Roofer prevailing wage rates in New Jersey
Federal Davis-Bacon rates published in 38 active determinations, 2026
- Active federal Davis-Bacon determinations for New Jersey publish 73 roofer classification rates, across 38 determinations covering 21 counties.
- Those published base rates run from $30.21 to $50.25 an hour before fringe benefits. Which one applies to a job depends on its county, its construction type and the determination written into the contract.
- Construction types covered: Building, Residential.
- Last determination revision affecting roofer rates in New Jersey: .
This page collects every classification in New Jersey's active federal determinations that is a form of roofer work (built-up, single-ply and shingle roofing) and shows the rate published for it. Determinations name a classification the way the underlying union agreement or wage survey named it, so the wording varies between them; the rate and the fringe are reproduced exactly as published.
Published rates by determination
NJ20260005 rev 1 · Residential · Atlantic
| Classification as published | Base rate | Fringes | Rate schedule |
|---|---|---|---|
| ROOFER (ALL TYPES) | $34.35 | 21.75 | ROOF0030-019 collectively bargained (union) rate |
Official document: NJ20260005 on SAM.gov.
NJ20260006 rev 1 · Residential · Bergen
| Classification as published | Base rate | Fringes | Rate schedule |
|---|---|---|---|
| ROOFER (INCLUDES ALL TYPES OF ROOFS) | $45.40 | 29.14 | ROOF0010-003 collectively bargained (union) rate |
Official document: NJ20260006 on SAM.gov.
NJ20260007 rev 2 · Residential · Burlington
| Classification as published | Base rate | Fringes | Rate schedule |
|---|---|---|---|
| ROOFER ( ALL TYPES) | $34.35 | 21.75 | ROOF0030-019 collectively bargained (union) rate |
Official document: NJ20260007 on SAM.gov.
NJ20260008 rev 1 · Residential · Camden
| Classification as published | Base rate | Fringes | Rate schedule |
|---|---|---|---|
| ROOFER (ALL TYPES) | $34.35 | 21.75 | ROOF0030-019 collectively bargained (union) rate |
Official document: NJ20260008 on SAM.gov.
NJ20260009 rev 1 · Residential · Cape May
| Classification as published | Base rate | Fringes | Rate schedule |
|---|---|---|---|
| ROOFER (ALL TYPES) | $34.35 | 21.75 | ROOF0030-019 collectively bargained (union) rate |
Official document: NJ20260009 on SAM.gov.
NJ20260010 rev 1 · Residential · Cumberland
| Classification as published | Base rate | Fringes | Rate schedule |
|---|---|---|---|
| ROOFER (ALL TYPES) | $34.35 | 21.75 | ROOF0030-019 collectively bargained (union) rate |
Official document: NJ20260010 on SAM.gov.
NJ20260011 rev 1 · Residential · Essex
| Classification as published | Base rate | Fringes | Rate schedule |
|---|---|---|---|
| ROOFER (INCLUDES ALL TYPES OF ROOFS) | $44.52 | 32.25 | ROOF0004-007 collectively bargained (union) rate |
Official document: NJ20260011 on SAM.gov.
NJ20260012 rev 1 · Residential · Gloucester
| Classification as published | Base rate | Fringes | Rate schedule |
|---|---|---|---|
| ROOFER (ALL TYPES) | $34.35 | 21.75 | ROOF0030-019 collectively bargained (union) rate |
Official document: NJ20260012 on SAM.gov.
NJ20260013 rev 1 · Residential · Hudson
| Classification as published | Base rate | Fringes | Rate schedule |
|---|---|---|---|
| ROOFER (INCLUDES ALL TYPES OF ROOFS) REMAINDER OF AREA | $44.52 | 35.25 | ROOF0004-001 collectively bargained (union) rate |
| ROOFER (ALL TYPES) (HUDSON COUNTY (EAST OF THE HACKENSACK RIVER) | $50.25 | 32.62 | ROOF0008-001 collectively bargained (union) rate |
Official document: NJ20260013 on SAM.gov.
NJ20260014 rev 1 · Residential · Mercer
| Classification as published | Base rate | Fringes | Rate schedule |
|---|---|---|---|
| ROOFER (ALL TYPES) | $34.35 | 21.75 | ROOF0030-019 collectively bargained (union) rate |
Official document: NJ20260014 on SAM.gov.
