLING OR TAMPING IN
CONNECTION WITH THE PERFORMANCE OF SUCH LANDSCAPING
AND IRRIGATION WORK; SPRIGGING, HANDSEEDING, AND
PLANTING OF TREES, SHRUBS, GROUND COVERS, AND OTHER
PLANTINGS AND THE PERFORMANCE OF ALL TYPES OF
GARDENING AND HORTICULTURAL WORK RELATING TO SAID
PLANTING; OPERATION OF FLAT BED TRUCKS (UP TO AND
INCLUDING 2 1/2 TONS).: ...........................$ 28.40 17.15
LANDSCAPE & IRRIGATION LABORERS, GROUP 3:
MAINTENANCE OF TREES, SHRUBS, GROUND COVERS, LAWNS
AND OTHER PLANTED AREAS, INCLUDING THE REPLANTING
OF TREES, SHRUBS, GROUND COVERS, AND OTHER
PLANTINGS THAT DID NOT ""TAKE"" OR WHICH ARE DAMAGED;
PROVIDED, HOWEVER, THAT RE-PLANTING THAT REQUIRES
THE USE OF EQUIPMENT, MACHINERY, OR POWER TOOLS
SHALL BE PAID FOR AT THE RATE OF PAY SPECIFIED
UNDER LANDSCAPE AND IRRIGATION LABORER, GROUP 1;
RAKING, MOWING, TRIMMING, AND RUNING, INCLUDING THE
USE OF ""WEED EATERS"", HEDGE TRIMMERS, VACUUMS,
BLOWERS, AND OTHER HAND-HELD GAS, AIR, ELECTRIC, OR
SELF-POWERED TOOLS, AND THE OPERATION OF LAWN
MOWERS (NOTE: THE OPERATION OF SIT-DOWN TYPE AND
""GANG"" MOWERS SHALL BE PAID FOR AT THE RATE OF PAY
SPECIFIED UNDER LANDSCAPE & IRRIGATION LABORER,
GROUP 2); GUYWIRING, STAKING, PROPPING, AND
SUPPORTING TREES; FERTILIZING, CHEMICAL SPRAYING
USING SPRAY EQUIPMENT WITH LESS THAN 200 GALLON
CAPACITY, MAINTAINING IRRIGATION AND SPRINKLER
SYSTEMS, INCLUDING THE STAKING, CLAMPING, AND
ADJUSTMENT OF RISERS, AND THE ADJUSTMENT AND/OR
REPLACEMENT OF SPRINKLER HEADS, (NOTE: THE CLEANING
AND GLUING OF PIPE AND FITTINGS SHALL BE PAID FOR
AT THE RATE OF PAY SPECIFIED UNDER LANDSCAPE &
IRRIGATION LABORER(GROUP 1); WATERING BY HAND OR
SPRINKLER SYSTEM AND THE PEFORMANCE OF OTHER TYPES
OF GARDENING, YARDMAN, AND HORTICULTURAL-RELATED
WORK................................................$ 23.00 17.15
LANDSCAPE & IRRIGATION LABORERS,GROUP 2: LAYOUT OF
IRRIGATION AND OTHER NON-POTABLE IRRIGATION WATER
SYSTEMS AND THE LAYOUT OF DRINKING FOUNTAINS AND
OTHER POTABLE IRRIGATION WATER SYSTEMS IN
CONNECTION WITH SUCH LANDSCAPING AND IRRIGATION
WORK. THIS INCLUDES THE LAYOUT OF ALL HEADS,
RISERS, VALVES, VALVE BOXES, VACUUM BREAKERS, LOW
VOLTAGE ELECTRICAL LINES, HYDRAULIC AND ELECTRICAL
CONTROLLERS, AND METALLIC (COPPERS, BRASS,
GALVANIZED, OR SIMILAR) PIPE, AS WELL AS PVC OR
OTHER PLASTIC PIPE. THIS WORK ALSO INCLUDES THE
READING AND INTERPRETATION OF PLANS AND
SPECIFICATIONS IN CONNECTION WITH THE LAYOUT OF
LANDSCAPING, ROCKSCAPE, WATERSCAPE, AND IRRIGATION
WORK; OPERATION OF HYDRO-MULCHING MACHINES
(SPRAYMAN AND DRIVER), DRILLERS, TRENCHERS (RIDING
TYPE, DAVIS T-66, AND SIMILAR) AND FORK LIFTS USED
IN CONNECTION WITH THE PERFORMANCE OF SUCH
LANDSCAPING AND IRRIGATION WORK; TREE CLIMBERS AND
CHAIN SAW TREE TRIMMERS, SPORADIC OPERATION (WHEN
USED IN CONNECTION WITH LANDSCAPING, ROCKSCAPE,
WATERSCAPE, AND IRRIGATION WORK) OF SKID-STEER
LOADERS (BOBCAT AND SIMILAR), CRANES (BANTAM,
GROVE, AND SIMILAR), HOPTOS, BACKHOES, LOADERS,
ROLLERS, AND DOZERS (CASE, JOHN DEERE, AND
SIMILAR), WATER TRUCKS, TRUCKS REQUIRING A STATE OF
HAWAII PUBLIC UTILITIES COMMISSION TYPE 5 AND/OR
TYPE 7 LICENSE, SIT-DOWN TYPE AND ""GANG"" MOWERS,
