Prevailing Wage Index
HomePrevailing wage by stateNew JerseyDeterminations › NJ20260027

Wage determination NJ20260027

Building construction - New Jersey, revision 2, modified 2026-05-18

Verify against the official document: this page mirrors WD NJ20260027 revision 2 (retrieved ) for reference. The determination incorporated into your contract governs - read the official copy at SAM.gov.

Rate schedules

Parsed from the official text as a reading aid - zone pay, group definitions and footnotes in the full text below modify specific classifications. Identifier prefixes: union-agreement rates carry the local's id, SU marks DOL survey rates (how to read a determination).

ASBE0014-003 (collectively bargained (union) rate, 05/01/2025)

ClassificationBase rateFringes
ASBESTOS WORKER/HEAT & FROST INSULATOR: (INCLUDES THE APPLICATION OF ALL INSULATING MATERIALS, PROTECTIVE COVERINGS, COATINGS AND FINISHINGS TO ALL TYPES OF MECHANICAL SYSTEMS; ALS$60.8448.38

ASBE0089-003 (collectively bargained (union) rate, 07/01/2025)

ClassificationBase rateFringes
ASBESTOS WORKER/HEAT & FROST INSULATOR: (INCLUDES THE APPLICATION OF ALL INSULATING MATERIALS, PROTECTIVE COVERINGS, COATINGS AND FINISHINGS TO ALL TYPES OF MECHANICAL SYSTEMS; ALS$55.8040.80

BRNJ0002-013 (collectively bargained (union) rate, 05/01/2021)

ClassificationBase rateFringes
BRICKLAYER Work on high stacks: 22% per hour additional$45.2033.26

BRNJ0007-012 (collectively bargained (union) rate, 07/07/2025)

ClassificationBase rateFringes
MARBLE SETTER$64.6640.97

BRNJ0007-014 (collectively bargained (union) rate, 07/01/2025)

ClassificationBase rateFringes
TERRAZZO WORKER/SETTER$61.7742.82

BRNJ0007-017 (collectively bargained (union) rate, 06/02/2025)

ClassificationBase rateFringes
TILE SETTER$52.3138.01
TILE Work grouting all epoxy: $10.00 additional per day$43.6332.12

CARP0006-009 (collectively bargained (union) rate, 05/01/2025)

ClassificationBase rateFringes
CARPENTER (SCAFFOLD The first sixty feet at the regular rate, 10% per hour additional for each additional fifty feet thereafter$57.4234.17

CARP0006-010 (collectively bargained (union) rate, 05/01/2025)

ClassificationBase rateFringes
CARPENTER, INCLUDING ACOUSTICAL CEILING INSTALLATION, DRYWALL HANGING, FORMWORK, BATT AND BLOWN INSULATION$57.4234.17

CARP0029-006 (collectively bargained (union) rate, 05/01/2025)

ClassificationBase rateFringes
SOFT FLOOR LAYER$57.4234.17

CARP0454-009 (collectively bargained (union) rate, 05/01/2023)

ClassificationBase rateFringes
PILEDRIVERMAN PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED THAT THE WORKER WORKS AN$46.7341.69

CARP0715-007 (collectively bargained (union) rate, 05/01/2025)

ClassificationBase rateFringes
MILLWRIGHT (Work of erection and dismantling of elevators and towers, such as concrete conveyors and temporary material elevators, scaffolding or other structures to be used as sca$58.8435.06

ELEC0269-017 (collectively bargained (union) rate, 01/05/2026)

ClassificationBase rateFringes
ELECTRICIAN AND CABLE SPLICER: INCLUDES LOW VOLTAGE WIRING (BURLINGTON COUNTY (NORTH OF A LINE FOLLOWING THE WEST AND SOUTH LIMITS OF BURLINGTON BOROUGH FROM THE DELAWARE RIVER, IN$63.8241.99

ELEC0351-001 (collectively bargained (union) rate, 09/30/2024)

ClassificationBase rateFringes
ELECTRICIAN AND CABLE SPLICER (ATLANTIC COUNTY; BURLINGTON COUNTY (south of a line following the west and south limits of Burlington Borough from the Delaware River, in a southeast$55.0548.76
ELECTRICIAN: CABLE SPLICER ON LEAD CABLE (ATLANTIC COUNTY; BURLINGTON COUNTY (south of a line following the west and south limits of Burlington Borough from the Delaware River, in $45.5134.39

ELEV0005-004 (collectively bargained (union) rate, 01/01/2025)

ClassificationBase rateFringes
ELEVATOR A. PAID VACATION: Employer contributes 8% of basic hourly rate for 5 years or more of service or 6% for 6 months to 5 years of B. Eight Paid Holidays (provided employee ha$71.8538.44

ENGI0825-020 (collectively bargained (union) rate, 07/01/2025)

ClassificationBase rateFringes
POWER EQUIPMENT OPERATORS: GROUP 5 OILER HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZA$52.8837.50
POWER EQUIPMENT OPERATORS: GROUP 4 BOBCAT/SKID LOADER; COMPRESSOR (SINGLE); FARM TRACTOR; FRONT END LOADER (UNDER 1 CU. YD.); HYDROSEEDER; ROLLER, GRADE; PUMP, HYDRAULIC HAZARDOUS $56.5937.50
POWER EQUIPMENT OPERATORS: GROUP 3 ASPHALT SPREADER; BULLDOZER;COMPRESSOR(2 OR 3) (IN BATTERY) (WITHIN 100 FT.); FORKLIFT; FRONT END LOADER (1 CU. YD. AND OVER BUT LESS THAN 2 CU. $58.2237.50
POWER EQUIPMENT OPERATORS: GROUP 2 BACKHOE LOADER COMBO; CONCRETE PUMPER; GRADER/BLADE (FINISH); HOIST; HYDRAULIC CRANE, 10 TONS AND UNDER; FRONT END LOADER (2 CU. YD. BUT LESS THA$60.1337.50
POWER EQUIPMENT OPERATORS: GROUP 1 BACKHOE, INCLUDING BACKHOE TRACK; BOOM; CONCRETE PAVING MACHINE; CRANE (ALL TYPES, INCLUDING OVERHEAD AND STRADDLE TRAVELING TYPE); DRILL (DOWN-T$61.7237.50

IRON0399-005 (collectively bargained (union) rate, 07/01/2024)

ClassificationBase rateFringes
IRONWORKER: STRUCTURAL AND ORNAMENTAL$54.2438.40
IRONWORKER: REINFORCING$53.2438.40

LABO0008-001 (collectively bargained (union) rate, 05/01/2011)

ClassificationBase rateFringes
ASBESTOS REMOVAL The removal, abatement, enclosure and decontamination of personal protective equipment, chemical protective clothing and machinery relating to asbestos and/or toxi$28.3721.62