NJ20260015 rev 1 · Residential · Monmouth
| Classification as published | Base rate | Fringes | Rate schedule |
|---|---|---|---|
| ROOFER (INCLUDES ALL TYPES OF ROOFS) (MONMOUTH COUNTY (EAST OF ROUTE #571)) | $44.52 | 32.25 | ROOF0004-006 collectively bargained (union) rate |
| ROOFER (ALL TYPES) (MONMOUTH COUNTY (WEST OF ROUTE #571)) | $34.35 | 21.75 | ROOF0030-023 collectively bargained (union) rate |
Official document: NJ20260015 on SAM.gov.
NJ20260016 rev 1 · Residential · Morris
| Classification as published | Base rate | Fringes | Rate schedule |
|---|---|---|---|
| ROOFER (INCLUDES ALL TYPES OF ROOFS) | $44.52 | 32.25 | ROOF0004-007 collectively bargained (union) rate |
Official document: NJ20260016 on SAM.gov.
NJ20260017 rev 1 · Residential · Ocean
| Classification as published | Base rate | Fringes | Rate schedule |
|---|---|---|---|
| ROOFER (ALL TYPES) | $34.35 | 21.75 | ROOF0030-019 collectively bargained (union) rate |
Official document: NJ20260017 on SAM.gov.
NJ20260018 rev 1 · Residential · Passaic
| Classification as published | Base rate | Fringes | Rate schedule |
|---|---|---|---|
| ROOFER (INCLUDES ALL TYPES OF ROOFS) | $45.40 | 29.14 | ROOF0010-003 collectively bargained (union) rate |
Official document: NJ20260018 on SAM.gov.
NJ20260019 rev 1 · Residential · Salem
| Classification as published | Base rate | Fringes | Rate schedule |
|---|---|---|---|
| ROOFER (ALL TYPES) | $34.35 | 21.75 | ROOF0030-019 collectively bargained (union) rate |
Official document: NJ20260019 on SAM.gov.
NJ20260020 rev 1 · Residential · Somerset
| Classification as published | Base rate | Fringes | Rate schedule |
|---|---|---|---|
| ROOFER (ALL TYPES) (SOMERSET COUNTY (north of a line drawn from the Mercer/Somerset county line along Route #206 north to Route #514; then, west along Route #514 to the Hunterdon/S | $44.52 | 32.25 | ROOF0004-004 collectively bargained (union) rate |
| ROOFER (ALL TYPES) (SOMERSET COUNTY (south of a line drawn from the Mercer/Somerset county line north along Route #206 to Route #514; then, west along Route #514 to the Hunterdon/S | $34.35 | 21.75 | ROOF0030-024 collectively bargained (union) rate |
Official document: NJ20260020 on SAM.gov.
NJ20260021 rev 1 · Residential · Sussex
| Classification as published | Base rate | Fringes | Rate schedule |
|---|---|---|---|
| ROOFER (INCLUDES ALL TYPES OF ROOFS) | $44.52 | 32.25 | ROOF0004-007 collectively bargained (union) rate |
Official document: NJ20260021 on SAM.gov.
NJ20260022 rev 1 · Residential · Union
| Classification as published | Base rate | Fringes | Rate schedule |
|---|---|---|---|
| ROOFER (INCLUDES ALL TYPES OF ROOFS) | $44.52 | 32.25 | ROOF0004-007 collectively bargained (union) rate |
Official document: NJ20260022 on SAM.gov.
NJ20260023 rev 1 · Residential · Warren
| Classification as published | Base rate | Fringes | Rate schedule |
|---|---|---|---|
| ROOFER (INCLUDES ALL TYPES OF ROOFS) | $44.52 | 32.25 | ROOF0004-007 collectively bargained (union) rate |
Official document: NJ20260023 on SAM.gov.
NJ20260024 rev 2 · Residential · Hunterdon, Middlesex
| Classification as published | Base rate | Fringes | Rate schedule |
|---|---|---|---|
| ROOFER (INCLUDES ALL TYPES OF ROOFS) (MIDDLESEX COUNTY (NORTH AND EAST OF ROUTE #18)) | $44.52 | 32.25 | ROOF0004-008 collectively bargained (union) rate |
| ROOFER (ALL TYPES) (MIDDLESEX COUNTY (SOUTH AND WEST OF ROUTE #18)) | $34.35 | 21.75 | ROOF0030-018 collectively bargained (union) rate |
| ROOFER (ALL TYPES) (HUNTERDON COUNTY) | $34.35 | 21.75 | ROOF0030-036 collectively bargained (union) rate |
Official document: NJ20260024 on SAM.gov.