AND OTHER SELF-PROPELLED, SIT-DOWN OPERATED
MACHINES NOT LISTED UNDER LANDSCAPE & IRRIGATION
MAINTENANCE LABORER; CHEMICAL SPRAYING USING
SELF-PROPELLED POWER SPRAYING EQUIPMENT (200 GALLON
CAPACITY OR MORE)...................................$ 29.40 17.15
LANDSCAPE & IRRIGATION LABORERS: GROUP 2 LAYOUT OF
IRRIGATION AND OTHER NON-POTABLE IRRIGATION WATER
SYSTEMS AND THE LAYOUT OF DRINKING FOUNTAINS AND
OTHER POTABLE IRRIGATION WATER SYSTEMS IN
CONNECTION WITH SUCH LANDSCAPING AND IRRIGATION
WORK. THIS INCLUDES THE LAYOUT OF ALL HEADS,
RISERS, VALVES, VALVE BOXES, VACUUM BREAKERS, LOW
VOLTAGE ELECTRICAL LINES, HYDRAULIC AND ELECTRICAL
CONTROLLERS, AND METALLIC (COPPERS, BRASS,
GALVANIZED, OR SIMILAR) PIPE, AS WELL AS PVC OR
OTHER PLASTIC PIPE. THIS WORK ALSO INCLUDES THE
READING AND INTERPRETATION OF PLANS AND
SPECIFICATIONS IN CONNECTION WITH THE LAYOUT OF
LANDSCAPING, ROCKSCAPE, WATERSCAPE, AND IRRIGATION
WORK; OPERATION OF HYDRO-MULCHING MACHINES
(SPRAYMAN AND DRIVER), DRILLERS, TRENCHERS (RIDING
TYPE, DAVIS T-66, AND SIMILAR) AND FORK LIFTS USED
IN CONNECTION WITH THE PERFORMANCE OF SUCH
LANDSCAPING AND IRRIGATION WORK; TREE CLIMBERS AND
CHAIN SAW TREE TRIMMERS, SPORADIC OPERATION (WHEN
USED IN CONNECTION WITH LANDSCAPING, ROCKSCAPE,
WATERSCAPE, AND IRRIGATION WORK) OF SKID-STEER
LOADERS (BOBCAT AND SIMILAR), CRANES (BANTAM,
GROVE, AND SIMILAR), HOPTOS, BACKHOES, LOADERS,
ROLLERS, AND DOZERS (CASE, JOHN DEERE, AND
SIMILAR), WATER TRUCKS, TRUCKS REQUIRING A STATE OF
HAWAII PUBLIC UTILITIES COMMISSION TYPE 5 AND/OR
TYPE 7 LICENSE, SIT-DOWN TYPE AND ""GANG"" MOWERS,
AND OTHER SELF-PROPELLED, SIT-DOWN OPERATED
MACHINES NOT LISTED UNDER LANDSCAPE & IRRIGATION
MAINTENANCE LABORER; CHEMICAL SPRAYING USING
SELF-PROPELLED POWER SPRAYING EQUIPMENT (200 GALLON
CAPACITY OR MORE)...................................$ 29.40 17.15
----------------------------------------------------------------
LABO0368-003 09/02/2024
Rates Fringes
UNDERGROUND LABORER, GROUP 1: WATCHMEN; CHANGE
HOUSE ATTENDANT.....................................$ 42.35 25.91
UNDERGROUND LABORER, GROUP 2: SWAMPER; BRAKEMAN;
BULL GANG-MUCKERS, TRACKMEN; DUMPMEN (ANY METHOD);
CONCRETE CREW (INCLUDES RODDING AND SPREADING);
GROUT CREW; REBOUNDMEN..............................$ 43.85 25.91
UNDERGROUND LABORER, GROUP 3: CHUCKTENDERS AND
CABLETENDERS; POWDERMAN (PRIME HOUSE); VIBRATORMAN,
PAVEMENT BREAKERS...................................$ 44.35 25.91
UNDERGROUND LABORER, GROUP 4: MINERS - TUNNEL
(INCLUDING TOP AND BOTTOM MAN ON SHAFT AND RAISE
WORK); TIMBERMAN, RETIMBERMAN (WOOD OR STEEL OR
SUBSTITUTE MATERIALS THEREOF); BLASTERS, DRILLERS,
POWDERMAN (IN HEADING); MICROTUNNEL LABORER;
HEADMAN; CHERRY PICKERMAN (WHERE CAR IS LIFTED);
NIPPER; GROUT GUNMEN; GROUT PUMPMAN & POTMAN;
GUNITE, SHOTCRETE GUNMEN & POTMEN; CONCRETE
FINISHER (IN TUNNEL); CONCRETE SCREED MAN; BIT
GRINDER; STEEL FORM RAISERS & SETTERS; HIGH
PRESSURE NOZZLEMAN; NOZZLEMAN (ON SLICK LINE);
SANDBLASTER-POTMAN (COMBINATION WORK ASSIGNMENT
INTERCHANGEABLE); TUGGER............................$ 45.35 25.91
UNDERGROUND LABORER, GROUP 5: SHAFT WORK & RAISE