LABO0077-002 (collectively bargained (union) rate, 05/01/2022)

ClassificationBase rateFringes
LABORER: MASON TENDER: BRICK/CEMENT/CONCRETE$36.5030.22

LABO0077-004 (collectively bargained (union) rate, 05/01/2022)

ClassificationBase rateFringes
LABORER: ASPHALT SHOVELER, ASPHALT SPREADER, LANDSCAPE LABORER, PIPELAYER, POWER TOOLE OPERATOR AND SCREEDMAN$35.7530.22

PAIN0021-032 (collectively bargained (union) rate, 05/01/2025)

ClassificationBase rateFringes
GLAZIER (BURLINGTON COUNTY (south of a line drawn between these cities: Florence to Bustleton to Columbus to Jobstown to Pemberton to Ongs Hat to Chatsworth to Whiting to Pinewald $49.9635.11

PAIN0711-011 (collectively bargained (union) rate, 05/01/2025)

ClassificationBase rateFringes
GLAZIER (BURLINGTON COUNTY (north of a line drawn between these cities: Florence to Bustleton to Columbus to Jobstown to Pemberton to Ongs Hat to Chatsworth to Whiting to Pinewald $52.6831.29

PAIN0711-018 (collectively bargained (union) rate, 05/01/2025)

ClassificationBase rateFringes
DRYWALL FINISHER/TAPER$44.8730.15

PAIN0711-019 (collectively bargained (union) rate, 05/01/2025)

ClassificationBase rateFringes
PAINTER (SPRAY)$45.5529.86
PAINTER (BRUSH & ROLLER)$45.5529.86

PLAS0592-036 (collectively bargained (union) rate, 05/01/2025)

ClassificationBase rateFringes
CEMENT MASON/CONCRETE FINISHER$53.2133.42

PLUM0009-015 (collectively bargained (union) rate, 07/01/2025)

ClassificationBase rateFringes
PLUMBER: EXCLUDING HVAC PIPE INSTALLATION (BURLINGTON COUNTY (NORTH OF A LINE DRAWN FROM THE TOWN OF BURLINGTON CITY, INCLUDES BURLINGTON CITY; THEN, ALONG COUNTY ROAD ROUTE 541 EA$59.5746.45
PIPEFITTER: INCLUDING HVAC PIPE INSTALLATION (BURLINGTON COUNTY (NORTH OF A LINE DRAWN FROM THE TOWN OF BURLINGTON CITY, INCLUDES BURLINGTON CITY; THEN, ALONG COUNTY ROAD ROUTE 541$59.5746.45
PLUMBER: SERVICE AND REPAIR (BURLINGTON COUNTY (NORTH OF A LINE DRAWN FROM THE TOWN OF BURLINGTON CITY, INCLUDES BURLINGTON CITY; THEN, ALONG COUNTY ROAD ROUTE 541 EAST, ALSO KNOWN$46.2329.23
PIPEFITTER: SERVICE AND REPAIR (BURLINGTON COUNTY (NORTH OF A LINE DRAWN FROM THE TOWN OF BURLINGTON CITY, INCLUDES BURLINGTON CITY; THEN, ALONG COUNTY ROAD ROUTE 541 EAST, ALSO KN$46.2329.23

PLUM0322-008 (collectively bargained (union) rate, 05/01/2025)

ClassificationBase rateFringes
PLUMBER: EXCLUDING HVAC PIPE INSTALLATION (BURLINGTON COUNTY (SOUTH OF A LINE DRAWN FROM THE TOWN OF BURLINGTON CITY, DOES NOT INCLUDE BURLINGTON CITY; THEN, ALONG COUNTY ROAD ROUT$56.3050.76
PIPEFITTER: INCLUDING HVAC PIPE INSTALLATION (BURLINGTON COUNTY (SOUTH OF A LINE DRAWN FROM THE TOWN OF BURLINGTON CITY, DOES NOT INCLUDE BURLINGTON CITY; THEN, ALONG COUNTY ROAD R$56.3050.76

ROOF0030-027 (collectively bargained (union) rate, 05/01/2025)

ClassificationBase rateFringes
ROOFER: Mopper, and operator of felt-laying machine: $.50 per hour Work applying roofing material, on any new construction job, on those days on which a felt-laying machine or slag$35.9521.85
ROOFER: SLATE AND Mopper, and operator of felt-laying machine: $.50 per hour Work applying roofing material, on any new construction job, on those days on which a felt-laying machi$38.9521.85
ROOFER: ALL OTHER Mopper, and operator of felt-laying machine: $.50 per hour Work applying roofing material, on any new construction job, on those days on which a felt-laying machi$46.0334.27

SFNJ0669-006 (collectively bargained (union) rate, 04/01/2025)

ClassificationBase rateFringes
SPRINKLER FITTER (FIRE SPRINKLERS)$59.1936.51

SFNJ0692-002 (collectively bargained (union) rate, 05/01/2021)

ClassificationBase rateFringes
SPRINKLER FITTER (FIRE SPRINKLERS) (WITHIN 15 MILES BEYOND THE CITY LIMITS OF PHILADELPHIA)$60.8330.34

SHEE0027-009 (collectively bargained (union) rate, 06/01/2024)

ClassificationBase rateFringes
SHEET METAL WORKER (INCLUDING HVAC DUCT INSTALLATION)$59.0847.06

SUNJ2004-003 (DOL wage survey rate, 01/02/2009)

ClassificationBase rateFringes
PLASTERER$42.330.00
LABORER: COMMON OR GENERAL$19.2712.42

TEAM0469-003 (collectively bargained (union) rate, 05/01/2025)

ClassificationBase rateFringes
TRUCK DRIVER: DUMP TRUCK (BURLINGTON COUNTY (EAST OF A LINE DRAWN FROM THE NEW JERSEY TURNPIKE TO THE DELAWARE HAZARDOUS WASTE REMOVAL WORK: Work on a state or federally designated$48.6342.66
TRUCK DRIVER: OFF THE ROAD TRUCK (BURLINGTON COUNTY (EAST OF A LINE DRAWN FROM THE NEW JERSEY TURNPIKE TO THE DELAWARE HAZARDOUS WASTE REMOVAL WORK: Work on a state or federally de$48.7842.66

TEAM0676-002 (collectively bargained (union) rate, 05/01/2025)

ClassificationBase rateFringes
TRUCK DRIVER: OFF THE ROAD TRUCK (BURLINGTON COUNTY (WEST OF THE LINE DRAWN FROM THE NEW JERSEY TURNPIKE TO THE DELAWARE RIVER)) HAZARDOUS WASTE REMOVAL WORK: Work on a state or fe$44.6534.11
TRUCK DRIVER: DUMP TRUCK DRIVERS (BURLINGTON COUNTY (WEST OF THE LINE DRAWN FROM THE NEW JERSEY TURNPIKE TO THE DELAWARE RIVER)) HAZARDOUS WASTE REMOVAL WORK: Work on a state or fe$44.3034.11
Full official text of NJ20260027 rev 2
"General Decision Number: NJ20260027 05/18/2026