NJ20260025 rev 1 · Building · Atlantic
| Classification as published | Base rate | Fringes | Rate schedule |
|---|---|---|---|
| ROOFER: Mopper, and operator of felt-laying machine: $.50 per hour Work applying roofing material, on any new construction job, on those days on which a felt-laying machine or slag | $35.95 | 21.85 | ROOF0030-027 collectively bargained (union) rate |
| ROOFER: SLATE AND Mopper, and operator of felt-laying machine: $.50 per hour Work applying roofing material, on any new construction job, on those days on which a felt-laying machi | $38.95 | 21.85 | ROOF0030-027 collectively bargained (union) rate |
| ROOFER: ALL OTHER Mopper, and operator of felt-laying machine: $.50 per hour Work applying roofing material, on any new construction job, on those days on which a felt-laying machi | $46.03 | 34.27 | ROOF0030-027 collectively bargained (union) rate |
Official document: NJ20260025 on SAM.gov.
NJ20260026 rev 1 · Building · Bergen
| Classification as published | Base rate | Fringes | Rate schedule |
|---|---|---|---|
| ROOFER (INCLUDES ALL TYPES OF ROOFS) | $45.40 | 29.14 | ROOF0010-003 collectively bargained (union) rate |
Official document: NJ20260026 on SAM.gov.
NJ20260027 rev 2 · Building · Burlington
| Classification as published | Base rate | Fringes | Rate schedule |
|---|---|---|---|
| ROOFER: Mopper, and operator of felt-laying machine: $.50 per hour Work applying roofing material, on any new construction job, on those days on which a felt-laying machine or slag | $35.95 | 21.85 | ROOF0030-027 collectively bargained (union) rate |
| ROOFER: SLATE AND Mopper, and operator of felt-laying machine: $.50 per hour Work applying roofing material, on any new construction job, on those days on which a felt-laying machi | $38.95 | 21.85 | ROOF0030-027 collectively bargained (union) rate |
| ROOFER: ALL OTHER Mopper, and operator of felt-laying machine: $.50 per hour Work applying roofing material, on any new construction job, on those days on which a felt-laying machi | $46.03 | 34.27 | ROOF0030-027 collectively bargained (union) rate |
Official document: NJ20260027 on SAM.gov.
NJ20260028 rev 1 · Building · Camden
| Classification as published | Base rate | Fringes | Rate schedule |
|---|---|---|---|
| ROOFER: Mopper, and operator of felt-laying machine: $.50 per hour Work applying roofing material, on any new construction job, on those days on which a felt-laying machine or slag | $35.95 | 21.85 | ROOF0030-027 collectively bargained (union) rate |
| ROOFER: SLATE AND Mopper, and operator of felt-laying machine: $.50 per hour Work applying roofing material, on any new construction job, on those days on which a felt-laying machi | $38.95 | 21.85 | ROOF0030-027 collectively bargained (union) rate |
| ROOFER: ALL OTHER Mopper, and operator of felt-laying machine: $.50 per hour Work applying roofing material, on any new construction job, on those days on which a felt-laying machi | $46.03 | 34.27 | ROOF0030-027 collectively bargained (union) rate |
Official document: NJ20260028 on SAM.gov.
NJ20260029 rev 1 · Building · Cape May
| Classification as published | Base rate | Fringes | Rate schedule |
|---|---|---|---|
| ROOFER: Mopper, and operator of felt-laying machine: $.50 per hour Work applying roofing material, on any new construction job, on those days on which a felt-laying machine or slag | $35.95 | 21.85 | ROOF0030-027 collectively bargained (union) rate |
| ROOFER: SLATE AND Mopper, and operator of felt-laying machine: $.50 per hour Work applying roofing material, on any new construction job, on those days on which a felt-laying machi | $38.95 | 21.85 | ROOF0030-027 collectively bargained (union) rate |
| ROOFER: ALL OTHER Mopper, and operator of felt-laying machine: $.50 per hour Work applying roofing material, on any new construction job, on those days on which a felt-laying machi | $46.03 | 34.27 | ROOF0030-027 collectively bargained (union) rate |
Official document: NJ20260029 on SAM.gov.