(BELOW ACTUAL OR EXCAVATED GROUND LEVEL); DIAMOND
DRILLER; GUNITE OR SHOTCRETE NOZZLEMAN; RODMAN;
GROUNDMAN...........................................$ 45.70 25.91
UNDERGROUND LABORER, GROUP 6: SHIFTER...............$ 45.95 25.91
UNDERGROUND LABORER, GROUP 7: SHIFTER (SHAFT WORK &
RAISER).............................................$ 46.40 25.91
----------------------------------------------------------------
PAIN1791-001 07/01/2025
Rates Fringes
PAINTERS: BRUSH.....................................$ 44.05 30.05
PAINTERS: SANDBLASTER; SPRAY........................$ 44.05 30.05
----------------------------------------------------------------
PAIN1889-001 07/01/2025
Rates Fringes
GLAZIERS............................................$ 48.50 40.20
----------------------------------------------------------------
PAIN1926-001 03/02/2025
Rates Fringes
SOFT FLOOR LAYERS...................................$ 43.27 35.18
----------------------------------------------------------------
PAIN1944-001 01/01/2025
Rates Fringes
TAPER...............................................$ 47.36 32.00
----------------------------------------------------------------
PLAS0630-001 09/04/2023
Rates Fringes
PLASTERER...........................................$ 46.12 34.53
----------------------------------------------------------------
PLAS0630-002 09/04/2023
Rates Fringes
CEMENT MASONS.......................................$ 44.12 33.63
CEMENT MASONS: TROWEL MACHINE OPERATORS.............$ 44.27 33.63
----------------------------------------------------------------
PLUM0675-001 07/06/2025
Rates Fringes
PLUMBER, PIPEFITTER, STEAMFITTER & SPRINKLER FITTER.$ 53.83 33.19
----------------------------------------------------------------
ROOF0221-001 11/06/2022
Rates Fringes
ROOFERS (INCLUDING BUILT UP, COMPOSITION AND SINGLE
PLY)................................................$ 43.15 21.21
----------------------------------------------------------------
SHEE0293-001 03/02/2025
Rates Fringes
SHEET METAL WORKER..................................$ 50.16 33.32
----------------------------------------------------------------
SUHI1997-002 09/15/1997
Rates Fringes
DRAPERY INSTALLER...................................$ 13.60 1.20
FENCE ERECTOR (CHAIN LINK FENCE)....................$ 9.33 1.65
----------------------------------------------------------------
----------------------------------------------------------------------------------------------------
LABORERS: LABORER I: AIR BLASTING RUN BY ELECTRIC OR PNEUMATIC COMPRESSOR; ASPHALT
LABORER, IRONER, RAKER, LUTEMAN, & HANDROLLER, AND ALL TYPES OF ASPHALT SPREADER
BOXES; ASPHALT SHOVELER; ASSEMBLY & INSTALLATION OF MULTIPLATES, LINER PLATES, RINGS,
MESH, MATS; BATCHING PLANT (PORTABLE & TEMPORARY); BORING MACHINE OPERATOR
(UNDER STREETS & SIDEWALKS); BUGGYMOBILE; BURNING & WELDING; CHAINSAW, FALLER,
LOGLOADER, & BUCKER; COMPACTORS (JACKSON JUMPING JACK & SIMILAR); CONCRETE BUCKET
DUMPMAN; CONCRETE CHIPPING; CONCRETE CHUTEMAN/HOSEMAN (POURING CONCRETE)
(THE HANDLING OF THE CHUTE FROM READY-MIX TRUCKS FOR SUCH JOBS AS WALLS, SLABS,
DECKS, FLOORS, FOUNDATIONS, FOOTINGS, CURBS, GUTTERS, & SIDEWALKS); CONCRETE CORE