State: New Jersey


Construction Types: Building


Counties: New Jersey Counties of 
Burlington




 


Modification Number     Publication Date
          1                01/30/2026
          2                05/18/2026


 ASBE0014-003 05/01/2025
                                                     Rates                  Fringes
ASBESTOS WORKER/HEAT & FROST INSULATOR: (INCLUDES 
THE APPLICATION OF ALL INSULATING MATERIALS, 
PROTECTIVE COVERINGS, COATINGS AND FINISHINGS TO 
ALL TYPES OF MECHANICAL SYSTEMS; ALSO, THE 
APPLICATION OF FIRESTOPPING MATERIAL TO OPENINGS 
AND PENETRATIONS IN WALLS, FLOORS, CEILINGS AND 
CURTAIN WALLS; ALSO, ALL LEAD ABATEMENT) 
(BURLINGTON COUNTY (CITY OF BEVERLY; TOWNSHIPS OF 
CINNAMINSON, DELANCO, DELRON, EDGEWATER PARK, 
EVESHAM, HAINESPORT AND LUMBERTON; BOROUGH OF MAPLE 
SHADE; TOWNSHIP OF MEDFOD; BOROUGH OF MEDFORD 
LAKES; TOWNSHIP OF RIVERSIDE; BOROUGH OF RIVERTON; 
TOWNSHIPS OF SHAMONG, SOUTHAMPTON, TABERNACLE, 
WESTHAMPTON AND WILLINGBORO)).......................$ 60.84                  48.38
----------------------------------------------------------------

 ASBE0089-003 07/01/2025
                                                     Rates                  Fringes
ASBESTOS WORKER/HEAT & FROST INSULATOR: (INCLUDES 
THE APPLICATION OF ALL INSULATING MATERIALS, 
PROTECTIVE COVERINGS, COATINGS AND FINISHINGS TO 
ALL TYPES OF MECHANICAL SYSTEMS; ALSO, THE 
APPLICATION OF FIRESTOPPING MATERIAL TO OPENINGS 
AND PENETRATIONS IN WALLS, FLOORS, CEILINGS AND 
CURTAIN WALLS; ALSO, ALL LEAD ABATEMENT) 
(BURLINGTON COUNTY (TOWNSHIPS OF BORDENTOWN, 
BURLINGTON, CHESTERFIELD, EASTHAMPTON, FLORENCE, 
MANSFIELD, MT. HOLLY, NEW HANOVER, NORTH HANOVER, 
PEMBERTON, SPRINGFIELD AND WOODLAND) PAID HOLIDAYS: 
The last day prior to the Christmas and New Year's 
Day observed holiday: 4 hrs. pay....................$ 55.80                  40.80
----------------------------------------------------------------

 BRNJ0002-013 05/01/2021
                                                     Rates                  Fringes
BRICKLAYER 
Work on high stacks: 22% per hour additional........$ 45.20                  33.26
----------------------------------------------------------------

 BRNJ0007-012 07/07/2025
                                                     Rates                  Fringes
MARBLE SETTER.......................................$ 64.66                  40.97
----------------------------------------------------------------

 BRNJ0007-014 07/01/2025
                                                     Rates                  Fringes
TERRAZZO WORKER/SETTER..............................$ 61.77                  42.82
----------------------------------------------------------------

 BRNJ0007-017 06/02/2025
                                                     Rates                  Fringes
TILE  SETTER........................................$ 52.31                  38.01
TILE 
Work grouting all epoxy: $10.00 additional per day..$ 43.63                  32.12
----------------------------------------------------------------

 CARP0006-009 05/01/2025
                                                     Rates                  Fringes
CARPENTER (SCAFFOLD 
The first sixty feet at the regular rate, 10% per 
hour additional for each additional fifty feet 
thereafter..........................................$ 57.42                  34.17
----------------------------------------------------------------

 CARP0006-010 05/01/2025
                                                     Rates                  Fringes
CARPENTER, INCLUDING ACOUSTICAL CEILING 
INSTALLATION, DRYWALL HANGING, FORMWORK, BATT AND 
BLOWN INSULATION ...................................$ 57.42                  34.17
----------------------------------------------------------------

 CARP0029-006 05/01/2025
                                                     Rates                  Fringes
SOFT FLOOR LAYER....................................$ 57.42                  34.17
----------------------------------------------------------------

 CARP0454-009 05/01/2023
                                                     Rates                  Fringes
PILEDRIVERMAN PAID HOLIDAYS:  NEW YEAR'S DAY, 
WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE 
DAY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY; 
PROVIDED THAT THE WORKER WORKS ANY OF THE THREE 
DAYS IN THE FIVE-DAY WORK WEEK PRECEDING THE 
HOLIDAY AND THE FIRST WORK DAY AFTER THE HOLIDAY. ..$ 46.73                  41.69
----------------------------------------------------------------

 CARP0715-007 05/01/2025
                                                     Rates                  Fringes
MILLWRIGHT (Work of erection and dismantling of 
elevators and towers, such as concrete conveyors 
and temporary material elevators, scaffolding or 
other structures to be used as scaffolding inside 
or outside of buildings: the first sixty feet at 
the regular rate, 10% per hour additional for each 
additional fifty feet thereafter.)..................$ 58.84                  35.06
----------------------------------------------------------------

 ELEC0269-017 01/05/2026
                                                     Rates                  Fringes
ELECTRICIAN AND CABLE SPLICER: INCLUDES LOW VOLTAGE 
WIRING (BURLINGTON COUNTY (NORTH OF A LINE 
FOLLOWING THE WEST AND SOUTH LIMITS OF BURLINGTON 
BOROUGH FROM THE DELAWARE RIVER, IN A SOUTHEASTERLY 
DIRECTION, TO THE BURLINGTON - MT. HOLLY ROAD; 
THEN, SOUTH-SOUTHEAST ALONG THE BURLINGTON - MT. 
HOLLY ROAD TO THE TOWN OF MT. HOLLY, INCLUDES MT. 
HOLLY; THEN, EAST ALONG THE PENNSYLVANIA RAILROAD 
TO THE TOWN OF NEW LISBON, INCLUDES NEW LISBON; 
THEN, CONTINUING ALONG THE PENNSYLVANIA RAILROAD TO 
THE OCEAN COUNTY LINE)).............................$ 63.82                  41.99
----------------------------------------------------------------