NJ20260030 rev 1 · Building · Cumberland
| Classification as published | Base rate | Fringes | Rate schedule |
|---|---|---|---|
| ROOFER: Mopper, and operator of felt-laying machine: $.50 per hour Work applying roofing material, on any new construction job, on those days on which a felt-laying machine or slag | $35.95 | 21.85 | ROOF0030-027 collectively bargained (union) rate |
| ROOFER: SLATE AND Mopper, and operator of felt-laying machine: $.50 per hour Work applying roofing material, on any new construction job, on those days on which a felt-laying machi | $38.95 | 21.85 | ROOF0030-027 collectively bargained (union) rate |
| ROOFER: ALL OTHER Mopper, and operator of felt-laying machine: $.50 per hour Work applying roofing material, on any new construction job, on those days on which a felt-laying machi | $46.03 | 34.27 | ROOF0030-027 collectively bargained (union) rate |
Official document: NJ20260030 on SAM.gov.
NJ20260031 rev 1 · Building · Essex
| Classification as published | Base rate | Fringes | Rate schedule |
|---|---|---|---|
| ROOFER (SHINGLES, SHAKE AND TILE) | $44.52 | 32.25 | ROOF0004-011 collectively bargained (union) rate |
| ROOFER, EXCLUDES SHAKE & SHINGLE, AND TILE ROOFS | $30.21 | 15.25 | SUNJ2004-007 DOL wage survey rate |
Official document: NJ20260031 on SAM.gov.
NJ20260032 rev 1 · Building · Gloucester
| Classification as published | Base rate | Fringes | Rate schedule |
|---|---|---|---|
| ROOFER: Mopper, and operator of felt-laying machine: $.50 per hour Work applying roofing material, on any new construction job, on those days on which a felt-laying machine or slag | $35.95 | 21.85 | ROOF0030-027 collectively bargained (union) rate |
| ROOFER: SLATE AND Mopper, and operator of felt-laying machine: $.50 per hour Work applying roofing material, on any new construction job, on those days on which a felt-laying machi | $38.95 | 21.85 | ROOF0030-027 collectively bargained (union) rate |
| ROOFER: ALL OTHER Mopper, and operator of felt-laying machine: $.50 per hour Work applying roofing material, on any new construction job, on those days on which a felt-laying machi | $46.03 | 34.27 | ROOF0030-027 collectively bargained (union) rate |
Official document: NJ20260032 on SAM.gov.
NJ20260033 rev 1 · Building · Hudson
| Classification as published | Base rate | Fringes | Rate schedule |
|---|---|---|---|
| ROOFER (INCLUDES ALL TYPES OF ROOFERS) | $44.52 | 32.25 | ROOF0004-007 collectively bargained (union) rate |
| ROOFER (ALL TYPES) (HUDSON COUNTY (EAST OF THE HACKENSACK RIVER)) | $50.25 | 39.62 | ROOF0008-005 collectively bargained (union) rate |
Official document: NJ20260033 on SAM.gov.
NJ20260034 rev 2 · Building · Hunterdon
| Classification as published | Base rate | Fringes | Rate schedule |
|---|---|---|---|
| ROOFER: ALL OTHER Mopper, and operator of felt-laying machine: $.50 per hour Work applying roofing material, on any new construction job, on those days on which a felt-laying machi | $46.03 | 34.27 | ROOF0030-028 collectively bargained (union) rate |
| ROOFER: SLATE AND Mopper, and operator of felt-laying machine: $.50 per hour Work applying roofing material, on any new construction job, on those days on which a felt-laying machi | $38.95 | 21.85 | ROOF0030-028 collectively bargained (union) rate |
| ROOFER: Mopper, and operator of felt-laying machine: $.50 per hour Work applying roofing material, on any new construction job, on those days on which a felt-laying machine or slag | $35.95 | 21.85 | ROOF0030-028 collectively bargained (union) rate |
Official document: NJ20260034 on SAM.gov.
NJ20260035 rev 2 · Building · Mercer
| Classification as published | Base rate | Fringes | Rate schedule |
|---|---|---|---|
| ROOFER: Mopper, and operator of felt-laying machine: $.50 per hour Work applying roofing material, on any new construction job, on those days on which a felt-laying machine or slag | $35.95 | 21.85 | ROOF0030-027 collectively bargained (union) rate |
| ROOFER: SLATE AND Mopper, and operator of felt-laying machine: $.50 per hour Work applying roofing material, on any new construction job, on those days on which a felt-laying machi | $38.95 | 21.85 | ROOF0030-027 collectively bargained (union) rate |
| ROOFER: ALL OTHER Mopper, and operator of felt-laying machine: $.50 per hour Work applying roofing material, on any new construction job, on those days on which a felt-laying machi | $46.03 | 34.27 | ROOF0030-027 collectively bargained (union) rate |
Official document: NJ20260035 on SAM.gov.