CUTTER (WALLS, FLOORS, & CEILING); CONCRETE GRINDING OR SANDING; CONCRETE: HOOKING
ON, SIGNALING, DUMPING OF CONCRETE FOR TREME WORK OVER WATER ON CAISSONS,
PILINGS, ABUTMENTS, ETC.; CONCRETE: MIXING, HANDLING, CONVEYING, POURING, VIBRATING,
OTHERWISE PLACING OF CONCRETE OR AGGREGATES OR BY ANY OTHER PROCESS;
CONCRETE: OPERATION OF MOTORIZED WHEELBARROWS OR BUGGIES OR MACHINES OF
SIMILAR CHARACTER, WHETHER RUN BY GAS, DIESEL, OR ELECTRIC POWER; CONCRETE
PLACEMENT MACHINE OPERATOR: OPERATION OF SOMERO HAMMERHEAD, COPPERHEADS, OR
SIMILAR MACHINES; CONCRETE PUMP MACHINE (LAYING, COUPLING, UNCOUPLING OF ALL
CONNECTIONS & CLEANING OF EQUIPMENT); CONCRETE SHOVELERS/LABORERS (WET OR DRY);
CONCRETE SCREEDING FOR ROUGH STRIKE-OFF: RODDING OR STRIKING-OFF, BY HAND OR
MECHANICAL MEANS PRIOR TO FINISHING; CONCRETE VIBRATOR OPERATOR;
CORING HOLES: WALLS, FOOTINGS, PIERS OR OTHER OBSTRUCTIONS FOR PASSAGE OF PIPES
OR CONDUITS FOR ANY PURPOSE & THE POURING OF CONCRETE TO SECURE THE HOLE;
CRIBBERS, SHORER, LAGGING, SHEETING, & TRENCH JACKING & BRACING, HAND-GUIDED
LAGGING HAMMER WHALING BRACING; CURBING (CONCRETE & ASPHALT); CURING OF
CONCRETE (IMPERVIOUS MEMBRANE & FORM OILER) MORTAR & OTHER MATERIALS BY ANY
MODE OR METHOD; CUT GRANITE CURB SETTER (SETTING, LEVELING & GROUTING OF ALL
PRECAST CONCRETE OR STONE CURBS); CUTTING & BURNING TORCH (DEMOLITION); DRI PAK-IT
MACHINE; ENVIRONMENTAL ABATEMENT: REMOVAL OF ASBESTOS, LEAD, & BIO HAZARDOUS
MATERIALS (EPA &/OR OSHA CERTIFIED); FALLING, BUCKING, YARDING, LOADING OR BURNING
OF ALL TREES OR TIMBER ON CONSTRUCTION SITE; FORKLIFT (9 FT. & UNDER); GAS, PNEUMATIC,
& ELECTRIC TOOLS; GRATING & GRILL WORK FOR DRAINS OR OTHER PURPOSES; GREEN CUTTER
OF CONCRETE OR AGGREGATE IN ANY FORM, BY HAND, MECHANICAL MEANS, GRINDSTONE OR
AIR &/OR WATER; GROUT: SPREADING FOR ANY PURPOSE; GUINEA CHASER (GRADE CHECKER)
FOR GENERAL UTILITY TRENCHES, SITEWORK, & EXCAVATION; HEADERBOARD MAN (ASPHALT OR
CONCRETE); HEAT WELDER OF PLASTIC (LABORERS' AGC CERTIFIED WORKERS) (WHEN WORK
INVOLVES WATERPROOFING FOR WATERPONDS, ARTIFICIAL LAKES & RESERVOIR) HEAT WELDING
FOR SEWER PIPES & FUSION OF HDPE PIPES; HEAVY HIGHWAY LABORER (RIGGING, SIGNALING,
HANDLING, & INSTALLATION OF PRE-CAST CATCH BASINS, MANHOLES, CURBS & GUTTERS); HIGH
PRESSURE NOZZLEMAN - HYDRAULIC MONITOR (OVER 100# PRESSURE); JACKHAMMER OPERATOR;
JACKING OF SLIP FORMS: ALL SEMI & UNSKILLED WORK CONNECTED THEREWITHIN; LAYING OF ALL
MULTI-CELL CONDUIT OR MULTI-PURPOSE PIPE; MAGNESITE & MASTIC WORKERS (WET OR DRY)
(INCLUDING MIXER OPERATOR);MORTAR MAN; MORTAR MIXER (BLOCK, BRICK, MASONRY, &
PLASTERING); NOZZLEMAN (SANDBLASTING &/OR WATER BLASTING): HANDLING, PLACING &
OPERATION OF NOZZLE; OPERATION, MANUAL OR HYDRAULIC JACKING OF SHIELDS & THE USE OF
SUCH OTHER MECHANICAL EQUIPMENT AS MAY BE NECESSARY; PAVEMENT BREAKERS; PAVING,
CURBING & SURFACING OF STREETS, WAYS, COURTS, UNDER & OVERPASSES, BRIDGES, APPROACHES,
SLOPE WALLS, & ALL OTHER LABOR CONNECTED THEREWITH; PILECUTTERS; PIPE ACCESSMENT IN
PLACE, BOLTING & LINING UP OF SECTIONAL METAL OR OTHER PIPE INCLUDING CORRUGATED PIPE;