 ELEC0351-001 09/30/2024
                                                     Rates                  Fringes
ELECTRICIAN AND CABLE SPLICER (ATLANTIC COUNTY; 
BURLINGTON COUNTY (south of a line following the 
west and south limits of Burlington Borough from 
the Delaware River, in a southeasterly direction, 
to the Burlington - Mt. Holly road; then, 
south-southeast along the Burlington - Mt. Holly 
road to the town of Mt. Holly, does not include Mt. 
Holly; then, east along the Pennsylvania Railroad 
to the town of New Lisbon, does not include New 
Lisbon; then, continuing along the Pennsylvania 
Railroad to the Ocean County line); CAMDEN, CAPE 
MAY, CUMBERLAND, GLOUCESTER AND SALEM COUNTIES).....$ 55.05                  48.76
ELECTRICIAN: CABLE SPLICER ON LEAD CABLE (ATLANTIC 
COUNTY; BURLINGTON COUNTY (south of a line 
following the west and south limits of Burlington 
Borough from the Delaware River, in a southeasterly 
direction, to the Burlington - Mt. Holly road; 
then, south-southeast along the Burlington - Mt. 
Holly road to the town of Mt. Holly, does not 
include Mt. Holly; then, east along the 
Pennsylvania Railroad to the town of New Lisbon, 
does not include New Lisbon; then, continuing along 
the Pennsylvania Railroad to the Ocean County 
line); CAMDEN, CAPE MAY, CUMBERLAND, GLOUCESTER AND 
SALEM COUNTIES).....................................$ 45.51                  34.39
----------------------------------------------------------------

 ELEV0005-004 01/01/2025
                                                     Rates                  Fringes
ELEVATOR 
A.  PAID VACATION: Employer contributes 8% of basic 
hourly rate for 5 years or more of service or 6% 
for 6 months to 5 years of 
B. Eight Paid Holidays (provided employee has 
worked 5 consecutive days before and the working 
day after the holiday):  New Years's Day; Memorial 
Day; Independence Day; Labor Day; Veteran's Day; 
Thanksgiving Day and the Friday after Thanksgiving 
Day, and Christmas Day..............................$ 71.85                  38.44
----------------------------------------------------------------

 ENGI0825-020 07/01/2025
                                                     Rates                  Fringes
POWER EQUIPMENT OPERATORS: GROUP 5 OILER  HAZARDOUS 
WASTE REMOVAL WORK:  WORK ON A STATE OR FEDERALLY 
DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER 
IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND 
WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR 
RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR 
ADDITIONAL.  PAID HOLIDAYS:  NEW YEAR'S DAY, 
WASHINGTON'S BIRTHDAY OBSERVED, MEMORIAL DAY, 
INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION 
DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS 
DAY; PROVIDED 1) THAT THE WORKER WORKS THREE OF THE 
PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR, 
THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY 
AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS 
THE WORK DAY BEFORE AND THE WORK DAY AFTER THE 
HOLIDAY.............................................$ 52.88                  37.50
POWER EQUIPMENT OPERATORS: GROUP 4 BOBCAT/SKID 
LOADER; COMPRESSOR (SINGLE); FARM TRACTOR; FRONT 
END LOADER (UNDER 1 CU. YD.); HYDROSEEDER; ROLLER, 
GRADE; PUMP, HYDRAULIC  HAZARDOUS WASTE REMOVAL 
WORK:  WORK ON A STATE OR FEDERALLY DESIGNATED 
HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT 
CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL 
PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, 
SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL.  
PAID HOLIDAYS:  NEW YEAR'S DAY, WASHINGTON'S 
BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, 
LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S 
DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 
1) THAT THE WORKER WORKS THREE OF THE PRECEDING 
FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY 
BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE 
HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY 
BEFORE AND THE WORK DAY AFTER THE HOLIDAY...........$ 56.59                  37.50
POWER EQUIPMENT OPERATORS: GROUP 3 ASPHALT 
SPREADER; BULLDOZER;COMPRESSOR(2 OR 3) (IN BATTERY) 
(WITHIN 100 FT.);  FORKLIFT; FRONT END LOADER (1 
CU. YD. AND OVER BUT LESS THAN 2 CU. YD.); LULL; 
MECHANIC; PAVER, ASPHALT; ROLLER, BLACKTOP; 
TRACTOR;  HAZARDOUS WASTE REMOVAL WORK:  WORK ON A 
STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, 
WHERE THE WORKER IS IN DIRECT CONTACT WITH 
HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE 
EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE 
PROTECTION: 20% PER HOUR ADDITIONAL.  PAID 
HOLIDAYS:  NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY 
OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, LABOR 
DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, 
THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 1) 
THAT THE WORKER WORKS THREE OF THE PRECEDING FIVE 
WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY 
BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE 
HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY 
BEFORE AND THE WORK DAY AFTER THE HOLIDAY...........$ 58.22                  37.50
POWER EQUIPMENT OPERATORS: GROUP 2 BACKHOE LOADER 
COMBO; CONCRETE PUMPER; GRADER/BLADE (FINISH); 
HOIST; HYDRAULIC CRANE, 10 TONS AND UNDER;  FRONT 
END LOADER (2 CU. YD. BUT LESS THAN 5 CU. YD.); 
SCRAPER; SIDE BOOM  HAZARDOUS WASTE REMOVAL WORK:  
WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS 
WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT 
WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL 
PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, 
SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL.  
PAID HOLIDAYS:  NEW YEAR'S DAY, WASHINGTON'S 
BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, 
LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S 
DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 
1) THAT THE WORKER WORKS THREE OF THE PRECEDING 
FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY 
BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE 
HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY 
BEFORE AND THE WORK DAY AFTER THE HOLIDAY...........$ 60.13                  37.50
POWER EQUIPMENT OPERATORS: GROUP 1 BACKHOE, 
INCLUDING BACKHOE TRACK; BOOM; CONCRETE PAVING 
MACHINE; CRANE (ALL TYPES, INCLUDING OVERHEAD AND 
STRADDLE TRAVELING TYPE); DRILL (DOWN-THE-HOLE 
DRILL, ROTARY DRILL, SELF-PROPELLED HYDRAULIC 
DRILL, SELF-POWERED DRILL); ELEVATING GRADER; 
EXCAVATOR; FRONT END LOADER (5 CU. YD. AND OVER); 
PILEDRIVER (LENGTH OF BOOM, INCLUDING LENGTH OF 
LEADS, SHALL DETERMINE PREMIUM RATE APPLICABLE); 
TRENCHER  HAZARDOUS WASTE REMOVAL WORK:  WORK ON A 
STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, 
WHERE THE WORKER IS IN DIRECT CONTACT WITH 
HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE 
EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE 
PROTECTION: 20% PER HOUR ADDITIONAL.  PAID 
HOLIDAYS:  NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY 
OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, LABOR 
DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, 
THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 1) 
THAT THE WORKER WORKS THREE OF THE PRECEDING FIVE 
WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY 
BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE 
HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY 
BEFORE AND THE WORK DAY AFTER THE HOLIDAY...........$ 61.72                  37.50
----------------------------------------------------------------