NJ20260036 rev 1 · Building · Middlesex
| Classification as published | Base rate | Fringes | Rate schedule |
|---|---|---|---|
| ROOFER (INCLUDES ALL TYPES OF ROOFERS) (MIDDLESEX COUNTY (north and east of Route #18)) | $44.52 | 32.25 | ROOF0004-008 collectively bargained (union) rate |
| ROOFER: SLATE AND TILE (MIDDLESEX COUNTY (SOUTH AND WEST OF ROUTE #18)) MOPPER, AND OPERATOR OF FELT-LAYING MACHINE: $.50 PER HOUR ADDITIONAL. WORK APPLYING ROOFING MATERIAL, ON AN | $38.95 | 21.85 | ROOF0030-030 collectively bargained (union) rate |
| ROOFER: SHINGLES (MIDDLESEX COUNTY (SOUTH AND WEST OF ROUTE #18)) MOPPER, AND OPERATOR OF FELT-LAYING MACHINE: $.50 PER HOUR ADDITIONAL. WORK APPLYING ROOFING MATERIAL, ON ANY NEW | $35.95 | 21.85 | ROOF0030-030 collectively bargained (union) rate |
| ROOFER: ALL OTHER WORK (MIDDLESEX COUNTY (SOUTH AND WEST OF ROUTE #18)) MOPPER, AND OPERATOR OF FELT-LAYING MACHINE: $.50 PER HOUR ADDITIONAL. WORK APPLYING ROOFING MATERIAL, ON AN | $46.03 | 34.27 | ROOF0030-030 collectively bargained (union) rate |
Official document: NJ20260036 on SAM.gov.
NJ20260037 rev 1 · Building · Monmouth
| Classification as published | Base rate | Fringes | Rate schedule |
|---|---|---|---|
| ROOFER (MONMOUTH COUNTY (EAST OF ROUTE #571) Mop person: $.30 per hour additional. Work on a job where pitch is being applied: $.50 per hour additional | $44.52 | 32.25 | ROOF0004-009 collectively bargained (union) rate |
| ROOFER, SLATE AND TILE (MONMOUTH COUNTY (WEST OF ROUTE #571)) MOPPER, AND OPERATOR OF FELT-LAYING MACHINE: $.50 PER HOUR ADDITIONAL. WORK APPLYING ROOFING MATERIAL, ON ANY NEW CONS | $38.95 | 21.85 | ROOF0030-026 collectively bargained (union) rate |
| ROOFER, SHINGLES (MONMOUTH COUNTY (WEST OF ROUTE #571)) MOPPER, AND OPERATOR OF FELT-LAYING MACHINE: $.50 PER HOUR ADDITIONAL. WORK APPLYING ROOFING MATERIAL, ON ANY NEW CONSTRUCTI | $35.95 | 21.85 | ROOF0030-026 collectively bargained (union) rate |
| ROOFER, ALL OTHER WORK (MONMOUTH COUNTY (WEST OF ROUTE #571)) MOPPER, AND OPERATOR OF FELT-LAYING MACHINE: $.50 PER HOUR ADDITIONAL. WORK APPLYING ROOFING MATERIAL, ON ANY NEW CONS | $46.03 | 34.27 | ROOF0030-026 collectively bargained (union) rate |
Official document: NJ20260037 on SAM.gov.
NJ20260038 rev 1 · Building · Morris
| Classification as published | Base rate | Fringes | Rate schedule |
|---|---|---|---|
| ROOFER (INCLUDES ALL TYPES OF ROOFERS) | $44.52 | 32.25 | ROOF0004-007 collectively bargained (union) rate |
Official document: NJ20260038 on SAM.gov.
NJ20260039 rev 1 · Building · Ocean
| Classification as published | Base rate | Fringes | Rate schedule |
|---|---|---|---|
| ROOFER: SHINGLES MOPPER, AND OPERATOR OF FELT-LAYING MACHINE: $.50 PER HOUR ADDITIONAL. WORK APPLYING ROOFING MATERIAL, ON ANY NEW CONSTRUCTION JOB, ON THOSE DAYS ON WHICH A FELT-L | $35.95 | 21.85 | ROOF0030-027 collectively bargained (union) rate |
| ROOFER: SLATE AND TILE MOPPER, AND OPERATOR OF FELT-LAYING MACHINE: $.50 PER HOUR ADDITIONAL. WORK APPLYING ROOFING MATERIAL, ON ANY NEW CONSTRUCTION JOB, ON THOSE DAYS ON WHICH A | $38.95 | 21.85 | ROOF0030-027 collectively bargained (union) rate |
| ROOFER: ALL OTHER WORK MOPPER, AND OPERATOR OF FELT-LAYING MACHINE: $.50 PER HOUR ADDITIONAL. WORK APPLYING ROOFING MATERIAL, ON ANY NEW CONSTRUCTION JOB, ON THOSE DAYS ON WHICH A | $46.03 | 34.27 | ROOF0030-027 collectively bargained (union) rate |
Official document: NJ20260039 on SAM.gov.