PIPELAYER PERFORMING ALL SERVICES IN THE LAYING & INSTALLATION OF PIPE FROM THE POINT
OF RECEIVING PIPE IN THE DITCH UNTIL COMPLETION OF OPERATION, INCLUDING ANY & ALL FORMS
OF TUBULAR MATERIAL, WHETHER PIPE, HDPE, METALLIC OR NON-METALLIC, CONDUIT, & ANY
OTHER STATIONARY-TYPE OF TUBULAR DEVICE USED FOR CONVEYING OF ANY SUBSTANCE OR
ELEMENT, WHETHER WATER, SEWAGE, SOLID, GAS, AIR, OR OTHER PRODUCT WHATSOEVER &
WITHOUT REGARD TO THE NATURE OF MATERIAL FROM WHICH TUBULAR MATERIAL IS FABRICATED;
NO-JOINT PIPE & STRIPPING OF SAME, PIPEWRAPPER, CAULKER, BANDER, KETTLEMEN, & MEN
APPLYING ASPHALT, LAYKOLD, TREATING CREOSOTE & SIMILAR-TYPE MATERIALS (6-INCH) PIPE &
OVER); PIPING: RESURFACING & PAVING OF ALL DITCHES IN PREPARATION FOR LAYING OF ALL PIPES;
PIPE LAYING OF LATERAL SEWER PIPE FROM MAIN OR SIDE SEWER TO BUILDINGS OR STRUCTURE
(EXCEPT CONTACTOR MAY DIRECT WORK BE DONE UNDER PROPER SUPERVISION); PIPE LAYING,
LEVELING & MARKING OF THE JOINT USED FOR MAIN OR SIDE SEWERS & STORM SEWERS; LAYING OF
ALL CLAY, TERRA COTTA, IRONSTONE, VITRIFIED CONCRETE, HDPE OR OTHER PIPE FOR DRAINAGE;
PLACING & SETTING OF WATER MAINS, GAS MAINS & ALL PIPE INCLUDING REMOVAL OF SKIDS;
PLASTER MORTAR MIXER/PUMP; PNEUMATIC IMPACT WRENCH; PORTABLE SAWMILL OPERATION:
CHOKER SETTERS, OFF BEARERS, & LUMBER HANDLERS CONNECTED WITH CLEARING; POSTHOLE
DIGGER (HAND HELD, GAS, AIR & ELECTRIC); POWDERMAN'S TENDER; POWER BROOM SWEEPERS
(SMALL); PREPARATION & COMPACTION OF ROADBEDS FOR RAILROAD TRACK LAYING, HIGHWAY
CONSTRUCTION, & THE PREPARATION OF TRENCHES, FOOTINGS, ETC., FOR CROSS-COUNTRY
TRANSMISSION BY PIPELINES, ELECTRICAL TRANSMISSION OR UNDERGROUND LINES OR CABLES
(BY MECHANICAL MEANS); RAISING OF STRUCTURE BY MANUAL OR HYDRAULIC JACKS OR OTHER
METHODS & RESETTING OF STRUCTURE IN NEW LOCATIONS, INCLUDING ALL CONCRETE WORK;
RAMMING OR COMPACTION; RIGGING IN CONNECTION WITH LABORERS' WORK (EXCEPT
DEMOLITION), SIGNALING (INCLUDING THE USE OF WALKIE TALKIE) CHOKE SETTING, TAG LINE
USAGE; TAGGING & SIGNALING OF BUILDING MATERIALS INTO HIGH RISE UNITS; RIPRAP,
STONEPAVER, & ROCK SLINGER (INCLUDES PLACEMENT OF STACKED CONCRETE, WET OR DRY &
LOADING, UNLOADING, SIGNALING, SLINGING & SETTING OF OTHER SIMILAR MATERIALS);
ROTARY SCARIFIER (INCLUDING MULTIPLE HEAD CONCRETE CHIPPING SCARIFIER); SALAMANDER
HEATER, DRYING OF PLASTER, CONCRETE MORTAR OR OTHER AGGREGATE; SCAFFOLD ERECTOR
LEADMAN; SCAFFOLDS: (SWING & HANGING) INCLUDING MAINTENANCE THEREOF; SCALER;
SEPTIC TANK/CESSPOOL & DRAIN FIELDS DIGGER & INSTALLER; SHREDDER/CHIPPER (TREE
BRANCHES, BRUSH, ETC.); STRIPPING & SETTING FORMS; STRIPPING OF FORMS: OTHER THAN
PANEL FORMS WHICH ARE TO BE RE-USED IN THEIR ORIGINAL FORM, & STRIPPING OF FORMS ON
ALL FLAT ARCH WORK; TAMPERS (BARKO, WACKER, & SIMILAR TYPE); TANK SCALER & CLEANERS;
TARMAN; TREE CLIMBERS & TRIMMERS; TRENCHER (INCLUDES HAND-HELD, DAVIS T-66 & SIMILAR
TYPE); TRUCKS (FLATBED UP TO & INCLUDING 2 1/2 TONS WHEN USED IN CONNECTION WITH
ON-SITE LABORERS'WORK; TRUCKS (REFUSE & GARBAGE DISPOSAL) (FROM JOB SITE TO DUMP);
VIBRA-SCREED (BULL FLOAT IN CONNECTION WITH LABORERS' WORK); WELL POINTS,
INSTALLATION OF OR ANY OTHER DEWATERING SYSTEM.