 IRON0399-005 07/01/2024
                                                     Rates                  Fringes
IRONWORKER: STRUCTURAL AND ORNAMENTAL...............$ 54.24                  38.40
IRONWORKER: REINFORCING.............................$ 53.24                  38.40
----------------------------------------------------------------

 LABO0008-001 05/01/2011
                                                     Rates                  Fringes
ASBESTOS REMOVAL 
The removal, abatement, enclosure and 
decontamination of personal protective equipment, 
chemical protective clothing and machinery relating 
to asbestos and/or toxic and hazardous waste or 
materials which shall include but not necessarily 
be limited to: the erection, moving, servicing and 
dismantling of all enclosures, scaffolding and 
barricades; the operation of all tools and 
equipment normally used in the removal or abatement 
of asbestos and toxic or hazardous waste or 
materials; the    labeling, bagging, cartoning, 
crating, or other packaging of materials for 
disposal; the clean-up of the worksite; and all 
other work incidental to the removal, abatement, 
encapsulation, enclosure, and decontamination of 
asbestos and toxic or hazardous waste or materials; 
and, in addition, all work tasks involved in the 
maintenance and operation of energy resource 
recovery plants (co-generation plants)..............$ 28.37                  21.62
----------------------------------------------------------------

 LABO0077-002 05/01/2022
                                                     Rates                  Fringes
LABORER: MASON TENDER: BRICK/CEMENT/CONCRETE........$ 36.50                  30.22
----------------------------------------------------------------

 LABO0077-004 05/01/2022
                                                     Rates                  Fringes
LABORER: ASPHALT SHOVELER, ASPHALT SPREADER, 
LANDSCAPE LABORER, PIPELAYER, POWER TOOLE OPERATOR 
AND SCREEDMAN.......................................$ 35.75                  30.22
----------------------------------------------------------------

 PAIN0021-032 05/01/2025
                                                     Rates                  Fringes
GLAZIER (BURLINGTON COUNTY (south of a line drawn 
between these cities: Florence to Bustleton to 
Columbus to Jobstown to Pemberton to Ongs Hat to 
Chatsworth to Whiting to Pinewald to Ocean Gate to 
Seaside 
Work at 30 ft. above the working surface, or on a 
swing stage: $1.00 per hour additional..............$ 49.96                  35.11
----------------------------------------------------------------

 PAIN0711-011 05/01/2025
                                                     Rates                  Fringes
GLAZIER (BURLINGTON COUNTY (north of a line drawn 
between these cities: Florence to Bustleton to 
Columbus to Jobstown to Pemberton to Ongs Hat to 
Chatsworth to Whiting to Pinewald to Ocean Gate to 
Seaside 
Work welding or using a cutting torch: $1.00 per 
hour 
Work on a swing stage scaffold; on a pipe scaffold 
providing the working height of the platform is 30 
ft. or above; and on motorized lifts provided that 
the height of the lift platform is above the second 
floor or above thirty feet:   $1.00 per hour 
additional..........................................$ 52.68                  31.29
----------------------------------------------------------------

 PAIN0711-018 05/01/2025
                                                     Rates                  Fringes
DRYWALL FINISHER/TAPER..............................$ 44.87                  30.15
----------------------------------------------------------------

 PAIN0711-019 05/01/2025
                                                     Rates                  Fringes
PAINTER (SPRAY).....................................$ 45.55                  29.86
PAINTER (BRUSH & ROLLER)............................$ 45.55                  29.86
----------------------------------------------------------------

 PLAS0592-036 05/01/2025
                                                     Rates                  Fringes
CEMENT MASON/CONCRETE FINISHER......................$ 53.21                  33.42
----------------------------------------------------------------

 PLUM0009-015 07/01/2025
                                                     Rates                  Fringes
PLUMBER: EXCLUDING HVAC PIPE INSTALLATION 
(BURLINGTON COUNTY (NORTH OF A LINE DRAWN FROM THE 
TOWN OF BURLINGTON CITY, INCLUDES BURLINGTON CITY; 
THEN, ALONG COUNTY ROAD ROUTE 541 EAST, ALSO KNOWN 
AS HIGH ST., UNTIL IT REACHES THE CITY OF MT. 
HOLLY, INCLUDES THE CITY OF MT. HOLLY; THEN, ALONG 
MADISON AVE. IN MT. HOLLY TO STATE ROAD ROUTE 38 
EAST; THEN, ALONG STATE ROAD ROUTE 38 EAST UNTIL IT 
CROSSES OVER STATE ROAD ROUTE 206 AND BECOMES 
COUNTY ROAD ROUTE 530; THEN, ALONG COUNTY ROAD 
ROUTE 530 TO Magnolia Road, includes Pemberton 
Borough; then, south on Magnolia Road in Pemberton 
Township to Magnolia New Lisbon Road (Route 545); 
then, south on Mt. Holly Misery Road to State Road 
Route 70 East; then, along State Road Route 70 East 
to the Ocean County line)...........................$ 59.57                  46.45
PIPEFITTER: INCLUDING HVAC PIPE INSTALLATION 
(BURLINGTON COUNTY (NORTH OF A LINE DRAWN FROM THE 
TOWN OF BURLINGTON CITY, INCLUDES BURLINGTON CITY; 
THEN, ALONG COUNTY ROAD ROUTE 541 EAST, ALSO KNOWN 
AS HIGH ST., UNTIL IT REACHES THE CITY OF MT. 
HOLLY, INCLUDES THE CITY OF MT. HOLLY; THEN, ALONG 
MADISON AVE. IN MT. HOLLY TO STATE ROAD ROUTE 38 
EAST; THEN, ALONG STATE ROAD ROUTE 38 EAST UNTIL IT 
CROSSES OVER STATE ROAD ROUTE 206 AND BECOMES 
COUNTY ROAD ROUTE 530; THEN, ALONG COUNTY ROAD 
ROUTE 530 to Magnolia Road, includes Pemberton 
Borough; then, south on Magnolia Road in Pemberton 
Township to Magnolia New Lisbon Road (Route 545); 
then, south on Mt. Holly Misery Road to State Road 
Route 70 East; then, along State Road Route 70 East 
to the Ocean County line)...........................$ 59.57                  46.45
PLUMBER: SERVICE AND REPAIR (BURLINGTON COUNTY 
(NORTH OF A LINE DRAWN FROM THE TOWN OF BURLINGTON 
CITY, INCLUDES BURLINGTON CITY; THEN, ALONG COUNTY 
ROAD ROUTE 541 EAST, ALSO KNOWN AS HIGH ST., UNTIL 
IT REACHES THE CITY OF MT. HOLLY, INCLUDES THE CITY 
OF MT. HOLLY; THEN, ALONG MADISON AVE. IN MT. HOLLY 
TO STATE ROAD ROUTE 38 EAST; THEN, ALONG STATE ROAD 
ROUTE 38 EAST UNTIL IT CROSSES OVER STATE ROAD 
ROUTE 206 AND BECOMES COUNTY ROAD ROUTE 530; THEN, 
ALONG COUNTY ROAD ROUTE 530 TO Magnolia Road, 
includes Pemberton Borough; then, south on Magnolia 
Road in Pemberton Township to Magnolia New Lisbon 
Road (Route 545); then, south on Mt. Holly Misery 
Road to State Road Route 70 East; then, along State 
Road Route 70 East to the Ocean County line)........$ 46.23                  29.23
PIPEFITTER: SERVICE AND REPAIR (BURLINGTON COUNTY 
(NORTH OF A LINE DRAWN FROM THE TOWN OF BURLINGTON 
CITY, INCLUDES BURLINGTON CITY; THEN, ALONG COUNTY 
ROAD ROUTE 541 EAST, ALSO KNOWN AS HIGH ST., UNTIL 
IT REACHES THE CITY OF MT. HOLLY, INCLUDES THE CITY 
OF MT. HOLLY; THEN, ALONG MADISON AVE. IN MT. HOLLY 
TO STATE ROAD ROUTE 38 EAST; THEN, ALONG STATE ROAD 
ROUTE 38 EAST UNTIL IT CROSSES OVER STATE ROAD 
ROUTE 206 AND BECOMES COUNTY ROAD ROUTE 530; THEN, 
ALONG COUNTY ROAD ROUTE 530 to Magnolia Road, 
includes Pemberton Borough; then, south on Magnolia 
Road in Pemberton Township to Magnolia New Lisbon 
Road (Route 545); then, south on Mt. Holly Misery 
Road to State Road Route 70 East; then, along State 
Road Route 70 East to the Ocean County line)........$ 46.23                  29.23
----------------------------------------------------------------

