"General Decision Number: NY20260045 05/18/2026
State: New York
Construction Types: Building, Heavy and Highway
Counties: New York Counties of
Tioga
Building Construction Projects
Heavy Construction Projects
Highway Construction Projects
Modification Number Publication Date
1 01/30/2026
2 05/18/2026
ASBE0030-001 05/01/2023
Rates Fringes
HAZARDOUS MATERIAL HANDLER (SCOPE OF WORK: DUTIES
LIMITED TO PREPARATION, WETTING, STRIPPING,
REMOVAL, SCRAPPING, VACUUMING, BAGGING, AND
DISPOSING OF ALL INSULATION MATERIALS, WHETHER THEY
CONTAIN ASBESTOS OR NOT FROM MECHANICAL SYSTEM).....$ 38.50 25.04
ASBESTOS/INSULATOR WORKER (INCLUDES APPLICATION OF
ALL MATERIALS, PROTECTIVE COVERINGS, COATINGS AND
FINISHINGS TO ALL TYPES OF MECHANICAL SYSTEMS.
ALSO THE APPLICATION OF FIRESTOPPING MATERIAL TO
OPENINGS AND PENETRATIONS IN WALLS, FLOORS,
CEILINGS, CURTAIN WALLS AND ALL LEAD ABATEMENT.)....$ 43.25 27.29
----------------------------------------------------------------
ASBE0030-001 05/01/2025
Rates Fringes
HAZARDOUS MATERIAL HANDLER (SCOPE OF WORK: DUTIES
LIMITED TO PREPARATION, WETTING, STRIPPING,
REMOVAL, SCRAPPING, VACUUMING, BAGGING, AND
DISPOSING OF ALL INSULATION MATERIALS, WHETHER THEY
CONTAIN ASBESTOS OR NOT FROM MECHANICAL SYSTEM).....$ 38.50 25.04
ASBESTOS/INSULATOR WORKER (INCLUDES APPLICATION OF
ALL MATERIALS, PROTECTIVE COVERINGS, COATINGS AND
FINISHINGS TO ALL TYPES OF MECHANICAL SYSTEMS.
ALSO THE APPLICATION OF FIRESTOPPING MATERIAL TO
OPENINGS AND PENETRATIONS IN WALLS, FLOORS,
CEILINGS, CURTAIN WALLS AND ALL LEAD ABATEMENT.)....$ 43.25 27.29
----------------------------------------------------------------
BOIL0197-001 01/01/2025
Rates Fringes
BOILERMAKER.........................................$ 43.34 27.66
----------------------------------------------------------------
BRNY0003-014 07/01/2025
Rates Fringes
MARBLE MASONS, TILE LAYER, TERRAZZO WORKER:
BUILDING CONSTRUCTION (CORNING CHAPTER TIOGA
COUNTY (TOWNSHIPS OF BARTON, SPENCER AND PART OF
NICHOLS AND TIOGA)).................................$ 34.34 28.46
CEMENT MASONS: HEAVY & HIGHWAY CONSTRUCTION
(CORNING CHAPTER TIOGA COUNTY (TOWNSHIPS OF
BARTON, SPENCER AND PART OF NICHOLS AND TIOGA)).....$ 38.63 25.05
BRICKLAYERS, CEMENT MASONS, PLASTERERS, STONE
MASONS, TILE SETTERS, TERRAZZO WORKERS, MARBLE
MASONS, POINTERS, CAULKERS AND CLEANERS: BUILDING
CONSTRUCTION (CORNING CHAPTER TIOGA COUNTY
(TOWNSHIPS OF BARTON, SPENCER AND PART OF NICHOLS
AND TIOGA)).........................................$ 34.34 28.46
----------------------------------------------------------------
BRNY0003-015 07/01/2025
Rates Fringes
CEMENT MASON/CONCRETE FINISHER: HEAVY & HIGHWAY
CONSTRUCTION (BINGHAMTON CHAPTER TIOGA COUNTY
(TOWNSHIPS OF BERKSHIRE, NEWARK VALLEY, OWEGO,
RICHFORD, PARTS OF CANDOR, NICHOLS AND TIOGA))......$ 38.63 25.05
----------------------------------------------------------------
BRNY0008-003 07/01/2025
Rates Fringes
CEMENT MASON/CONCRETE FINISHER (HEAVY & HIGHWAY
CONSTRUCTION).......................................$ 38.63 25.05
BRICKLAYER (BUILDING CONSTRUCTION MARBLE, TILE AND
TERRAZZO FINISHERS).................................$ 34.44 20.38
BRICKLAYER (BUILDING CONSTRUCTION BRICKLAYERS,
CEMENT MASONS, PLASTERERS, STONE MASONS, TILE
SETTERS, TERRAZZO WORKERS, MARBLE MASONS, POINTERS,
CAULKERS, TUCKERS)..................................$ 34.34 28.46
----------------------------------------------------------------
CARP0277-011 07/01/2025
Rates Fringes
MILLWRIGHT BUILDING CONSTRUCTION FOOTNOTE: A.
PAID HOLIDAYS: MEMORIAL DAY, JULY THE 4TH, LABOR
DAY, THANKGIVING DAY (PROVIDED THE EMPLOYEE IS
EMPLOYED (1) DAY BEFORE AND (1) DAY AFTER THE
HOLIDAY.............................................$ 31.69 21.92
CARPENTERS: (HEAVY & HIGHWAY CONSTRUCTION)
FOOTNOTE: A. PAID HOLIDAYS: MEMORIAL DAY, JULY
THE 4TH, LABOR DAY, THANKGIVING DAY (PROVIDED THE
EMPLOYEE IS EMPLOYED (1) DAY BEFORE AND (1) DAY
AFTER THE HOLIDAY...................................$ 39.52 27.16
CARPENTER BUILDING CONSTRUCTION FOOTNOTE: A.