LABORERS: LABORER II: ASPHALT PLANT LABORER; BORING MACHINE TENDER; BRIDGE LABORER;
BURNING OF ALL DEBRIS (CRATES, BOXES, PACKAGING WASTE MATERIALS); CHAINMAN,
RODMEN, & GRADE MARKERS; CLEANING, CLEARING, GRADING &/OR REMOVAL FOR STREETS,
HIGHWAYS, ROADWAYS, APRONS, RUNWAYS, SIDEWALKS, PARKING AREAS, AIRPORTS,
APPROACHES, & OTHER SIMILAR INSTALLATIONS; CLEANING OR RECONDITIONING OF STREETS,
WAYS, SEWERS & WATERLINES, ALL MAINTENANCE WORK & WORK OF AN UNSKILLED &
SEMI-SKILLED NATURE; CONCRETE BUCKET TENDER (GROUNDMAN) HOOKING & UNHOOKING OF
BUCKET; CONCRETE FORMS; MOVING, CLEANING, OILING & CARRYING TO THE NEXT POINT OF
ERECTION OF ALL FORMS; CONCRETE PRODUCTS PLANT LABORERS; CONVEYOR TENDER
(CONVEYING OF BUILDING MATERIALS); CRUSHED STONE YARDS & GRAVEL & SAND PIT LABORERS
& ALL OTHER SIMILAR PLANTS; DEMOLITION, WRECKING & SALVAGE LABORERS: WRECKING &
DISMANTLING OF BUILDINGS & ALL STRUCTURES, WITH USE OF CUTTING OR WRECKING TOOLS,
BREAKING AWAY, CLEANING & REMOVAL OF ALL FIXTURES, ALL HOOKING, UNHOOKING,
SIGNALING OF MATERIALS FOR SALVAGE OR SCRAP REMOVED BY CRANE OR DERRICK; DIGGING
UNDER STREETS, ROADWAYS, APRONS OR OTHER PAVED SURFACES; DRILLER'S TENDER; CHUCK
TENDER, OUTSIDE
NIPPER; DRY-PACKING OF CONCRETE (PLUGGING & FILLING OF SHE-BOLT HOLES); FENCE &/OR
GUARDRAIL ERECTOR: DISMANTLING &/OR RE-INSTALLATION OF ALL FENCE; FINEGRADER;
FIREWATCHER; FLAGMAN (CONING, PREPARING, STABLISHING & REMOVING PORTABLE ROADWAY
BARRICADE DEVICES); SIGNAL MEN ON ALL CONSTRUCTION WORK DEFINED HEREIN, INCLUDING
TRAFFIC CONTROL SIGNAL MEN AT CONSTRUCTION SITE; GENERAL EXCAVATION; BACKFILLING,
GRADING & ALL OTHER LABOR CONNECTED THEREWITH; DIGGING OF TRENCHES, DITCHES &
MANHOLES & THE LEVELING, GRADING & OTHER PREPARATION PRIOR TO LAYING PIPE OR
CONDUIT FOR ANY PURPOSE; EXCAVATIONS & FOUNDATIONS FOR BUILDINGS, PIERS,
FOUNDATIONS & HOLES, & ALL OTHER CONSTRUCTION. PREPARATION OF STREET WAYS &
BRIDGES; GENERAL LABORER: CLEANING & CLEARING OF ALL DEBRIS & SURPLUS MATERIAL.
CLEAN-UP OF RIGHT-OF-WAY. CLEARING & SLASHING OF BRUSH OR TREES BY HAND OR
MECHANICAL CUTTING. GENERAL CLEAN UP: SWEEPING, CLEANING, WASH-DOWN, WIPING OF
CONSTRUCTION FACILITY & EQUIPMENT (OTHER THAN ""LIGHT CLEAN UP (JANITORIAL) LABORER.
GARBAGE & DEBRIS HANDLERS & CLEANERS. APPLIANCE HANDLING (JOB SITE) (AFTER DELIVERY
UNLADING IN STORAGE AREA); GROUND & SOIL TREATMENT WORK (PEST CONTROL);
GUNITE/SHOTCRETE OPERATOR TENDER; JUNK YARD LABORERS (SAME AS SALVAGE YARD);
LASER BEAM ""TARGET MAN"" IN CONNECTION WITH LABORERS' WORK; LAYOUT PERSON FOR
PLASTIC (WHEN WORK INVOLVES WATERPROOFING FOR WATERPONDS, ARTIFICIAL LAKES &
RESERVOIRS); LIMBERS, BRUSH LOADERS, & PILERS; LOADING, UNLOADING, CARRYING,
DISTRIBUTING & HANDLING OF ALL RODS & MATERIAL FOR USE IN REINFORCING CONCRETE
CONSTRUCTION (EXCEPT WHEN A DERRICK OR OUTRIGGER OPERATED BY OTHER THAN HAND
POWER IS USED); LOADING, UNLOADING, SORTING, STOCKPILING, HANDLING & DISTRIBUTION
OF WATER MAINS, GAS MAINS & ALL PIPES; LOADING & UNLOADING OF ALL MATERIALS, FIXTURES,
FURNISHINGS & APPLIANCES FROM POINT OF DELIVERY TO STOCKPILE TO POINT OF
INSTALLATION; HOOKING & SIGNALING FROM TRUCK, CONVEYANCE OR STOCKPILE; MATERIAL
YARD LABORERS; PIPELAYER TENDER; PIPEWRAPPER, CAULKER, BANDER, KETTLEMEN, & MEN
APPLYING ASPHALT, LAYKOLD, CREOSOTE, & SIMILAR-TYPE MATERIALS (PIPE UNDER 6 INCHES);
PLASTERER LABORER; PREPARATION, CONSTRUCTION & MAINTENANCE OF ROADBEDS &
SUB-GRADE FOR ALL PAVING, INCLUDING EXCAVATION, DUMPING, & SPREADING OF SUB-GRADE
MATERIAL; PRESTRESSED OR PRECAST CONCRETE SLABS, WALLS, OR SECTIONS: ALL LOADING,
UNLOADING, STOCKPILING, HOOKING ON OF SUCH SLABS, WALLS OR SECTIONS; QUARRY
LABORERS; RAILROAD, STREETCAR, & RAIL TRANSIT MAINTENANCE & REPAIR; ROUSTABOUT;
RUBBISH TRUCKS IN CONNECTION WITH BUILDING CONSTRUCTION PROJECTS (EXCLUDING
CLEARING, GRUBBING, & EXCAVATING); SALVAGE YARD: ALL WORK CONNECTED WITH CUTTING,