 PLUM0322-008 05/01/2025
                                                     Rates                  Fringes
PLUMBER: EXCLUDING HVAC PIPE INSTALLATION 
(BURLINGTON COUNTY (SOUTH OF A LINE DRAWN FROM THE 
TOWN OF BURLINGTON CITY, DOES NOT INCLUDE 
BURLINGTON CITY; THEN, ALONG COUNTY ROAD ROUTE 541 
EAST, ALSO KNOWN AS HIGH ST., UNTIL IT REACHES THE 
CITY OF MT. HOLLY, DOES NOT INCLUDE THE CITY OF MT. 
HOLLY; THEN, ALONG MADISON AVE. IN MT. HOLLY TO 
STATE ROAD ROUTE 38 EAST; THEN, ALONG STATE ROAD 
ROUTE 38 EAST UNTIL IT CROSSES OVER STATE ROAD 
ROUTE 206 AND BECOMES COUNTY ROAD ROUTE 530, DOES 
NOT INCLUDE Pemberton Borough; then, south on 
Magnolia Road in Pemberton Township to Magnolia New 
Lisbon Road (Route 545); then, south on Mt. Holly 
Misery Rd. to State Road Route 70 East; then, along 
State Road Route 70 East to the Ocean County line)..$ 56.30                  50.76
PIPEFITTER: INCLUDING HVAC PIPE INSTALLATION 
(BURLINGTON COUNTY (SOUTH OF A LINE DRAWN FROM THE 
TOWN OF BURLINGTON CITY, DOES NOT INCLUDE 
BURLINGTON CITY; THEN, ALONG COUNTY ROAD ROUTE 541 
EAST, ALSO KNOWN AS HIGH ST., UNTIL IT REACHES THE 
CITY OF MT. HOLLY, DOES NOT INCLUDE THE CITY OF MT. 
HOLLY; THEN, ALONG MADISON AVE. IN MT. HOLLY TO 
STATE ROAD ROUTE 38 EAST; THEN, ALONG STATE ROAD 
ROUTE 38 EAST UNTIL IT CROSSES OVER STATE ROAD 
ROUTE 206 AND BECOMES COUNTY ROAD ROUTE 530, DOES 
NOT INCLUDE Pemberton Borough; then, south on 
Magnolia Road in Pemberton Township to Magnolia New 
Lisbon Road (Route 545); then, south on Mt. Holly 
Misery Rd. to State Road Route 70 East; then, along 
State Road Route 70 East to the Ocean County line)..$ 56.30                  50.76
----------------------------------------------------------------

 ROOF0030-027 05/01/2025
                                                     Rates                  Fringes
ROOFER: 
Mopper, and operator of felt-laying machine: $.50 
per hour 
Work applying roofing material, on any new 
construction job, on those days on which a 
felt-laying machine or slag dispensing machine is 
used: $.50 per hour 
PAID HOLIDAY: The last working day before 
Christmas, to be paid at the rate of four hours 
pay.................................................$ 35.95                  21.85
ROOFER: SLATE AND 
Mopper, and operator of felt-laying machine: $.50 
per hour 
Work applying roofing material, on any new 
construction job, on those days on which a 
felt-laying machine or slag dispensing machine is 
used: $.50 per hour 
PAID HOLIDAY: The last working day before 
Christmas, to be paid at the rate of four hours 
pay.................................................$ 38.95                  21.85
ROOFER: ALL OTHER 
Mopper, and operator of felt-laying machine: $.50 
per hour 
Work applying roofing material, on any new 
construction job, on those days on which a 
felt-laying machine or slag dispensing machine is 
used: $.50 per hour 
PAID HOLIDAY: The last working day before 
Christmas, to be paid at the rate of four hours 
pay.................................................$ 46.03                  34.27
----------------------------------------------------------------

 SFNJ0669-006 04/01/2025
                                                     Rates                  Fringes
SPRINKLER FITTER (FIRE SPRINKLERS)..................$ 59.19                  36.51
----------------------------------------------------------------

 SFNJ0692-002 05/01/2021
                                                     Rates                  Fringes
SPRINKLER FITTER (FIRE SPRINKLERS) (WITHIN 15 MILES 
BEYOND THE CITY LIMITS OF PHILADELPHIA).............$ 60.83                  30.34
----------------------------------------------------------------

 SHEE0027-009 06/01/2024
                                                     Rates                  Fringes
SHEET METAL WORKER (INCLUDING HVAC DUCT 
INSTALLATION).......................................$ 59.08                  47.06
----------------------------------------------------------------

 SUNJ2004-003 01/02/2009
                                                     Rates                  Fringes
PLASTERER...........................................$ 42.33                  0.00
LABORER:  COMMON OR GENERAL.........................$ 19.27                  12.42
----------------------------------------------------------------