PAID HOLIDAYS: MEMORIAL DAY, JULY THE 4TH, LABOR
DAY, THANKGIVING DAY (PROVIDED THE EMPLOYEE IS
EMPLOYED (1) DAY BEFORE AND (1) DAY AFTER THE
HOLIDAY.............................................$ 31.69 21.92
----------------------------------------------------------------
ELEC0139-008 06/01/2025
Rates Fringes
ELECTRICIAN (BARTON AND NICHOLS TOWNSHIPS)..........$ 43.40 31.72
----------------------------------------------------------------
ELEC0241-001 06/01/2025
Rates Fringes
ELECTRICIAN (CANDOR AND SPENCER TOWNSHIPS)..........$ 44.50 31.89
----------------------------------------------------------------
ELEC0325-004 06/01/2025
Rates Fringes
ELECTRICIAN (BERKSHIRE, NEWARK VALLEY, OWEGO,
RICHFORD AND TIOGA TOWNSHIPS).......................$ 42.68 33.06
CABLE SPLICER (BERKSHIRE, NEWARK VALLEY, OWEGO,
RICHFORD AND TIOGA TOWNSHIPS).......................$ 50.43 33.29
----------------------------------------------------------------
ELEC1249-003 05/05/2025
Rates Fringes
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC
SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE
NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC
MONITORING SYSTEMS AND ROAD WEATHER INFORMATION
SYSTEMS MECHANIC FOOTNOTE: A. NEW YEAR'S DAY,
MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY,
THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S
DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR
THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY
FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED
THE EMPLOYEE WORKS THE DAY BEFORE OR THE DAY AFTER
THE HOLIDAY.........................................$ 42.29 30.66
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC
SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE
NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC
MONITORING SYSTEMS AND ROAD WEATHER INFORMATION
SYSTEMS LINEMAN & TECHNICIAN FOOTNOTE: A. NEW
YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR
DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS
PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY,
ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES
AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF
NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY
BEFORE OR THE DAY AFTER THE HOLIDAY.................$ 52.86 35.60
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC
SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE
NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC
MONITORING SYSTEMS AND ROAD WEATHER INFORMATION
SYSTEMS GROUNDMAN TRUCK DRIVER (TRACTOR TRAILER
UNIT) FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL
DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY,
CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY,
DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF
THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR
OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE
WORKS THE DAY BEFORE OR THE DAY AFTER THE HOLIDAY...$ 47.57 31.03
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC
SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE
NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC
MONITORING SYSTEMS AND ROAD WEATHER INFORMATION
SYSTEMS GROUNDMAN (TRUCK DRIVER) FOOTNOTE: A.
NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY,
LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS
PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY,
ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES
AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF
NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY
BEFORE OR THE DAY AFTER THE HOLIDAY.................$ 42.29 30.66
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC
SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE
NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC
MONITORING SYSTEMS AND ROAD WEATHER INFORMATION
SYSTEMS FLAGMAN FOOTNOTE: A. NEW YEAR'S DAY,
MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY,
THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S
DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR
THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY
FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED
THE EMPLOYEE WORKS THE DAY BEFORE OR THE DAY AFTER
THE HOLIDAY.........................................$ 31.72 29.87
----------------------------------------------------------------
ELEC1249-004 05/05/2025
Rates Fringes
ELECTRICIAN, LINE CONSTRUCTION: MECHANIC (Switching
structures; railroad catenary installation and
maintenance, third rail type underground fluid or
gas filled transmission conduit and cable
installations (including any and all fiber optic
ground product by any other name manufactured for
the dual purpose of ground fault protection and
fiber optic capabilities), pipetype cable
installation and maintenance jobs or projects, and
maintenance bonding of rails; Pipetype cable
installation).......................................$ 49.25 31.15
ELECTRICIAN, LINE CONSTRUCTION: MECHANIC
(Substation:).......................................$ 49.25 31.15
ELECTRICIAN, LINE CONSTRUCTION: MECHANIC (Overhead
and underground distribution and maintenance work
and all overhead and underground transmission line
work including any and all fiber optic ground wire,
fiber optic shield wire or any other like product
by any other name manufactured for the dual purpose
of ground fault protection and fiber optic
capabilities :).....................................$ 49.25 31.15
ELECTRICIAN, LINE CONSTRUCTION: LINEMAN &
TECHNICIAN (Switching structures; railroad catenary
installation and maintenance, third rail type
underground fluid or gas filled transmission
conduit and cable installations (including any and
all fiber optic ground product by any other name
manufactured for the dual purpose of ground fault
protection and fiber optic capabilities), pipetype
cable installation and maintenance jobs or
projects, and maintenance bonding of rails;
Pipetype cable ins..................................$ 61.56 36.21
ELECTRICIAN, LINE CONSTRUCTION: LINEMAN &
TECHNICIAN (Substation:)............................$ 61.56 36.21
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK
DRIVER (TRACTOR TRAILER UNIT) (Substation:).........$ 49.25 31.15
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK
DRIVER (TRACTOR TRAILER UNIT) (Overhead and
underground distribution and maintenance work and
all overhead and underground transmission line work
including any and all fiber optic ground wire,
fiber optic shield wire or any other like product
by any other name manufactured for the dual purpose
of ground fault protection and fiber optic
capabilities :).....................................$ 49.25 31.15
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK
DRIVER (Switching structures; railroad catenary
installation and maintenance, third rail type
underground fluid or gas filled transmission
conduit and cable installations (including any and
all fiber optic ground product by any other name
manufactured for the dual purpose of ground fault
protection and fiber optic capabilities), pipetype
cable installation and maintenance jobs or
projects, and maintenance bonding of rails;
Pipetype cable installat............................$ 49.25 31.15
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK
DRIVER (Overhead and underground distribution and