CLEANING, STORING, STOCKPILING OR HANDLING OF MATERIALS, ALL CLEANUP, REMOVAL OF
DEBRIS, BURNING, BACK-FILLING & LANDSCAPING OF THE SITE; SANDBLASTING TENDER (POT
TENDER): HOSES & POTS OR MARKERS; SCAFFOLDS: ERECTION, PLANKING & REMOVAL OF ALL
SCAFFOLDS USED FOR SUPPORT FOR LATHERS, PLASTERS, BRICK LAYERS, MASONS, & OTHER
CONSTRUCTION TRADES CRAFTS; SCAFFOLDS: (SPECIALLY DESIGNED BY CARPENTERS) LABORERS
SHALL TEND SAID CARPENTER ON ERECTION & DISMANTLING THEREOF, PREPARATION FOR
FOUNDATION OR MUDSILLS, MAINTENANCE; SCRAPING OF FLOORS; SCREEDS: HANDLING OF
ALL SCREEDS TO BE REUSED; HANDLING, DISMANTLING & CONVEYANCE OF SCREEDS; SETTING,
LEVELING & SECURING OR BRACING OF METAL OR OTHER ROAD FORMS & EXPANSION JOINTS;
SHEETING PILING/TRENCH SHORING (HANDLING & PLACING OF SKIP SHEET OR WOOD PLANK
TRENCH SHORING); SHIP SCALERS; SHIPWRIGHT TENDER; SIGN ERECTOR (SUBDIVISION TRAFFIC,
REGULATORY, & STREET-NAME SIGNS); SLOPER; SLURRY SEAL CREWS (MIXER OPERATOR,
APPLICATOR, SQUEEGEE MAN, SHUTTLE MAN, TOP MAN); SNAPPING OF WALL TIES & REMOVAL
OF TIE RODS; SOIL TEST OPERATIONS OF SEMI & UNSKILLED LABOR SUCH AS FILLING SAND
BAGS; STRIPER (ASPHALT, CONCRETE OR OTHER PAVED SURFACES); TOOL ROOM ATTENDANT
(JOB SITE); TRAFFIC DELINEATING DEVICE APPLICATOR; UNDERPINNING, LAGGING, BRACING,
PROPPING & SHORING, LOADING, SIGNALING, RIGHT-OF-WAY CLEARANCE ALONG THE ROUTE
OF MOVEMENT, THE CLEARANCE OF NEW SITE, EXCAVATION OF FOUNDATION WHEN MOVING
A HOUSE OR STRUCTURE FROM OLD SITE TO NEW SITE; UTILITIES EMPLOYEES; WATER MAN;
WATERSCAPE/HARDSCAPE LABORERS; WIRE MESH PULLING (ALL CONCRETE POURING
OPERATIONS); WRECKING, STRIPPING, DISMANTLING & HANDLING CONCRETE FORMS AN FALSE
WORK.
----------------------------------------------------------------------------------------------------
WELDERS - Receive rate prescribed for craft performing
operation to which welding is incidental.
================================================================
Note: Executive Order (EO) 13706, Establishing Paid Sick Leave
for Federal Contractors applies to all contracts subject to the
Davis-Bacon Act for which the contract is awarded (and any
solicitation was issued) on or after January 1, 2017. If this
contract is covered by the EO, the contractor must provide
employees with 1 hour of paid sick leave for every 30 hours
they work, up to 56 hours of paid sick leave each year.
Employees must be permitted to use paid sick leave for their
own illness, injury or other health-related needs, including
preventive care; to assist a family member (or person who is
like family to the employee) who is ill, injured, or has other
health-related needs, including preventive care; or for reasons
resulting from, or to assist a family member (or person who is
like family to the employee) who is a victim of, domestic
violence, sexual assault, or stalking. Additional information
on contractor requirements and worker protections under the EO
is available at
https://www.dol.gov/agencies/whd/government-contracts.
Note: Executive Order 13658 generally applies to contracts subject to
the Davis-Bacon Act that were awarded on or between January 1,
2015 and January 29, 2022, and that have not been renewed or
extended on or after January 30, 2022. Executive Order 13658 does
not apply to contracts subject only to the Davis-Bacon Related Acts
regardless of when they were awarded. If a contract is subject to
Executive Order 13658, the contractor must pay all covered workers at
least $13.65 per hour (or the applicable wage rate listed on this wage
determination, if it is higher) for all hours spent performing on the
contract from May 11, 2026, through December 31, 2026. The applicable
Executive Order minimum wage rate will be adjusted annually.
Additional information on contractor requirements and worker
protections under Executive Order 13658 is available at
www.dol.gov/whd/govcontracts.