NJ20260040 rev 2 · Building · Passaic
| Classification as published | Base rate | Fringes | Rate schedule |
|---|---|---|---|
| ROOFER: INCLUDES ALL TYPES OF ROOFS | $45.40 | 29.14 | ROOF0010-003 collectively bargained (union) rate |
Official document: NJ20260040 on SAM.gov.
NJ20260041 rev 2 · Building · Salem
| Classification as published | Base rate | Fringes | Rate schedule |
|---|---|---|---|
| ROOFER: SHINGLES (MOPPER, AND OPERATOR OF FELT-LAYING MACHINE: $0.50 PER HOUR ADDITIONAL.) WORK APPLYING ROOFING MATERIAL, ON ANY NEW CONSTRUCTION JOB, ON THOSE DAYS ON WHICH A FEL | $35.95 | 21.85 | ROOF0030-027 collectively bargained (union) rate |
| ROOFER: SLATE AND TILE (MOPPER, AND OPERATOR OF FELT-LAYING MACHINE: $0.50 PER HOUR ADDITIONAL.) WORK APPLYING ROOFING MATERIAL, ON ANY NEW CONSTRUCTION JOB, ON THOSE DAYS ON WHICH | $38.95 | 21.85 | ROOF0030-027 collectively bargained (union) rate |
| ROOFER: ALL OTHER WORK (MOPPER, AND OPERATOR OF FELT-LAYING MACHINE: $0.50 PER HOUR ADDITIONAL.) WORK APPLYING ROOFING MATERIAL, ON ANY NEW CONSTRUCTION JOB, ON THOSE DAYS ON WHICH | $46.03 | 34.27 | ROOF0030-027 collectively bargained (union) rate |
Official document: NJ20260041 on SAM.gov.
NJ20260042 rev 2 · Building · Somerset
| Classification as published | Base rate | Fringes | Rate schedule |
|---|---|---|---|
| ROOFER: SLATE AND TILE (SOMERSET COUNTY (SOUTH OF A LINE DRAWN FROM THE MERCER/SOMERSET COUNTY LINE NORTH ALONG ROUTE #206 TO ROUTE #514; THEN, WEST ALONG ROUTE #514 TO THE HUNTERD | $38.95 | 21.85 | ROOF0030-029 collectively bargained (union) rate |
| ROOFER: SHINGLES (SOMERSET COUNTY (SOUTH OF A LINE DRAWN FROM THE MERCER/SOMERSET COUNTY LINE NORTH ALONG ROUTE #206 TO ROUTE #514; THEN, WEST ALONG ROUTE #514 TO THE HUNTERDON/SOM | $35.95 | 21.85 | ROOF0030-029 collectively bargained (union) rate |
| ROOFER: ALL OTHER WORK (SOMERSET COUNTY (SOUTH OF A LINE DRAWN FROM THE MERCER/SOMERSET COUNTY LINE NORTH ALONG ROUTE #206 TO ROUTE #514; THEN, WEST ALONG ROUTE #514 TO THE HUNTERD | $46.03 | 34.27 | ROOF0030-029 collectively bargained (union) rate |
Official document: NJ20260042 on SAM.gov.
Where to go next
Roofer rates in every state · New Jersey prevailing wage and state law · New Jersey determinations by county · pay calculator
Other trades in New Jersey
Electrician · Plumber · Pipefitter · Sheet Metal Worker · Carpenter · Construction Laborer · Heavy Equipment Operator · Truck Driver · Ironworker · Cement Mason / Concrete Finisher · Bricklayer / Mason · Painter · Drywall Finisher / Taper · Plasterer · Glazier · Insulator (Heat & Frost) · Millwright · Elevator Constructor · Sprinkler Fitter · Piledriver · Tile Setter · Tile Finisher · Floor Layer · Line Constructor / Lineman