maintenance work and all overhead and underground
transmission line work including any and all fiber
optic ground wire, fiber optic shield wire or any
other like product by any other name manufactured
for the dual purpose of ground fault protection and
fiber optic capabilities :).........................$ 49.25 31.15
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING
MACHINE OPERATOR (Switching structures; railroad
catenary installation and maintenance, third rail
type underground fluid or gas filled transmission
conduit and cable installations (including any and
all fiber optic ground product by any other name
manufactured for the dual purpose of ground fault
protection and fiber optic capabilities), pipetype
cable installation and maintenance jobs or
projects, and maintenance bonding of rails;
Pipetype cab........................................$ 55.40 31.78
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING
MACHINE OPERATOR (Substation:)......................$ 55.40 31.78
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING
MACHINE OPERATOR (Overhead and underground
distribution and maintenance work and all overhead
and underground transmission line work including
any and all fiber optic ground wire, fiber optic
shield wire or any other like product by any other
name manufactured for the dual purpose of ground
fault protection and fiber optic capabilities :)....$ 55.40 31.78
ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN (Switching
structures; railroad catenary installation and
maintenance, third rail type underground fluid or
gas filled transmission conduit and cable
installations (including any and all fiber optic
ground product by any other name manufactured for
the dual purpose of ground fault protection and
fiber optic capabilities), pipetype cable
installation and maintenance jobs or projects, and
maintenance bonding of rails; Pipetype cable
installation).......................................$ 35.34 30.12
ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN
(Substation:).......................................$ 35.34 30.12
ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN (Overhead
and underground distribution and maintenance work
and all overhead and underground transmission line
work including any and all fiber optic ground wire,
fiber optic shield wire or any other like product
by any other name manufactured for the dual purpose
of ground fault protection and fiber optic
capabilities :).....................................$ 35.34 30.12
ELECTRICIAN, LINE CONSTRUCTION: CABLE SPLICER
(Switching structures; railroad catenary
installation and maintenance, third rail type
underground fluid or gas filled transmission
conduit and cable installations (including any and
all fiber optic ground product by any other name
manufactured for the dual purpose of ground fault
protection and fiber optic capabilities), pipetype
cable installation and maintenance jobs or
projects, and maintenance bonding of rails;
Pipetype cable installation)........................$ 64.59 42.92
ELECTRICIAN, LINE CONSTRUCTION: CABLE SPLICER
(Substation:).......................................$ 63.14 33.82
ELECTRICIAN LINE CONSTRUCTION SWITCHING STRUCTURES;
RAILROAD CATENARY INSTALLATION AND MAINTENANCE,
THIRD RAIL TYPE UNDERGROUND FLUID OR GAS FILLED
TRANSMISSION CONDUIT AND CABLE INSTALLATIONS
(INCLUDING ANY AND ALL FIBER OPTIC GROUND PRODUCT
BY ANY OTHER NAME MANUFACTURED FOR THE DUAL PURPOSE
OF GROUND FAULT PROTECTION AND FIBER OPTIC
CAPABILITIES), PIPETYPE CABLE INSTALLATION AND
MAINTENANCE JOBS OR PROJECTS, AND MAINTENANCE
BONDING OF RAILS; PIPETYPE CABLE INSTALLATION
GROUNDMAN TRUCK DRIVER (TRACTOR-TRAILER UNIT)
FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY,
PRESIDENTS' DAY, MEMORIAL DAY, GOOD FRIDAY,
INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY,
CHRISTMAS DAY, AND ELECTION DAY FOR THE PRESIDENT
OF THE UNITED STATES AND ELECTION DAY FOR THE
GOVERNOR OF NEW YORK STATE, PROVIDED THE EMPLOYEE
WORKS TWO DAYS BEFORE OR TWO DAYS AFTER THE
HOLIDAY.............................................$ 49.25 31.15
ELECTRICIAN LINE CONSTRUCTION SUBSTATION: GROUND
MAN TRUCK DRIVER FOOTNOTE: A. PAID HOLIDAYS:
NEW YEAR'S DAY, PRESIDENTS' DAY, MEMORIAL DAY, GOOD
FRIDAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING
DAY, CHRISTMAS DAY, AND ELECTION DAY FOR THE
PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR
THE GOVERNOR OF NEW YORK STATE, PROVIDED THE
EMPLOYEE WORKS TWO DAYS BEFORE OR TWO DAYS AFTER
THE HOLIDAY.........................................$ 49.25 31.15
ELECTRICIAN LINE CONSTRUCTION OVERHEAD AND
UNDERGROUND DISTRIBUTION AND MAINTENANCE WORK AND
ALL OVERHEAD AND UNDERGROUND TRANSMISSION LINE WORK
INCLUDING ANY AND ALL FIBER OPTIC GROUND WIRE,
FIBER OPTIC SHIELD WIRE OR ANY OTHER LIKE PRODUCT
BY ANY OTHER NAME MANUFACTURED FOR THE DUAL PURPOSE
OF GROUND FAULT PROTECTION AND FIBER OPTIC
CAPABILITIES : LINEMAN AND TECHNICIAN FOOTNOTE:
A. PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENTS' DAY,
MEMORIAL DAY, GOOD FRIDAY, INDEPENDENCE DAY, LABOR
DAY, THANKSGIVING DAY, CHRISTMAS DAY, AND ELECTION
DAY FOR THE PRESIDENT OF THE UNITED STATES AND
ELECTION DAY FOR THE GOVERNOR OF NEW YORK STATE,
PROVIDED THE EMPLOYEE WORKS TWO DAYS BEFORE OR TWO
DAYS AFTER THE HOLIDAY..............................$ 61.56 36.21
----------------------------------------------------------------
ELEC1249-008 01/01/2025
Rates Fringes
ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV
FIBEROPTICS CABLE AND EQUIPMENT INSTALLER
REPAIRMAN-TELEDATA LINEMAN/TECHNICIAN-EQUIPMENT
OPERATOR A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD
FRIDAY, DECORATION DAY, INDEPENDENCE DAY, LABOR
DAY, VETERAN'S DAY, THANKSGIVING DAY, DAY AFTER
THANKSGIVING, CHRISTMAS DAY.........................$ 38.73 6.93
ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV
FIBEROPTICS CABLE AND EQUIPMENT GROUNDMAN A. NEW
YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY,
DECORATION DAY, INDEPENDENCE DAY, LABOR DAY,
VETERAN'S DAY, THANKSGIVING DAY, DAY AFTER
THANKSGIVING, CHRISTMAS DAY.........................$ 20.53 6.39
ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV
FIBEROPTICS CABLE AND EQUIPMENT CABLE SPLICER A.
NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY,
DECORATION DAY, INDEPENDENCE DAY, LABOR DAY,
VETERAN'S DAY, THANKSGIVING DAY, DAY AFTER
THANKSGIVING, CHRISTMAS DAY.........................$ 40.81 6.99
----------------------------------------------------------------
ELEV0062-002 01/01/2025
Rates Fringes
ELEVATOR MECHANIC FOOTNOTE: A.VACATION:
6%/UNDER 5 YEARS BASED ON REGULAR HOURLY RATE FOR
ALL HOURS WORKED. 8%/OVER 5 YEARS BASED ON REGULAR
HOURLY RATE FOR ALL HOURS WORKED. B. PAID
HOLIDAYS: NEW YEAR'S DAY; MEMORIAL DAY;
INDEPENDENCE DAY; LABOR DAY; VETERANS' DAY;
THANKSGIVING DAY; THE FRIDAY AFTER THANKSGIVING
DAY; AND CHRISTMAS DAY..............................$ 58.44 38.44
----------------------------------------------------------------
ENGI0158-007 07/01/2025
Rates Fringes
POWER EQUIPMENT OPERATORS: GROUP A(1) CRANE,
HYDRAULIC CRANES, TOWER CRANE, LOCOMOTIVE CRANE,
PILEDRIVER, CABLEWAY, DERRICKS, WHIRLIES, DRAGLINE,
BOOM TRUCKS OVER 5 TONS BUILDING HAZARDOUS
WORK- ANYTIME OPERATING ENGINEERS ARE INVOLVED WITH
LEVEL C OR ABOVE, $3.00 PER HOUR OVER REGULAR RATE.
FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY,
MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY,
THANKSGIVING DAY, CHRISTMAS DAY. ...........$ 51.71 32.80
POWER EQUIPMENT OPERATORS: BUILDING: GROUP C FORK
LIFT, HIGH LIFT, LULL, OILER, FIREMAN AND
HEAVY-DUTY GREASER, BOILERS AND STEAM GENERATORS,
PUMP, VIBRATOR, MOTOR MIXER, AIR COMPRESSOR, DUST
COLLECTOR, SELDING MACHINE, WELL POINT, MECHANICAL
HEATER, GENERATORS, TEMPORARY LIGHT PLANTS,
CONCRETE PUMPS, ELECTRIC SUBMERSIBLE PUMP 4"" AND
OVER, MURPHY TYPE DISEL GENERATOR, CONVEYOR,
ELEVATORS, CONCRETE MIXER AND BELTCRETE POWER PACK
(BELCRETE SYSTEM SEEDING AND MULCHING MACHINES
PUMPS. HAZARDOUS WORK- ANYTIME OPERATING ENGINEERS
ARE INVOLVED WITH LEVEL C OR ABOVE, $3.00 PER HOUR
OVER REGULAR RATE. FOOTNOTE: A. PAID HOLIDAYS:
NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY,
LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY..........$ 46.54 32.80
POWER EQUIPMENT OPERATORS: BUILDING: GROUP B
BACKHOES (RUBBER TIRED BACKHOE/LOADER COMBINATION),
BULLDOZER, PUSHCAT, TRACTOR, TRAXCAVATOR, SCRAPER,
LETOURNEAU GRADER, FORM FINE GRADER, ROAD ROLLER,
BLACKTOP ROLLER, BLACKTOP SPREADER, POWER BROOMS,
SWEEPERS, TRENCHING MACHINE, BARBER GREEN LOADER,
SIDE BOOMS, HYDRO HAMMER, CONCRETE SPREADER,
CONCRETE FINISHING MACHINE, ONE DRUM HOIST, POWER
HOISTING (SINGLE DRUM), HOIST TWO DRUM OR MORE,
THREE DRUM ENGINE, POWER HOISTING (TWO DRUM AND
OVER), TWO DRUM AND SWINGING ENGINE, THREE DRUM
SWINGING ENGINE, HOD HOIST, A-L FRAME WINCHES, CORE
AND WELL DRILLERS (ONE DRUM), POST HOLE DIGGER,
MODEL CHB VIBROTAMP OR SIMILAR MACHINE, BATCH BIN
AND PLANT OPERATOR, DINKEY LOCOMOTIVE, SKID STEER
LOADER, TRACK EXCAVATOR 5/8 CU. YD. OR SMALLER.
HAZARDOUS WORK- ANYTIME OPERATING ENGINEERS ARE
INVOLVED WITH LEVEL C OR ABOVE, $3.00 PER HOUR OVER
REGULAR RATE. FOOTNOTE: A. PAID HOLIDAYS: NEW
YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR
DAY, THANKSGIVING DAY, CHRISTMAS DAY................$ 48.85 32.80
POWER EQUIPMENT OPERATORS: BUILDING: GROUP A
SHOVEL, ALL EXCAVATORS (INCLUDING RUBBER TIRE, FULL
SWING), GRADALLS, POWER ROAD GRADER ALL CMI
EQUIPMENT, FRONT-END RUBBER TIRE LOADER,
TRACTOR-MOUNTED DRILL (QUARRY MASTER), MUCKING
MACHINE, CONCRETE CENTRAL MIX PLANT, CONCRETE PUMP,
BELCRETE SYSTEM, AUTOMATED ASPHALT CONCRETE PLANT,
TRACTOR ROAD PAVER, BOOM TRUCKS 5 TONS AND UNDER,
MAINTENANCE ENGINEER, SELF CONTAINED CRAWLER
DRILL-HYDRAULIC ROCK DRILL. HAZARDOUS WORK-
ANYTIME OPERATING ENGINEERS ARE INVOLVED WITH LEVEL
C OR ABOVE, $3.00 PER HOUR OVER REGULAR RATE.
FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY,
MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY,
THANKSGIVING DAY, CHRISTMAS DAY.....................$ 49.31 32.80
----------------------------------------------------------------
ENGI0158-030 07/01/2025
Rates Fringes
POWER EQUIPMENT OPERATORS: GROUP 3..................$ 53.82 33.55
POWER EQUIPMENT OPERATORS (HEAVY & HIGHWAY): GROUP
7 MASTER MECHANIC FOOTNOTE: A. PAID HOLIDAYS:
NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY,
LABOR DAY, THANKSGIVING DAY, AND CHRISTMAS DAY......$ 58.91 33.55
POWER EQUIPMENT OPERATORS (HEAVY & HIGHWAY): GROUP
6 CRANES 49 TONS AND BELOW FOOTNOTE: A. PAID
HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY,
INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, AND
CHRISTMAS DAY.......................................$ 60.30 33.55
POWER EQUIPMENT OPERATORS (HEAVY & HIGHWAY): GROUP
5 CRANES 50 TONS AND OVER FOOTNOTE: A. PAID
HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY,
INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, AND
CHRISTMAS DAY.......................................$ 61.80 33.55
POWER EQUIPMENT OPERATORS (HEAVY & HIGHWAY): GROUP
4 TOWER CRANES FOOTNOTE: A. PAID HOLIDAYS: NEW
YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR
DAY, THANKSGIVING DAY, AND CHRISTMAS DAY............$ 63.30 33.55
POWER EQUIPMENT OPERATORS (HEAVY & HIGHWAY): GROUP
2 ASPHALT PAVER, BACKHOE (TRACTOR MOUNTED, RUBBER