Unlisted classifications needed for work not included within
the scope of the classifications listed may be added after
award only as provided in the labor standards contract clauses
(29CFR 5.5 (a) (1) (iii)).
-----------------------------------------------------------------------------------------------------
The body of each wage determination lists the classifications
and wage rates that have been found to be prevailing for the
type(s) of construction and geographic area covered by the wage
determination. The classifications are listed in alphabetical
order under rate identifiers indicating whether the particular
rate is a union rate (current union negotiated rate), a survey
rate, a weighted union average rate, a state adopted rate, or a
supplemental classification rate.
Union Rate Identifiers
A four-letter identifier beginning with characters other than
�SU�, �UAVG�, �SA�, or �SC� denotes that a union rate was
prevailing for that classification in the survey. Example:
PLUM0198-005 07/01/2024. PLUM is an identifier of the union
whose collectively bargained rate prevailed in the survey for
this classification, which in this example would be Plumbers.
0198 indicates the local union number or district council
number where applicable, i.e., Plumbers Local 0198. The next
number, 005 in the example, is an internal number used in
processing the wage determination. The date, 07/01/2024 in the
example, is the effective date of the most current negotiated
rate.
Union prevailing wage rates are updated to reflect all changes
over time that are reported to WHD in the rates
in the collective bargaining agreement (CBA) governing the
classification.
Union Average Rate Identifiers
The UAVG identifier indicates that no single rate prevailed for
those classifications, but that 100% of the data reported for
the classifications reflected union rates. EXAMPLE:
UAVG-OH-0010 01/01/2024. UAVG indicates that the rate is a
weighted union average rate. OH indicates the State of Ohio.
The next number, 0010 in the example, is an internal number
used in producing the wage determination. The date, 01/01/2024
in the example, indicates the date the wage determination was
updated to reflect the most current union average rate.
A UAVG rate will be updated once a year, usually in January, to
reflect a weighted average of the current rates in the
collective bargaining agreements on which the rate is based.
Survey Rate Identifiers
The �SU� identifier indicates that either a single non-union
rate prevailed (as defined in 29 CFR 1.2) for this
classification in the survey or that the rate was derived by
computing a weighted average rate based on all the rates
reported in the survey for that classification. As a weighted
average rate includes all rates reported in the survey, it may
include both union and non-union rates. Example: SUFL2022-007
6/27/2024. SU indicates the rate is a single non-union
prevailing rate or a weighted average of survey data for that
classification. FL indicates the State of Florida. 2022 is the
year of the survey on which these classifications and rates are
based. The next number, 007 in the example, is an internal
number used in producing the wage determination. The date,
6/27/2024 in the example, indicates the survey completion date
for the classifications and rates under that identifier.
�SU� wage rates typically remain in effect until a new survey
is conducted. However, the Wage and Hour Division (WHD) has the
discretion to update such rates under 29 CFR 1.6(c)(1).
State Adopted Rate Identifiers
The �SA� identifier indicates that the classifications and
prevailing wage rates set by a state (or local) government were
adopted under 29 C.F.R 1.3(g)-(h). Example: SAME2023-007
01/03/2024. SA reflects that the rates are state adopted. ME
refers to the State of Maine. 2023 is the year during which the
state completed the survey on which the listed classifications
and rates are based. The next number, 007 in the example, is an
internal number used in producing the wage determination.
The date, 01/03/2024 in the example, reflects the date on which
the classifications and rates under the �SA� identifier took
effect under state law in the state from which the rates were
adopted.
-----------------------------------------------------------------------------------------------------
WAGE DETERMINATION APPEALS PROCESS
1) Has there been an initial decision in the matter? This can
be:
a) a survey underlying a wage determination
b) an existing published wage determination
c) an initial WHD letter setting forth a position on
a wage determination matter
d) an initial conformance (additional classification
and rate) determination
On survey related matters, initial contact, including requests
for summaries of surveys, should be directed to the WHD Branch
of Wage Surveys. Requests can be submitted via email to
davisbaconinfo@dol.gov or by mail to:
Branch of Wage Surveys
Wage and Hour Division
U.S. Department of Labor
200 Constitution Avenue, N.W.
Washington, DC 20210
Regarding any other wage determination matter such as
conformance decisions, requests for initial decisions should be
directed to the WHD Branch of Construction Wage Determinations.
Requests can be submitted via email to BCWD-Office@dol.gov or
by mail to:
Branch of Construction Wage Determinations
Wage and Hour Division
U.S. Department of Labor
200 Constitution Avenue, N.W.
Washington, DC 20210
2) If an initial decision has been issued, then any interested
party (those affected by the action) that disagrees with the
decision can request review and reconsideration from the Wage
and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7).
Requests for review and reconsideration can be submitted via
email to dba.reconsideration@dol.gov or by mail to:
Wage and Hour Administrator
U.S. Department of Labor
200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the
interested party's position and any information (wage payment
data, project description, area practice material, etc.) that
the requestor considers relevant to the issue.
3) If the decision of the Administrator is not favorable, an
interested party may appeal directly to the Administrative
Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board
U.S. Department of Labor
200 Constitution Avenue, N.W.
Washington, DC 20210.
================================================================
END OF GENERAL DECISION"