 TEAM0469-003 05/01/2025
                                                     Rates                  Fringes
TRUCK DRIVER: DUMP TRUCK  (BURLINGTON COUNTY (EAST 
OF A LINE DRAWN FROM THE NEW JERSEY TURNPIKE TO THE 
DELAWARE 
HAZARDOUS WASTE REMOVAL WORK: Work on a state or 
federally designated hazardous waste site, where 
the worker is in direct contact with hazardous 
material, and when personal protective equipment is 
required for respiratory, skin and eye protection: 
$3.00 per hour 
Work on a state or federally designated hazardous 
waste site, in a zone requiring Level A personal 
protection for any workers other than the truck 
driver: $3.00 per hour additional. 
Work on a state or federally designated hazardous 
waste site where the worker is not working in a 
zone requiring Level A, B or C personal protection: 
$1.00 per hour 
PAID HOLIDAYS: New Year's Day, President's Day, 
Decoration Day, Independence Day, Labor Day, 
Presidential Election Day, Veteran's Day, 
Thanksgiving Day and Christmas 
VACATION PAY CREDIT: Workers working or receiving 
pay for 80 days within a year receive one week paid 
vacation (48 hours); 125 days receive two weeks 
paid vacation (96 hours); 145 days receive 15 days 
paid vacation (120 hours); 15 years seniority and 
145 days receive 4 weeks paid vacation (160 hours)..$ 48.63                  42.66
TRUCK DRIVER: OFF THE ROAD TRUCK  (BURLINGTON 
COUNTY (EAST OF A LINE DRAWN FROM THE NEW JERSEY 
TURNPIKE TO THE DELAWARE 
HAZARDOUS WASTE REMOVAL WORK: Work on a state or 
federally designated hazardous waste site, where 
the worker is in direct contact with hazardous 
material, and when personal protective equipment is 
required for respiratory, skin and eye protection: 
$3.00 per hour 
Work on a state or federally designated hazardous 
waste site, in a zone requiring Level A personal 
protection for any workers other than the truck 
driver: $3.00 per hour additional. 
Work on a state or federally designated hazardous 
waste site where the worker is not working in a 
zone requiring Level A, B or C personal protection: 
$1.00 per hour 
PAID HOLIDAYS: New Year's Day, President's Day, 
Decoration Day, Independence Day, Labor Day, 
Presidential Election Day, Veteran's Day, 
Thanksgiving Day and Christmas 
VACATION PAY CREDIT: Workers working or receiving 
pay for 80 days within a year receive one week paid 
vacation (48 hours); 125 days receive two weeks 
paid vacation (96 hours); 145 days receive 15 days 
paid vacation (120 hours); 15 years seniority and 
145 days receive 4 weeks paid vacation (160 hours)..$ 48.78                  42.66
----------------------------------------------------------------

 TEAM0676-002 05/01/2025
                                                     Rates                  Fringes
TRUCK DRIVER: OFF THE ROAD TRUCK (BURLINGTON COUNTY 
(WEST OF THE LINE DRAWN FROM THE NEW JERSEY 
TURNPIKE TO THE DELAWARE RIVER)) 
HAZARDOUS WASTE REMOVAL WORK:  Work on a state or 
federally designated hazardous waste site, where 
the worker is in direct contact with hazardous 
materials, and when personal protective equipment 
is required for respiratory, skin and eye 
protection: $3.00 per hour additional. Work on a 
state or federally designated hazardous waste site, 
where personal protection A, B, C or D is NOT 
required: $1.00 per hour 
SHIFT WORK: An owner mandated irregular shift 
staring any time other than between 6:00 am and 
8:00 am to receive $1.00 per hour, for each hour 
worked, in addition to the regular rate of 
PAID HOLIDAYS: New Year's Day, President's Day, 
Memorial Day, Independence Day, Labor Day, 
Presidential Election Day, Veteran's Day (or the 
day after Thanksgiving, at the option of the 
contractor), Thanksgiving Day, the afternoon of the 
day before Christmas (Dec. 24) provided that the 
worker works in the morning, and Christmas Day, 
provided that the worker works or is available for 
work on at least two days in the week in which the 
holiday 
BEREAVEMENT PAY: In case of a death in the worker's 
immediate famiy (mother, father, wife, husband, 
children, brother, sister, current mother-in-law, 
current father-in-law, grandparents), the worker 
shall be allowed leave not to exceed three (3) days 
straight-time pay, provided that he or she shall 
receive no pay unless the day of death and the 
burial day falls on a regular work day, and not on 
days off, holidays, vacation, Saturdays or Sundays..$ 44.65                  34.11
TRUCK DRIVER: DUMP TRUCK DRIVERS  (BURLINGTON 
COUNTY (WEST OF THE LINE DRAWN FROM THE NEW JERSEY 
TURNPIKE TO THE DELAWARE RIVER)) 
HAZARDOUS WASTE REMOVAL WORK:  Work on a state or 
federally designated hazardous waste site, where 
the worker is in direct contact with hazardous 
materials, and when personal protective equipment 
is required for respiratory, skin and eye 
protection: $3.00 per hour additional. Work on a 
state or federally designated hazardous waste site, 
where personal protection A, B, C or D is NOT 
required: $1.00 per hour 
SHIFT WORK: An owner mandated irregular shift 
staring any time other than between 6:00 am and 
8:00 am to receive $1.00 per hour, for each hour 
worked, in addition to the regular rate of 
PAID HOLIDAYS: New Year's Day, President's Day, 
Memorial Day, Independence Day, Labor Day, 
Presidential Election Day, Veteran's Day (or the 
day after Thanksgiving, at the option of the 
contractor), Thanksgiving Day, the afternoon of the 
day before Christmas (Dec. 24) provided that the 
worker works in the morning, and Christmas Day, 
provided that the worker works or is available for 
work on at least two days in the week in which the 
holiday 
BEREAVEMENT PAY: In case of a death in the worker's 
immediate famiy (mother, father, wife, husband, 
children, brother, sister, current mother-in-law, 
current father-in-law, grandparents), the worker 
shall be allowed leave not to exceed three (3) days 
straight-time pay, provided that he or she shall 
receive no pay unless the day of death and the 
burial day falls on a regular work day, and not on 
days off, holidays, vacation, Saturdays or Sundays..$ 44.30                  34.11
----------------------------------------------------------------

----------------------------------------------------------------------------------------------------
WELDERS - Receive rate prescribed for craft performing
operation to which welding is incidental.
================================================================
Note: Executive Order (EO) 13706, Establishing Paid Sick Leave
for Federal Contractors applies to all contracts subject to the
Davis-Bacon Act for which the contract is awarded (and any
solicitation was issued) on or after January 1, 2017.  If this
contract is covered by the EO, the contractor must provide
employees with 1 hour of paid sick leave for every 30 hours
they work, up to 56 hours of paid sick leave each year.
Employees must be permitted to use paid sick leave for their
own illness, injury or other health-related needs, including
preventive care; to assist a family member (or person who is
like family to the employee) who is ill, injured, or has other
health-related needs, including preventive care; or for reasons
resulting from, or to assist a family member (or person who is
like family to the employee) who is a victim of, domestic
violence, sexual assault, or stalking.  Additional information
on contractor requirements and worker protections under the EO
is available at https://www.dol.gov/agencies/whd/government-contracts.