TIRED), BITUMINOUS RECYCLER MACHINE, BITUMINOUS
SPREADER AND MIXER, BLACKTOP PLANT (NONAUTOMATED),
BLAST OR ROTARY DRILL (TRUCK OR TRACTOR MOUNTED),
BORING MACHINE, CAGE HOIST, CENTRAL MIX PLANT
(NONAUTOMATED) AND ALL CONCRETE BATCHING PLANTS,
CHERRY PICKER (5 TONS CAPACITY AND UNDER), CONCRETE
PAVER (OVER 16S), CRAWLER DRILL, SELF-CONTAINED,
CRUSHER, DIESEL POWER UNIT, DRILL RIGS, TRACTOR
MOUNTED, FRONT END LOADER (UNDER 4 CU. YD.),
GREASEMAN/LUBRICATION ENGINEER, HIPRESSURE BOILER
(15 LBS. AND OVER), HOIST (ONE DRUM), HYDRO-AXE,
KOLMAN PLANT LOADER AND SIMILAR TYPE LOADERS,
L.C.M. WORK BOAT OPERATOR, LOCOMOTIVE MIXER (FOR
STABILIZED BASE SELFPROPELLED), MONORAIL MACHINE,
PLANT ENGINEER, PROFILER (105 H.P. AND UNDER),
GRINDER, POST HOLE DIGGER AND POST DRIVER, POWER
BROOM (TOWED), POWER HEATERMAN, POWER SWEEPER,
REVINIUS WIDENER, ROLLER (GRADE AND FILL),
SCARIFIER, RIDE-ON, SHELL WINDER, SKID STEER LOADER
(BOBCAT OR SIMILAR), SPAN-SAW, RIDE-ON, STEAM
CLEANER, PUG MILL, PUMP CRETE READY MIX CONCRETE
PLANT REFRIGERATION EQUIPMENT (FOR SOIL
STABILIZATION)ROAD WIDENER, ROLLER (ALL ABOVE
SUBGRADE), SEA MULE, SELF-CONTAINED RIDE-ON ROCK
DRILL, EXCLUDING AIR-TRACK TYPE DRILL, SKIDDER,
TRACTOR WITH DOZER AND/OR PUSHER, TRENCHER. TUGGER
HOIST, VERMEER SAW (RIDE ON, ANY SIZE OR TYPE),
WINCH, WINCH CAT FOOTNOTE: A. PAID HOLIDAYS:
NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY,
LABOR DAY, THANKSGIVING DAY, AND CHRISTMAS DAY......$ 56.39 33.55
POWER EQUIPMENT OPERATORS (HEAVY & HIGHWAY): GROUP
1 ASPHALT CURB MACHINE, SELF PROPELLED, SLIPFORM,
AUTOMATED CONCRETE SPREADER (CMI TYPE), AUTOMATIC
FINE GRADER, BACKHOE (EXCEPT TRACTOR MOUNTED,
RUBBER TIRED), BACKHOE EXCAVATOR FULL SWING (CAT
212 OR SIMILAR TYPE), BACK FILLING MACHINE, BELT
PLACER (CMI TYPE), BLACKTOP PLANT (AUTOMATED), BOOM
TRUCK , CABLEWAY, CAISSON AUGER, CENTRAL MIX
CONCRETE PLANT (AUTOMATED), CONCRETE CURB MACHINE,
SELF PROPELLED, SLIPFORM, CONCRETE PUMP, CRANE,
CHERRY PICKER, DERRICKS (STEEL ERECTION), DRAGLINE,
OVERHEAD CRANE (GANTRY OR STRADDLE TYPE), PILE
DRIVER, TRUCK CRANE, DIRECTIONAL DRILLING MACHINE,
DREDGE, DUAL DRUM PAVER, EXCAVATOR (ALL PURPOSE
HYDRAULICALLY OPERATED) (GRADALL OR SIMILAR), FRONT
END LOADER ( 4 CU. YD. AND OVER), HEAD TOWER
(SAUERMAN OR EQUAL), HOIST (TWO OR THREE DRUM),
HOLLAND LOADER, MAINTENANCE ENGINEER, MINE HOIST,
MUCKING MACHINE OR MOLE PAVEMENT BREAKER(SP)
WERTGEN; PB-4 AND SIMILAR TYPE, POWER GRADER,
PROFILER (OVER 105 H.P.) QUAD 9, QUARRY MASTER (OR
EQUIVALENT), SCRAPER, FIREMAN, FORM TAMPER, GROUT
PUMP, GUNITE MACHINE, HAMMERS (HYDRAULIC
SELF-PROPELLED), HYDRA-SPIKER, RIDE-ON, HYDRAULIC
PUMP (JACKING SYSTEM), HYDRO-BLASTER (WATER),
MULCHING MACHINE, OILER, PARAPET CONCRETE OR
PAVEMENT, SHOVEL, SIDE BOOM, SLIP FORM PAVER,
TRACTOR DRAWN, BELTTYPE LOADER, TRUCK OR TRAILER
MOUNTED LOG , CHIPPER (SELF FEEDER), TUG OPERATOR
(MANNED RENTED EQUIPMENT EXCLUDED), TUNNEL SHOVEL
FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY,
MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY,
THANKSGIVING DAY, AND CHRISTMAS DAY.................$ 57.30 33.55
----------------------------------------------------------------
IRON0060-006 07/01/2025
Rates Fringes
IRONWORKER (STRUCTURAL, ORNAMENTAL, REINFORCING,
PRE-CAST CONCRETE ERECTOR, MACHINERY MOVER &
RIGGER, FENCE ERECTOR, STONE DERRICKMAN, WELDER,
SHEETER, SHEETER BUCKER-UP).........................$ 37.16 30.68
----------------------------------------------------------------
LABO0785-011 07/01/2024
Rates Fringes
LABORERS: HEAVY AND HIGHWAY GROUP 5: HAZARDOUS
WASTE REMOVAL TOWNSHIPS OF RICHFORD, BERKSHIRE,
NEWARK VALLEY, OWEGO, TIOGA, BARTON AND NICHOLS
FOOTNOTE A. PAID HOLIDAYS: MEMORIAL DAY,
INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY,
CHRISTMAS DAY AND NEW YEAR'S DAY....................$ 38.76 25.60
LABORERS: HEAVY AND HIGHWAY GROUP 4: BLASTERS,
FORM SETTERS, STONE OR GRANITE CURB SETTERS
TOWNSHIPS OF RICHFORD, BERKSHIRE, NEWARK VALLEY,
OWEGO, TIOGA, BARTON AND NICHOLS FOOTNOTE A.
PAID HOLIDAYS: MEMORIAL DAY, INDEPENDENCE DAY,
LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY AND NEW
YEAR'S DAY. .......................................$ 36.16 25.60
LABORERS: HEAVY AND HIGHWAY GROUP 3: ALL ROCK OR
DRILLING MACHINE OPERATORS (EXCEPT QUARRY MASTER
AND SIMILAR TYPE), ACETYLENE TORCH OPERATORS AND
ASPHALT PAVER, POWERMAN TOWNSHIPS OF RICHFORD,
BERKSHIRE, NEWARK VALLEY, OWEGO, TIOGA, BARTON AND
NICHOLS FOOTNOTE A. PAID HOLIDAYS: MEMORIAL
DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY,
CHRISTMAS DAY AND NEW YEAR'S DAY....................$ 35.96 25.60
LABORERS: HEAVY AND HIGHWAY GROUP 2: BULL FLOAT,
CHAIN SAW, CONCRETE AGGREGATE BIN, CONCRETE
BOOTMAN, GIN BUGGY, HAND OR MACHINE VIBRATOR,
JACKHAMMER, MASON TENDER, MORTOR MIXER, PAVEMENT
BREAKER, HANDLERS OF ALL STEEL MESH, SMALL
GENERATORS FOR LABORERS' TOOLS, INSTALLATION OF
BRIDGE DRAINAGE PIPE, PIPELAYERS, VIBRATOR TYPE
ROLLERS, TAMPER, DRILL DOCTOR TAIL OR SCREW
OPERATOR ON ASPHALT PAVER, WATER PUMP OPERATOR (1
1/2' AND SINGLE DIAPHRAM), NOZZLE (ASPHALT GUNNITE,
SEEDING AND SANDBLASTING), LABORERS ON CHAIN LINK
FENCE ERECTION, ROCK SPLITTER AND POWER UNIT,
PUSHER TYPE CONCRETE SAW AND ALL OPERATOR (1 1/2'
AND SINGLE DEAPHRAM), NOZZLER (ASPHALT GUNNITE,
SEEDING AND SANDBLASTING), LABORERS ON CHAIN LINK
FENCE ERECTION, OTHER GAS ELECTRIC, OIL AND AIR
TOOL OPERATORS, WRECKING LABORERS TOWNSHIPS OF
RICHFORD, BERKSHIRE, NEWARK VALLEY, OWEGO, TIOGA,
BARTON AND NICHOLS FOOTNOTE A. PAID HOLIDAYS:
MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY,
THANKSGIVING DAY, CHRISTMAS DAY AND NEW YEAR'S DAY.
...................................................$ 35.76 25.60
LABORERS: HEAVY AND HIGHWAY GROUP 1: COMMON
LABORERS, FLAGGERS TOWNSHIPS OF RICHFORD,
BERKSHIRE, NEWARK VALLEY, OWEGO, TIOGA, BARTON AND
NICHOLS FOOTNOTE A. PAID HOLIDAYS: MEMORIAL
DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY,
CHRISTMAS DAY AND NEW YEAR'S DAY....................$ 35.56 25.60
LABORERS: GROUP 3 (BUILDING) ASBESTOS ABATEMENT AND
HAZARDOUS WASTE REMOVAL TOWNSHIPS OF RICHFORD,
BERKSHIRE, NEWARK VALLEY, OWEGO, TIOGA, BARTON AND
NICHOLS FOOTNOTE A. PAID HOLIDAYS: MEMORIAL
DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY,
CHRISTMAS DAY AND NEW YEAR'S DAY....................$ 28.50 22.46
LABORERS: GROUP 2 (BUILDING) MASONARY FORKLIFTS,
BOB CATS, ROCK DRILLING EQUIPMENT, BLASTERS
TOWNSHIPS OF RICHFORD, BERKSHIRE, NEWARK VALLEY,
OWEGO, TIOGA, BARTON AND NICHOLS FOOTNOTE A.
PAID HOLIDAYS: MEMORIAL DAY, INDEPENDENCE DAY,
LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY AND NEW
YEAR'S DAY..........................................$ 28.50 22.46
LABORERS: GROUP 1 (BUILDING) BASIC LABORER
TOWNSHIPS OF RICHFORD, BERKSHIRE, NEWARK VALLEY,
OWEGO, TIOGA, BARTON AND NICHOLS FOOTNOTE A.
PAID HOLIDAYS: MEMORIAL DAY, INDEPENDENCE DAY,
LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY AND NEW
YEAR'S DAY..........................................$ 26.50 22.46
----------------------------------------------------------------
LABO0785-019 07/01/2024
Rates Fringes
LABORER: HEAVY & HIGHWAY: GROUP 5: HAZARDOUS WASTE
REMOVAL REMAINDER OF COUNTY FOOTNOTE: A. PAID
HOLIDAYS: NEW YEAR'S DAY; MEMORIAL DAY;
INDEPENDENCE DAY; LABOR DAY; THANKSGIVING DAY;
CHRISTMAS DAY, PROVIDED THE EMPLOYEE WORKS THE
WORKING DAY BEFORE AND THE WORKING DAY AFTER THE
HOLIDAY.............................................$ 38.76 25.60
LABORER: HEAVY & HIGHWAY: GROUP 4: BLASTERS; FORM
SETTERS; STONE OR GRANITE CURB SETTERS REMAINDER
OF COUNTY FOOTNOTE: A. PAID HOLIDAYS: NEW
YEAR'S DAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR
DAY; THANKSGIVING DAY; CHRISTMAS DAY, PROVIDED THE
EMPLOYEE WORKS THE WORKING DAY BEFORE AND THE
WORKING DAY AFTER THE HOLIDAY.......................$ 35.76 25.60
LABORER: HEAVY & HIGHWAY: GROUP 3: ALL ROCK OR
DRILL MACHINE OPERATORS (EXCEPT QUARRY MASTER AND
SIMILAR TYPE); ACETYLENE TORCH OPERATOR; ASPHALT
RAKER; POWDERMAN REMAINDER OF COUNTY FOOTNOTE:
A. PAID HOLIDAYS: NEW YEAR'S DAY; MEMORIAL DAY;
INDEPENDENCE DAY; LABOR DAY; THANKSGIVING DAY;
CHRISTMAS DAY, PROVIDED THE EMPLOYEE WORKS THE
WORKING DAY BEFORE AND THE WORKING DAY AFTER THE
HOLIDAY.............................................$ 35.96 25.60
LABORER: HEAVY & HIGHWAY: GROUP 2: BULL FLOAT;
CHAIN SAW; CONCRETE AGGREGATE BIN; CONCRETE
BOOTMAN; GIN BUGGY; HAND OR MACHINE VIBRATOR;
JACKHAMMER; MASON TENDER; MORTAR MIXER; PAVEMENT
BREAKER; HANDLERS OF ALL STEEL MESH; SMALL
GENERATORS FOR LABORERS' TOOLS; INSTALLATION OF
BRIDGE DRAINAGE PIPE; PIPELAYERS; VIBRATOR TYPE
ROLLERS; TAMPERS; DRILL DOCTOR; TAIL OR SCREW
OPERATOR ON ASPHALT PAVER; WATER PUMP OPERATOR
(1-1/2"" AND SINGLE DIAPHRAM); NOZZLE (ASPHALT,
GUNNITE, SEEDING AND SANDBLASTING); LABORERS ON
CHAIN LINK FENCE ERECTION; ROCK SPLITTER AND POWER
UNIT; PUSHER TYPE CONCRETE SAW AND ALL OTHER GAS,
ELECTRIC, OIL AND AIR TOOL OPERATORS; WRECKING
LABORERS REMAINDER OF COUNTY FOOTNOTE: A.