Note: Executive Order 13658 generally applies to contracts subject 
to the Davis-Bacon Act that were awarded on or between January 1, 
2015 and January 29, 2022, and that have not been renewed or 
extended on or after January 30, 2022. Executive Order 13658 does 
not apply to contracts subject only to the Davis-Bacon Related Acts 
regardless of when they were awarded. If a contract is subject to 
Executive Order 13658, the contractor must pay all covered workers 
at least $13.65 per hour (or the applicable wage rate listed on this 
wage determination, if it is higher) for all hours spent performing on 
the contract from May 11, 2026, through December 31, 2026.  The 
applicable Executive Order minimum wage rate will be adjusted annually.
Additional information on contractor requirements and worker 
protections under Executive Order 13658 is available at 
www.dol.gov/whd/govcontracts.

Unlisted classifications needed for work not included within
the scope of the classifications listed may be added after
award only as provided in the labor standards contract clauses
(29CFR 5.5 (a) (1) (iii)).
-----------------------------------------------------------------------------------------------------
The body of each wage determination lists the classifications
and wage rates that have been found to be prevailing for the
type(s) of construction and geographic area covered by the wage
determination. The classifications are listed in alphabetical
order under rate identifiers indicating whether the particular
rate is a union rate (current union negotiated rate), a survey
rate, a weighted union average rate, a state adopted rate, or a
supplemental classification rate.

Union Rate Identifiers

A four-letter identifier beginning with characters other than
�SU�, �UAVG�, �SA�, or �SC� denotes that a union rate was
prevailing for that classification in the survey. Example:
PLUM0198-005 07/01/2024. PLUM is an identifier of the union
whose collectively bargained rate prevailed in the survey for
this classification, which in this example would be Plumbers.
0198 indicates the local union number or district council
number where applicable, i.e., Plumbers Local 0198. The next
number, 005 in the example, is an internal number used in
processing the wage determination. The date, 07/01/2024 in the
example, is the effective date of the most current negotiated
rate.

Union prevailing wage rates are updated to reflect all changes
over time that are reported to WHD in the rates
in the collective bargaining agreement (CBA) governing the
classification.

Union Average Rate Identifiers

The UAVG identifier indicates that no single rate prevailed for
those classifications, but that 100% of the data reported for
the classifications reflected union rates. EXAMPLE:
UAVG-OH-0010 01/01/2024. UAVG indicates that the rate is a
weighted union average rate. OH indicates the State of Ohio.
The next number, 0010 in the example, is an internal number
used in producing the wage determination. The date, 01/01/2024
in the example, indicates the date the wage determination was
updated to reflect the most current union average rate.

A UAVG rate will be updated once a year, usually in January, to
reflect a weighted average of the current rates in the
collective bargaining agreements on which the rate is based.

Survey Rate Identifiers

The �SU� identifier indicates that either a single non-union
rate prevailed (as defined in 29 CFR 1.2) for this
classification in the survey or that the rate was derived by
computing a weighted average rate based on all the rates
reported in the survey for that classification. As a weighted
average rate includes all rates reported in the survey, it may
include both union and non-union rates. Example: SUFL2022-007
6/27/2024. SU indicates the rate is a single non-union
prevailing rate or a weighted average of survey data for that
classification. FL indicates the State of Florida. 2022 is the
year of the survey on which these classifications and rates are
based. The next number, 007 in the example, is an internal
number used in producing the wage determination. The date,
6/27/2024 in the example, indicates the survey completion date
for the classifications and rates under that identifier.

�SU� wage rates typically remain in effect until a new survey
is conducted. However, the Wage and Hour Division (WHD) has the
discretion to update such rates under 29 CFR 1.6(c)(1).

State Adopted Rate Identifiers

The �SA� identifier indicates that the classifications and
prevailing wage rates set by a state (or local) government were
adopted under 29 C.F.R 1.3(g)-(h).  Example: SAME2023-007
01/03/2024. SA reflects that the rates are state adopted. ME
refers to the State of Maine. 2023 is the year during which the
state completed the survey on which the listed classifications
and rates are based. The next number, 007 in the example, is an
internal number used in producing the wage determination.
The date, 01/03/2024 in the example, reflects the date on which
the classifications and rates under the �SA� identifier took
effect under state law in the state from which the rates were
adopted.
-----------------------------------------------------------------------------------------------------
WAGE DETERMINATION APPEALS PROCESS
1) Has there been an initial decision in the matter? This can
be:
           a) a survey underlying a wage determination
           b) an existing published wage determination
           c) an initial WHD letter setting forth a position on
                a wage determination matter
           d) an initial conformance (additional classification
                and rate) determination
On survey related matters, initial contact, including requests
for summaries of surveys, should be directed to the WHD Branch
of Wage Surveys. Requests can be submitted via email to
davisbaconinfo@dol.gov or by mail to:
            Branch of Wage Surveys
            Wage and Hour Division
            U.S. Department of Labor
            200 Constitution Avenue, N.W.
            Washington, DC 20210
Regarding any other wage determination matter such as
conformance decisions, requests for initial decisions should be
directed to the WHD Branch of Construction Wage Determinations.
Requests can be submitted via email to BCWD-Office@dol.gov or
by mail to:
            Branch of Construction Wage Determinations
            Wage and Hour Division
            U.S. Department of Labor
            200 Constitution Avenue, N.W.
            Washington, DC 20210
2) If an initial decision has been issued, then any interested
party (those affected by the action) that disagrees with the
decision can request review and reconsideration from the Wage
and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7).
Requests for review and reconsideration can be submitted via
email to dba.reconsideration@dol.gov or by mail to:
            Wage and Hour Administrator
            U.S. Department of Labor
            200 Constitution Avenue, N.W.
            Washington, DC 20210
The request should be accompanied by a full statement of the
interested party's position and any information (wage payment
data, project description, area practice material, etc.) that
the requestor considers relevant to the issue.

3) If the decision of the Administrator is not favorable, an
interested party may appeal directly to the Administrative
Review Board (formerly the Wage Appeals Board).  Write to:
            Administrative Review Board
            U.S. Department of Labor
            200 Constitution Avenue, N.W.
            Washington, DC 20210.
================================================================
          END OF GENERAL DECISION
"