PAID HOLIDAYS: NEW YEAR'S DAY; MEMORIAL DAY;
INDEPENDENCE DAY; LABOR DAY; THANKSGIVING DAY;
CHRISTMAS DAY, PROVIDED THE EMPLOYEE WORKS THE
WORKING DAY BEFORE AND THE WORKING DAY AFTER THE
HOLIDAY.............................................$ 36.16 25.60
LABORER: HEAVY & HIGHWAY: GROUP 1: LABORERS;
FLAGGERS; OUTBOARD AND HAND BOATS REMAINDER OF
COUNTY FOOTNOTE: A. PAID HOLIDAYS: NEW
YEAR'S DAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR
DAY; THANKSGIVING DAY; CHRISTMAS DAY, PROVIDED THE
EMPLOYEE WORKS THE WORKING DAY BEFORE AND THE
WORKING DAY AFTER THE HOLIDAY.......................$ 35.56 25.60
----------------------------------------------------------------
PAIN0004-032 05/01/2024
Rates Fringes
PAINTERS: (SWING SCAFFOLD, BOATSWAIN CHAIR, SPRAY,
SANDBLASTING, STEAM CLEANING, ACID AND HIGH
PRESSURE WATER, PAPERHANGERS, VINYL HANGERS, POWER
GRINDERS W/RESPIRATOR)..............................$ 29.10 23.83
PAINTERS: (STRUCTURAL STEEL (BUILDINGS) SPRAY WORK).$ 29.10 23.83
PAINTERS: (SPRAY WORK/STEEPLE JACK (OVER 100 FT))...$ 29.50 23.83
PAINTERS: (SPRAY EPOXY).............................$ 30.00 23.83
PAINTERS: (PAINTERS AND TAPERS).....................$ 29.93 23.83
PAINTERS: (EPOXY-BRUSH & ROLLER)....................$ 29.60 23.83
----------------------------------------------------------------
PAIN0677-003 05/01/2025
Rates Fringes
GLAZIER.............................................$ 30.00 31.95
----------------------------------------------------------------
PLUM0112-007 05/01/2025
Rates Fringes
PLUMBER, INCLUDING STEAMFITTING (TOWNSHIPS OF
NEWARK VALLEY AND OWEGO)...........................$ 44.91 33.31
----------------------------------------------------------------
PLUM0267-005 05/01/2019
Rates Fringes
PLUMBER, PIPEFITTER, STEAMFITTER: INCLUDING HVAC
WORK (THE TOWNS OF BARTON, BERKSHIRE, CANDOR,
NICHOLS, RICHFORD, SPENCER AND TIOGA)..............$ 35.51 24.57
----------------------------------------------------------------
ROOF0203-001 06/01/2023
Rates Fringes
ROOFER..............................................$ 30.50 19.84
----------------------------------------------------------------
SFNY0669-001 01/01/2026
Rates Fringes
SPRINKLER FITTER....................................$ 47.85 28.94
----------------------------------------------------------------
SHEE0112-004 05/01/2023
Rates Fringes
SHEET METAL WORKER..................................$ 35.94 20.89
----------------------------------------------------------------
TEAM0529-001 05/01/2025
Rates Fringes
TRUCK DRIVER GROUP 3 EUCLID-TYPE; OFF HIGHWAY
EQUIPMENT-BACK OR DOUBLE BOTTOM DUMP TRUCKS (OVER
20 TONS); STRADDLE TRUCKS; PUSHER; ARTICULATE
DUMPED TRUCKS; LOW BOY TRAILERS; SEMI TRAILERS;
ASPHALT DISTRIBUTORS; FUEL TRUCK FOOTNOTES: A.
PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY,
INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY,
CHRISTMAS DAY, PROVIDED THE EMPLOYEE WORKS THE
WORKING DAY BEFORE AND THE WORKING DAY AFTER THE
HOLIDAY.............................................$ 26.52 15.91
TRUCK DRIVER GROUP 2 DUMP TRUCK (OVER 10 YDS);
TRANSIT MIX (UNDER 5 YDS); TRANSIT MIX (OVER 5
YDS); FLAT OR STAKE BODY (TANDEM); A-FRAME/WINCH
TRUCKS; DRY BATCH TRUCK; TRUCK MOUNTED SWEEPER AND
VAC TRUCKS; DUMPSTER (TANDEM) FOOTNOTES: A.
PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY,
INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY,
CHRISTMAS DAY, PROVIDED THE EMPLOYEE WORKS THE
WORKING DAY BEFORE AND THE WORKING DAY AFTER THE
HOLIDAY.............................................$ 26.03 15.91
TRUCK DRIVER GROUP 1 FLAT BED TRUCK (SINGLE AXLE);
DUMP TRUCKS (UNDER 10 YDS SINGLE AXLE); STAKE BODY
TRUCK (SINGLE AXLE); DUMPSTER (SINGLE AXLE)
FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY,
MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY,
THANKSGIVING DAY, CHRISTMAS DAY, PROVIDED THE
EMPLOYEE WORKS THE WORKING DAY BEFORE AND THE
WORKING DAY AFTER THE HOLIDAY.......................$ 25.96 15.91
----------------------------------------------------------------
----------------------------------------------------------------------------------------------------
WELDERS - Receive rate prescribed for craft performing
operation to which welding is incidental.
================================================================
Note: Executive Order (EO) 13706, Establishing Paid Sick Leave
for Federal Contractors applies to all contracts subject to the
Davis-Bacon Act for which the contract is awarded (and any
solicitation was issued) on or after January 1, 2017. If this
contract is covered by the EO, the contractor must provide
employees with 1 hour of paid sick leave for every 30 hours
they work, up to 56 hours of paid sick leave each year.
Employees must be permitted to use paid sick leave for their
own illness, injury or other health-related needs, including
preventive care; to assist a family member (or person who is
like family to the employee) who is ill, injured, or has other
health-related needs, including preventive care; or for reasons
resulting from, or to assist a family member (or person who is
like family to the employee) who is a victim of, domestic
violence, sexual assault, or stalking. Additional information
on contractor requirements and worker protections under the EO
is available at
https://www.dol.gov/agencies/whd/government-contracts.
Note: Executive Order 13658 generally applies to contracts subject to
the Davis-Bacon Act that were awarded on or between January 1,
2015 and January 29, 2022, and that have not been renewed or
extended on or after January 30, 2022. Executive Order 13658 does
not apply to contracts subject only to the Davis-Bacon Related Acts
regardless of when they were awarded. If a contract is subject to
Executive Order 13658, the contractor must pay all covered workers at
least $13.65 per hour (or the applicable wage rate listed on this wage
determination, if it is higher) for all hours spent performing on the
contract from May 11, 2026, through December 31, 2026. The applicable
Executive Order minimum wage rate will be adjusted annually.
Additional information on contractor requirements and worker
protections under Executive Order 13658 is available at
www.dol.gov/whd/govcontracts.
Unlisted classifications needed for work not included within
the scope of the classifications listed may be added after
award only as provided in the labor standards contract clauses
(29CFR 5.5 (a) (1) (iii)).
----------------------------------------------------------------
The body of each wage determination lists the classifications
and wage rates that have been found to be prevailing for the
type(s) of construction and geographic area covered by the wage
determination. The classifications are listed in alphabetical
order under rate identifiers indicating whether the particular
rate is a union rate (current union negotiated rate), a survey
rate, a weighted union average rate, a state adopted rate, or a
supplemental classification rate.
Union Rate Identifiers
A four-letter identifier beginning with characters other than
""""SU"""", """"UAVG"""", ?SA?, or ?SC? denotes that a union rate was
prevailing for that classification in the survey. Example:
PLUM0198-005 07/01/2024. PLUM is an identifier of the union
whose collectively bargained rate prevailed in the survey for
this classification, which in this example would be Plumbers.
0198 indicates the local union number or district council
number where applicable, i.e., Plumbers Local 0198. The next
number, 005 in the example, is an internal number used in
processing the wage determination. The date, 07/01/2024 in the
example, is the effective date of the most current negotiated
rate.
Union prevailing wage rates are updated to reflect all changes
over time that are reported to WHD in the rates
in the collective bargaining agreement (CBA) governing the
classification.
Union Average Rate Identifiers
The UAVG identifier indicates that no single rate prevailed for
those classifications, but that 100% of the data reported for
the classifications reflected union rates. EXAMPLE:
UAVG-OH-0010 01/01/2024. UAVG indicates that the rate is a
weighted union average rate. OH indicates the State of Ohio.
The next number, 0010 in the example, is an internal number
used in producing the wage determination. The date, 01/01/2024
in the example, indicates the date the wage determination was
updated to reflect the most current union average rate.
A UAVG rate will be updated once a year, usually in January, to
reflect a weighted average of the current rates in the
collective bargaining agreements on which the rate is based.
Survey Rate Identifiers
The """"SU"""" identifier indicates that either a single non-union
rate prevailed (as defined in 29 CFR 1.2) for this
classification in the survey or that the rate was derived by
computing a weighted average rate based on all the rates
reported in the survey for that classification. As a weighted
average rate includes all rates reported in the survey, it may
include both union and non-union rates. Example: SUFL2022-007
6/27/2024. SU indicates the rate is a single non-union
prevailing rate or a weighted average of survey data for that
classification. FL indicates the State of Florida. 2022 is the
year of the survey on which these classifications and rates are
based. The next number, 007 in the example, is an internal
number used in producing the wage determination. The date,
6/27/2024 in the example, indicates the survey completion date
for the classifications and rates under that identifier.
?SU? wage rates typically remain in effect until a new survey
is conducted. However, the Wage and Hour Division (WHD) has the
discretion to update such rates under 29 CFR 1.6(c)(1).
State Adopted Rate Identifiers
The """"SA"""" identifier indicates that the classifications and
prevailing wage rates set by a state (or local) government were
adopted under 29 C.F.R 1.3(g)-(h). Example: SAME2023-007
01/03/2024. SA reflects that the rates are state adopted. ME
refers to the State of Maine. 2023 is the year during which the
state completed the survey on which the listed classifications
and rates are based. The next number, 007 in the example, is an
internal number used in producing the wage determination.
The date, 01/03/2024 in the example, reflects the date on which
the classifications and rates under the ?SA? identifier took
effect under state law in the state from which the rates were
adopted.
-----------------------------------------------------------
WAGE DETERMINATION APPEALS PROCESS
1) Has there been an initial decision in the matter? This can
be:
a) a survey underlying a wage determination
b) an existing published wage determination
c) an initial WHD letter setting forth a position on
a wage determination matter
d) an initial conformance (additional classification
and rate) determination
On survey related matters, initial contact, including requests
for summaries of surveys, should be directed to the WHD Branch
of Wage Surveys. Requests can be submitted via email to
davisbaconinfo@dol.gov or by mail to:
Branch of Wage Surveys
Wage and Hour Division
U.S. Department of Labor
200 Constitution Avenue, N.W.
Washington, DC 20210
Regarding any other wage determination matter such as
conformance decisions, requests for initial decisions should be
directed to the WHD Branch of Construction Wage Determinations.
Requests can be submitted via email to BCWD-Office@dol.gov or
by mail to:
Branch of Construction Wage Determinations
Wage and Hour Division
U.S. Department of Labor
200 Constitution Avenue, N.W.
Washington, DC 20210
2) If an initial decision has been issued, then any interested
party (those affected by the action) that disagrees with the
decision can request review and reconsideration from the Wage
and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7).
Requests for review and reconsideration can be submitted via
email to dba.reconsideration@dol.gov or by mail to:
Wage and Hour Administrator
U.S. Department of Labor
200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the
interested party's position and any information (wage payment
data, project description, area practice material, etc.) that
the requestor considers relevant to the issue.
3) If the decision of the Administrator is not favorable, an
interested party may appeal directly to the Administrative
Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board
U.S. Department of Labor
200 Constitution Avenue, N.W.
Washington, DC 20210.
================================================================
END OF GENERAL DECISION"